Replacement of a Legacy HMI as the First Step In a MultiPhase Control System Migration - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

Replacement of a Legacy HMI as the First Step In a MultiPhase Control System Migration

Description:

Experience in implementing/supporting virtually all ... Sparrows Point, Maryland 68 Inch Hot Mill. Critical Operation in Large Integrated Steel Mill ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 42
Provided by: danielj73
Category:

less

Transcript and Presenter's Notes

Title: Replacement of a Legacy HMI as the First Step In a MultiPhase Control System Migration


1
  • Replacement of a Legacy HMI as the First Step In
    a Multi-Phase Control System Migration

2
  • Independent Control Systems Integrator
  • More than 100 control and IT engineers
  • Experience in implementing/supporting virtually
    all commercially available DCS and PLC/SCADA
    systems
  • Eight offices in the Mid-Atlantic, New England,
    and Gulf Coast

3
Mittal Steel Corporation Sparrows Point,
Maryland 68 Inch Hot Mill
  • Critical Operation in Large Integrated Steel Mill
  • In continuous operation since 1947
  • 1990 Retrofit
  • Installed two new Stein Haurty Walking Beam
    Furnaces
  • Installed new Moore Products High Level
    Link/Local Instrument Link control system
  • Manufactures feedstock for all site finishing
    operations
  • Typical end uses
  • Structural steel
  • Tin cans
  • Truck frames
  • Appliances

4
Legacy System Architecture
  • A total of 103 Moore Products Local Instrument
    Link (LIL) Controllers and Communication Devices
    on Three Expanded LIL Networks
  • Model 352 Single Loop Digital Controllers
  • Model 353 Multi-Loop Controllers
  • Model 383 Multi-Point Display Stations
  • Model 324 Programmable Sequence Controllers
  • Model 321 Link Expansion Satellites
  • Model 320 Independent Computer Interfaces
  • Link Expansion Satellites Connect Three Expanded
    LILs to a High Level Link (HLL)
  • ACS Consoles on HLL
  • Model 2.5 ICI on HLL to Communicate with Level 2
    Supervisory Control System

5
Legacy Architecture Diagram
Applied Control Engineering, Inc.
6
Problems
  • ACS Consoles
  • Occasional failures and intermittent problems
  • Engineering console being used for spare parts
  • No other source for spare parts
  • Model 324 Programmable Sequence Controllers
  • Occasional failures in I/O cards and power
    supplies
  • Retired equipment being used for spare parts
  • No other source for spare parts

7
Problems (Contd)
  • ICI 2.5
  • Single point interface to VAX
  • No spare parts available
  • Link Expansion Satellites
  • Single points of failure with no spare parts
    available
  • HLL interface is most likely point of failure
  • Other LIL Devices
  • Very reliable
  • Technically obsolete, but can be replaced or
    repaired

8
Consequences of Device Failures
  • ACS Consoles
  • Failure of one very inconvenient, but
    operations could continue
  • Failure of two shut down entire hot mill (and
    therefore entire plant)
  • Model 324 Programmable Sequence Controllers
  • Failure of one shut down the associated furnace
  • ICI 2.5
  • Loss of level 2 interface
  • Operations could continue, but less efficient

9
Consequences of Device Failures (Contd)
  • Link Expansion Satellites
  • Failure of one LES shutdown of one furnace
  • Failure of any two LESs shut down entire hot
    mill
  • Other LIL Devices
  • Failure might shut down a furnace zone
  • Minor and temporary impact on operations

10
Migration Plan
  • Phase I Console Migration to Siemens PCS7 OS
  • Interface to LILs through ICI 320s
  • Customized solution to mimic ACS operation
  • Parallel Console Operation During Prove-Out
  • Phase II Replace PSCs with Siemens PCS7 AS
  • Removes controllers that have highest failure risk

11
Migration Plan (Contd)
  • Phase III Replace Level 2 Interface
  • Removes ICI 2.5
  • Phase IV Replacement of Remaining LIL Controls
  • Can be accomplished one device at a time
  • Final system is a integrated PCS7 DCS solution

12
Customer Requirements
  • Phase I Implementation Without Downtime
  • Closely Mimic ACS Navigation and Control
  • Navigate to screens by entering screen numbers
  • Navigate between furnace A and furnace B lower
    level screens without moving through screen
    hierarchy
  • Control using fixed window no pop-ups
  • Final Migration to a Distributed Control System
  • Single Database
  • Common HMI/Control engineering tool

13
Project Team
  • Wayne Medoff Mittal Steel
  • 68 Hot Mill Process Engineer
  • Vince Danna Mittal Steel
  • 68 Hot Mill Instrument Technician
  • Rob Duke Applied Control Engineering
  • Process Control Engineer
  • Dave Erby Applied Control Engineering
  • Process Control Engineer
  • Alex Shields Applied Control Engineering
  • Project Manager

