Team CIMAR: DARPA Grand Challenge 2004 - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Team CIMAR: DARPA Grand Challenge 2004

Description:

Team CIMAR: DARPA Grand Challenge 2004. Carl D. Crane. Center for Intelligent Machines and Robotics ... things to do (in a two month time period) arrange finances ... – PowerPoint PPT presentation

Number of Views:65
Avg rating:3.0/5.0
Slides: 15
Provided by: MAE100
Category:
Tags: cimar | darpa | challenge | crane | grand | team

less

Transcript and Presenter's Notes

Title: Team CIMAR: DARPA Grand Challenge 2004


1
Team CIMARDARPA Grand Challenge 2004
  • Carl D. Crane
  • Center for Intelligent Machines and Robotics
  • Dept. of Mechanical and Aerospace Engineering
  • University of Florida

2
Environment
3
Environment
4
The Team
  • University of Florida
  • Autonomous Solutions, Inc.
  • Eigenpoint Co.

5
The Plan
  • architecture based on JAUS 3.0
  • things to do (in a two month time period)
  • arrange finances
  • design and implement vehicle platform
  • obtain terrain data
  • design sensing system
  • pose
  • obstacles
  • terrain
  • develop planning software
  • route planning
  • reactive planning
  • develop action components
  • path following
  • reflexive obstacle avoidance
  • develop integration and test plan

6
The Plan
  • things to do (in a two month time period)
  • arrange finances
  • 12K, UF components
  • 12K, UF travel
  • all other funds provided by Autonomous Solutions,
    Inc.
  • sponsorships arranged
  • Eigenpoint Co.
  • Smiths
  • Preco
  • Gainesville Raceway

7
The Plan
  • things to do (in a two month time period)
  • design and implement vehicle platform

8
The Plan
  • things to do (in a two month time period)
  • obtain terrain data

data survey
9
The Plan
  • things to do (in a two month time period)
  • design sensing system
  • pose
  • Starfire GPS
  • Smiths IMU
  • obstacles
  • short and long range radar
  • 3D ladar
  • Videre stereo vision
  • terrain
  • stationary ladar
  • image processing
  • implement sensor arbitration

10
The Plan
  • things to do (in a two month time period)
  • develop planning software
  • route planning
  • identify known trails in waypoint corridor
  • plan series of path segments
  • reactive planning
  • output path segment based on sensor data

11
The Plan
  • things to do (in a two month time period)
  • develop action components
  • path following
  • demonstrate stable control at speeds up to 30 mph
  • reflexive obstacle avoidance

12
The Plan
  • things to do (in a two month time period)
  • develop integration and test plan
  • testing in Florida, 21 Jan 20 Feb 04
  • integration in Utah, 21 Feb 4 Mar 04
  • final integration in Barstow, 5 8 Mar 04

link drag strip movie
13
QID
show drawing of QID course link movie of best run
14
The Race 13 Mar 04
  • 15 teams passed QID
  • waypoint file received at 350 am
  • opening ceremony at 600 am
  • first launch at 630

add movie of race day