Kriegers Flak Offshore development in three different countries lessons learned and progress expecte - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Kriegers Flak Offshore development in three different countries lessons learned and progress expecte

Description:

Despite the fact that it is one area, the crucial points were different in every ... Proceeding with Kriegers Flak I (Germany) as one of the most promising projects ... – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 16
Provided by: haukea
Category:

less

Transcript and Presenter's Notes

Title: Kriegers Flak Offshore development in three different countries lessons learned and progress expecte


1
Kriegers Flak Offshore development in three
different countries - lessons learned and
progress expected

2
  • Construction and financing of RE-projects (1.4
    billion -invest, 1,000 MW)
  • Development of and sponsorship in international
    RE-projects
  • Development of offshore wind farms

3
WPD Offshore
  • Development of 10 projects in several European
    countries, inter alia
  • Kriegers Flak
  • Baltic I
  • Finngrunden (Sweden, 1000 MW)
  • He Dreiht (German North Sea, 595 MW)
  • Hochseewindpark Nordsee (German North Sea, 400
    MW)
  • Pipeline of more than 5000 MW

4
Baltic Sea- Baltic I- Kriegers Flak IIIIII-
218012891 320 turbines (up to 1600 MW)
together Europes largest advanced project area
in terms of area, turbines and capacity
developed by WPD since 2000 (Kriegers Flak II
Sweden sold to Vattenfall in 2005)
5
Baltic I
  • 21 Turbines up to 78 MW
  • Wind speed 8.7 m/s at 95m
  • Water depth 16-19 m
  • All permissions granted (August 2006)
  • Planned start of operation 2009

6
Baltic I - Permissions
  • Local proceedings as the project is in
    territorial waters
  • General planning permission (Raumordnungsverfahren
    ) granted February 2005
  • Permission for wind farm due to Federal Pollution
    Act (BImSchG) March 2006
  • Permission for cable due to Federal Pollution Act
    (BImSchG) August 2006
  • All needed permissions are granted

6
16.12.2009
7
Kriegers Flak I
  • 80 turbines ( 400 MW)
  • Wind speed 9.0 - 9.6 m/s at 100m
  • Water depth 20-35m
  • All permissions granted (April 2005)

8
Measuring mast Fino II
  • Unique in the Baltic Sea
  • Supported by the Federal and Local Government,
    Germanischer Loyd and Offshore Ostsee Wind AG
  • Foundation errected October 06

8
16.12.2009
9
Grid connection Kriegers Flak I Baltic I
Internal grid
Connection with Baltic I and Bentwisch
10
Kriegers Flak II
  • Located in the Swedish economic zone
  • Project developed by Sweden Offshore Wind AB
    (founded by WPD and WIND-Projekt in 2002)
  • Sweden Offshore sold to Vattenfall AB in May 2005
  • Permission for 128 x 5 MW granted 29 June 2006
  • Further development untill 2007 by WPD
    Scandinavia AB

11
Kriegers Flak III
  • Open Door Application filed in August 2006
  • 91 turbines
  • 3,6 to 5 MW type
  • 15 to 20 m deep
  • 9,5 m/s at 100m
  • 25km to Møn
  • ca. 3km to Kriegers Flak II
  • ca. 4km to Kriegers Flak I
  • Proposal by working group for future windfarms in
    Denmark Kriegers Flak included with 4 proposals
    200 MW each

12
Experiences
  • Neighbouring national authorithies want to be
    informed, but do not influence the neighbouring
    project
  • Despite the fact that it is one area, the crucial
    points were different in every country
  • Germany shipping safety
  • Sweden fishermen military
  • Denmark national ressources (sand)
  • Possibility of transnational transmission network
    attracts utilities (Vattenfall Baltic Wind Link)
  • For Kriegers Flak, still some technical issues
    regarding the foundations need to be solved
    strong advantages to have a smaller project to
    start with (Baltic I)

13
Progress expected
  • Regarding wind speed, Kriegers Flak seems to be
    the most attractive area in the Baltic Sea FINO
    II measurements will prove
  • Technically Kriegers Flak is less challenging
    than a lot of North Sea projects
  • WPDs next steps develop, finance, construct and
    operate
  • Baltic I (Germany) - in 2007 secure
    windturbines and project finance
  • - in 2008 start preparation of construction
    - in 2009 construction of Baltic I, start of
    operation

14
WPD offshore strategy
  • Likewise onshore, WPDs aim is to finance,
    construct and operate offshore windfarms
  • Building and operating Baltic I as the first
    offshore project in Germany
  • Proceeding with Kriegers Flak I (Germany) as one
    of the most promising projects
  • Developing a long-term project pipeline towards
    Europe

14
15
Dr. Gernot Blanke Member of the board WPD
AG Kurfürstenallee 23a 28211 Bremen Germany Tel.
49 (0) 421 168 66 10 Fax 49 (0) 421 -
168 66 66 www.wpd.de info_at_wpd.de
Write a Comment
User Comments (0)
About PowerShow.com