Fatality Investigation Report Fatal head injury at contractor - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Fatality Investigation Report Fatal head injury at contractor

Description:

BSP/Contractor fatality Incident Investigation Slide: * The main contractor, Warner & Co. was only identified during the detailed investigation. – PowerPoint PPT presentation

Number of Views:137
Avg rating:3.0/5.0
Slides: 13
Provided by: SEK63
Category:

less

Transcript and Presenter's Notes

Title: Fatality Investigation Report Fatal head injury at contractor


1
Fatality Investigation ReportFatal head injury
at contractors fabrication yard
Summary Details The incident happened in the
contractors fabrication yard in Seria. At the
time of the incident work activities had not
commenced in the fabrication yard. The deceased
was attempting to sit at the flange side of a 32
pipe spool Tee-piece, which was resting on two
supports. The pipe spool toppled over, resulting
in the deceased sustaining a fatal head injury.
2
Fatality Incident on 18 Aug 2004
  • Incident Details
  • At Zainal Daud (ZD) Fabrication Yard (G25) at
    7.30 a.m.
  • Victim Mr. Lee, 31 years old Malaysian working
    for Chin Wui Heng Welder Enterprise
  • Occupation Senior Marker, 8 yrs experience
  • Injury Death from severe head injuries.
  • Survived by Spouse 4 years old son.
  • Project Single Buoy Mooring (SBM) Metering
    (Phase 2)
  • Main Contractor Warner Company Sdn. Bhd.
  • Sub-contractor Zainal Daud Sdn. Bhd.
  • Sub sub-contractor Chin Wui Heng Welder
    Enterprise

3
Fatality Incident on 18 Aug 2004
This is the position of the Tee piece resting on
the ground after it slipped and toppled out of
the two ground supports and crashing the victim
on the head.
4
PICTORIAL REPRESENTATION
Based on witnesses accounts, deceased was about
to lift himself from the flange of the Tee piece.
The Tee piece slided for about 6 inches, touched
the ground, toppled over the deceased and crashed
him on the head. The Tee piece then came to a
rest on the ground.
5
Fatality Incident on 18 Aug 2004
  • Facts Findings (1)
  • Fabrication Yard Work delayed whilst waiting for
    Tool Box Talk
  • 32 pipe Tee piece 300 (1.3 tons) partially
    completed (2 flanges welded on). Suspended,
    awaiting material.
  • Was supported by 2 primary ground supports.
  • Chain block and 5 tons jack were used whilst
    fabrication was in progress for alignment
    purposes.
  • Chain block and jack were removed after welding
    of 2 flanges.
  • No further adjustments of the primary supports
    were made to improve stability.
  • Deceased was assigned the role of supervisor of
    the above fabrication activities.

6
Fatality Incident on 18 Aug 2004
  • Facts Findings (2)
  • Initial calculations indicate Tee-piece Centre of
    Gravity shifted significantly effectively on
    the verge of tilting.
  • Since materials were not available, no further
    work was carried out. Two days later, the
    deceased (ca. 70 Kg wt) attempted to sit on outer
    rim of Tee-piece flange.
  • Tee piece slipped toppled over crushing victim
    on the head

7
Findings
  • Direct Causes
  • The Tee piece became unstable after the
    installation of the two flanges. The centre of
    gravity had shifted but the primary supports were
    not adjusted.
  • For unknown reasons, the deceased attempted to
    sit on the vertical flange of the Tee piece
  • This action caused the unstable Tee piece to slip
    and topple over.
  • The deceased suffered severe head injuries after
    being crushed by the Tee piece.

8
Findings
  • Indirect Causes (1)
  • The A-Frame, chain block and 5 Tons jack used
    earlier for alignment purposes were removed
    leaving the Tee piece on the two unadjusted
    ground supports.
  • Although a co-worker, recognising a hazard,
    re-secured the Tee piece on a chain block, this
    was subsequently removed.
  • The instability of the Tee piece had not been
    communicated to the others. Enforcement of Duty
    to Stop was inadequate.
  • General lack of hazard awareness of the
    workforce.
  • Hazard Identification Plan (HIP) for the
    contractor fabrication yard was not developed.
  • Lack of barricades and warning signs around
    hazardous areas.
  • No designated rest area

9
Findings
  • Indirect Causes (2)
  • Lack of effective supervision.
  • Lack of planning Work started on the Tee piece
    before all the materials had arrived.
  • Contract HSE Management
  • Lack of clarity between contractor,
    sub-contractor sub-sub-contractor on
    responsibility for HSE management
  • The main contractor was required under its
    contract with BSP to play a leading role in HSE
    implementation, not just the subcontractor
  • There were early warning signs of a lack of
    commitment to safety such as not following up on
    repeated violations identified during site
    visits.

10
Immediate Action (1)
  • Please undertake the following
  • Survey work supports at all worksites
    immediately. Rectify where work supports are
    unsafe or inadequate. Communicate any unsafe
    conditions found.
  • Ensure you have a HIP for every stage of your
    project, including the fabrication stage, both at
    BSP and the contractor worksites.
  • Include HIP in Tool Box Talk. Address safety of
    worksites, even when unattended.
  • Ensure provision and enforce use of designated
    rest areas at worksites.

11
Immediate Action (2)
  • Please undertake the following
  • Supervisors contract holders/managers
    accountability for safety
  • Do you know the full extent of your role?
  • Do you know what you are accountable for?
  • Are you discharging your responsibility?
  • Confirm who is responsible for sub-contractor HSE
    management.

12
Areas requiring further work
  • We will need to strengthen the culture of
    intervention (e.g. PAKAT, House Rules,
    Consequence Management).
  • We will require senior management of all
    contractors, all direct and indirect
    sub-contractors to demonstrate commitment to HSE
    by, for example, site visits and mandatory joint
    HSE meetings.
  • We will require contract holders to include all
    direct and indirect sub contractors in HSE
    performance reviews.
  • Review appropriateness of contracting strategy to
    ensure HSE responsibilities can be effectively
    exercised.
Write a Comment
User Comments (0)
About PowerShow.com