14
Phase I Architecture
  • Redundant PCS7 OS Servers
  • Also act as client stations
  • Connect ICI 320s to each Local Instrument Link
  • Two on each LIL for redundant communications
  • Spare devices used no capital cost
  • Parallel Operation of ACS and PCS7 OS Until Final
    Acceptance

15
Phase I Architecture Drawing Parallel Operator
Stations
Applied Control Engineering, Inc.
16
Tag Database Creation Flow Chart
17
Objective Single Database with All Console and
Tag Address Information
  • Uploaded ACS configuration
  • Used MYCAD to obtain dBase format database
  • File contained animation information, but only
    HLL addresses
  • Uploaded LES configuration
  • Printed configuration to text file
  • Converted information to Excel
  • Imported into dBase tables
  • Combined ACS and LES Information
  • Merged through a series of queries
  • Result combined ACS/LES database with all
    console and LIL address information

18
Objective Extract ACS/LES Information to Create
File that can be Imported into PCS7 Database
Automation Utility
  • Identify ACS/LES parameters that will be required
    for PCS7 OS configuration
  • Assign required parameters to elements within
    structures
  • LIL_DISC
  • LIL_ANLG
  • LIL_LOOP
  • Develop application to query ACS/LES database and
    manipulate and map required information to proper
    format for import
  • Default values
  • Addressing information
  • Data extrapolation
  • Non-global information

19
Combined ACS/LES Database
20
Point Template
21
Press the magic button to build PCS7 points
22
Then A Miracle Occurs
Applied Control Engineering, Inc.
23
Import File for the OPC DBA
24
Not really a miracleLots and Lots of code
behind the magic button
25
Tag Database Creation Flow Chart
26
PCS7 OS OPC Database Automation Utility
  • Imported files produced by migration tool into
    the OPC DBA
  • Block icons not used (attributes, including
    symbol type, could not be assigned)
  • Screen hierarchy defined
  • Tags are assigned primary graphics

27
PCS7 OPC DBA Utility
28
PCS7 OPC DBA Utility
29
LIL OPC Server Limitations
  • No file import capability
  • Cannot copy devices or folders
  • Scaling for all analog tags had to be entered
    manually
  • Not supported for devices other than the 353
    (although it communicates to all LIL devices)

30
LIL OPC Server Configuration
  • Create one of each type of device as template
  • Manually enter device name
  • Manually create subfolders
  • Manually create elements
  • Manually scale analog tags
  • Create instances of device templates
  • Manually enter device name
  • Manually create subfolders
  • Copy elements into subfolders from device
    template
  • Manually scale analog tags

31
LIL OPC Server Configuration
32
LIL OPC Server Configuration
33
Discrete Point Communication Issues
  • Problem
  • PCS7 OS recognized LIL OPC Server discrete tags
    as integers values (based on bit location)
  • Some discretes (those above the 8th place in the
    word) would never toggle to True.
  • Solution
  • Read into PCS7 as integers
  • Treat zero values as False
  • Treat any non-zero value as True

34
PCS7 OS Customization
  • Animation Using Legacy Database Parameters
  • Visibility
  • Color
  • Decimal Places
  • Action
  • Navigation
  • Hot Key for immediately jumping to a screen
    number, regardless of position in hierarchy
  • Scripting to modify left/right navigation buttons
    to move to same screen on other furnace
  • Control
  • Embedded window rather than pop-ups
  • Populated by discrete, analog, or loop faceplate
    as appropriate

35
Typical Process Graphic
36
Animation of Number of Decimal Places
37
The PCS7 OS Request Queue
  • Behavior
  • PCS7 Request Queue jam-packed when any screen
    using symbols was used
  • PCS7 Request Queue jam-packed when global alarm
    acknowledgement configured

38
The PCS7 OS Request Queue
  • Consequences
  • No Operator request can be processed until queue
    clears
  • Waits could be as long as 10 minutes
  • If queue got too full, system would freeze-up,
    requiring a re-boot

39
The PCS7 OS Request Queue
  • Solution
  • Wherever possible, reconfigure screens to direct
    addressing vs. use of symbols
  • Add functionality to screens to reduce the need
    for picture window functionality
  • Add a line in the system registry to change the
    polling time for the request queue
  • Add a line in the system registry to change the
    polling time for alarms

40
Project Status
  • Configuration complete
  • PCS7 OS operating in parallel to ACS consoles
  • Turnover after operator and maintenance training
    completed

41
Final Phase I Architecture
Applied Control Engineering, Inc.
42
Contact
  • Alex Shields
  • Project Manager
  • Applied Control Engineering, Inc.
  • The Mill at White Clay
  • 700 Creek View Drive
  • Newark, DE 19711
  • alex.shields_at_ace-net.com
  • 302-738-8800 (office)
  • 443-745-3363 (cell)

43
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com