Title: GlobusEU DataGrid Coordination


1
Globus/EU DataGridCoordination
  • Jennifer Schopf
  • Argonne National Lab
  • Northwestern University

2
History
  • April 5-7 first coordination meeting at Argonne
    National Lab
  • June 18-19 second coordination meeting in Lecce
    (EuroGlobus)

3
Joint activities have value for both
  • Include U.S. sites in the production prototype
    system (at least ANL and ISI)
  • Accelerate development of packaging and certain
    other Globus elements, to ensure that they are
    available for use by EDG group.
  • Attempt to transfer some EDG technology (e.g.,
    dynamic accounts, resource broker) to U.S., for
    use in say GriPhyN experiments.

4
Specific Globus Tasks
  • MDS-2 (have alpha on Friday 13th April) GRIS
    performance, Index plug in, etc.
  • GridFTP (have alpha already)
  • GRAM job manager fix
  • All this handled via packaging
  • Replica management (alpha integration with GDMP)
  • Define U.S. nodes to integrate into tests
  • Prototype community authorization server (CAS)

5
Specific EDG Tasks
  • Group server
  • EDG-specific data providers (GRISs)
  • Dynamic accounts (collaboration on requirements)
  • Scheduler

6
Detailed Schedule
  • Apr 30
  • MDS-2.1A1 DONE
  • Replica Requirements- DONE
  • May 31
  • MDS-2.1 A2 Indexes hack done, new GIIS in Sept.
  • Initial repackaged release (Globus 2.0A)
    packages are mostly done, rest will be tar-ball
    (Globus priority 7/01)

7
Detail Schedule (cont.)
  • Jun 30
  • MDS security currently uses gridmap files,
    probably insufficient will use static
    mechanisms in OpenLDAP (works now)
  • MDS repackaging July 10
  • Group CAS rough demo for SC01, system for
    release, early 2002

8
Detailed Schedule (cont)
  • Jul 31 Final Replica Mgmt Package
  • FEATURE FREEZE
  • Aug 31 CODE FREEZE
  • Sep 30 All done

9
Contact lists
  • Accessible as both ltlistnamegt_at_globus.org and
    ltlistnamegt_at_eu-datagrid.org
  • Archived at
  • http//www-unix.globus.org/ mail_archive/ltlistnam
    egt/maillist.html

10
(No Transcript)
11
Future Meetings
  • A third joint meeting is planned for the
    Wednesday (July 18) after GGF2 in DC
  • A fourth joint meeting is planned in association
    with GGF3, October, Rome
  • Oct 1-2, 2-day hands-on Globus tutorial
  • Oct 3-5 EDG meeting including Globus coordination
    session
  • Oct 8-10 GGF-3