COMET Working Group Progress Report 09/26/03

Description:

... TDSPs where competitive metering is available Qualifying List of Three Phase Meters. For Competitive Meter ... PF , kVAR, kVARh, kVA ... Single Phase Meters. For ... – PowerPoint PPT presentation

Number of Views:6
Avg rating:3.0/5.0
Slides: 17
Provided by: TerryB187
Learn more at: http://www.ercot.com
Category:

less

Write a Comment
User Comments (0)
Transcript and Presenter's Notes

Title: COMET Working Group Progress Report 09/26/03


1
COMET Working GroupProgress Report09/26/03
2
Contents of Report
  • Timeline for Implementing the Competitive
    Metering Guides (CMG)
  • Timeline Estimate for Implementation of Phase 2
    of Competitive Metering
  • Revisions to the Qualifying List of Meters for
    Competitive Meter Ownership

3
Timeline for Approving the Competitive Metering
Guides (CMG)
  • COMET to deliver CMG to RMS on 10/17/03
  • RMS members review and forward their
    recommendations for revisions to COMET prior to
    11/10/03
  • COMET reviews RMS recommendations at the November
    11 12 scheduled meeting and provides redlined
    Guides to RMS for 11/13/03 vote
  • RMS approves CMG on 11/13/03 and delivers to TAC
    for vote on 12/04/03
  • TAC approves and delivers CMG to the ERCOT Board
    for approval on 12/16/03
  • ERCOT board approves and the CMG are posted to
    the ERCOT website

4
TIMELINE ESTIMATION TASK FORCE
COMET Team 3 Update for Aug. 12, 2003 Meeting
5
TASK FORCE MEMBERS
  • Paul Wattles Good Company
  • Johnny Robertson TXU
  • Kathy Scott CenterPoint
  • Jeff Michalski Appliance Lab
  • Don Tucker ERCOT
  • Glen Wingerd ERCOT

6
TASK FORCE GOAL
  • Estimate time-to-market necessary for Phase 2
    (MSP Phase) of Competitive Metering
  • Market Participants requirements
  • ERCOT requirements
  • Fulfill COMET Charter
  • Respond to Commissioner Perlmans inquiry
  • (This document does not address data collection/
    MDMA issues, which remain on the COMET agenda for
    the future.)

7
Assumptions
  • COMET Phase 2 (MSP) requirements for TDSPs and
    REPs will approximately equal that of the MIMO
    Stacking project
  • ERCOT requirements will be much smaller than for
    MIMO
  • Potential workaround phase not factored into
    estimates
  • MPs reluctant to launch workarounds, especially
    of unknown magnitude
  • COMET Phase 1 (ownership) expected to provide
    only limited gauge of market interest in
    competitive metering

8
Questions
  • Which transactions involving MSPs must be EDI
    (X-12)?
  • Which TX SET forms can be modified and used?
  • What format will be required for non-MSP
    transactions that cannot be handled through
    modifications to existing TX SET?

9
Milestones Time Estimates
PUCT COMET 2 (MSP) Rule approved ??
COMET stakeholders Identify high-level requirements 6 months
MPs, ERCOT Comment/ Clarification/RMS approval 3 months
MPs, ERCOT Design/Develop/Test 15 months
Estimated Total (Rule approved to LAUNCH)
24 MONTHS
10
Major Factors
  • PUCT Rulemaking schedule will define the start
    date deadlines
  • 25 new transactions identified so far
  • Many transactions will involve TX SET forms (new
    modified) automation of transactions will
    depend on TX SET schedule
  • TX SET version rollouts
  • V 1.6 COMET 1 Jan. 04 (firm)
  • V 2.0 MIMO Stacking Aug. 04 (firm)
  • V 2.1 MIMO fix (?) 1Q05
  • V X.X ??? 3Q05
  • Wholesale Market Design mega-project

11
Timeline Alternatives
  • Alternatives that could enable earlier MSP
    participation in market
  • Faster timeline under PUCT rule
  • Workarounds
  • Pilot Projects
  • Stakeholders are encouraged to offer other ideas

12
Disclaimers
  • Timeline is best-guess only
  • Subject to change if MSP Rule deviates
    significantly from Team 3 recommendation
  • We have barely drilled into Business Process
    Flows (cannot justify resources for further
    research in absence of a rule

13
Other Factors
  • Meeting this schedule (especially process of
    identifying requirements) will require
    commitments and concerted efforts from
    stakeholders
  • i.e., rigorous COMET schedule, regular
    attendance, and participation in offline task
    force activities
  • Personnel assignments (Design/Develop/
    Test/Deploy) will overlap with other projects
  • MIMO
  • COMET 1
  • Wholesale Market Design

14
(No Transcript)
15
(No Transcript)
16
Questions?????