Title: Replacement of a Legacy HMI as the First Step In a MultiPhase Control System Migration
1- Replacement of a Legacy HMI as the First Step In
a Multi-Phase Control System Migration
2- Independent Control Systems Integrator
- More than 100 control and IT engineers
- Experience in implementing/supporting virtually
all commercially available DCS and PLC/SCADA
systems - Eight offices in the Mid-Atlantic, New England,
and Gulf Coast
3Mittal Steel Corporation Sparrows Point,
Maryland 68 Inch Hot Mill
- Critical Operation in Large Integrated Steel Mill
- In continuous operation since 1947
- 1990 Retrofit
- Installed two new Stein Haurty Walking Beam
Furnaces - Installed new Moore Products High Level
Link/Local Instrument Link control system - Manufactures feedstock for all site finishing
operations - Typical end uses
- Structural steel
- Tin cans
- Truck frames
- Appliances
4Legacy System Architecture
- A total of 103 Moore Products Local Instrument
Link (LIL) Controllers and Communication Devices
on Three Expanded LIL Networks - Model 352 Single Loop Digital Controllers
- Model 353 Multi-Loop Controllers
- Model 383 Multi-Point Display Stations
- Model 324 Programmable Sequence Controllers
- Model 321 Link Expansion Satellites
- Model 320 Independent Computer Interfaces
- Link Expansion Satellites Connect Three Expanded
LILs to a High Level Link (HLL) - ACS Consoles on HLL
- Model 2.5 ICI on HLL to Communicate with Level 2
Supervisory Control System
5Legacy Architecture Diagram
Applied Control Engineering, Inc.
6Problems
- ACS Consoles
- Occasional failures and intermittent problems
- Engineering console being used for spare parts
- No other source for spare parts
- Model 324 Programmable Sequence Controllers
- Occasional failures in I/O cards and power
supplies - Retired equipment being used for spare parts
- No other source for spare parts
7Problems (Contd)
- ICI 2.5
- Single point interface to VAX
- No spare parts available
- Link Expansion Satellites
- Single points of failure with no spare parts
available - HLL interface is most likely point of failure
- Other LIL Devices
- Very reliable
- Technically obsolete, but can be replaced or
repaired
8Consequences of Device Failures
- ACS Consoles
- Failure of one very inconvenient, but
operations could continue - Failure of two shut down entire hot mill (and
therefore entire plant) - Model 324 Programmable Sequence Controllers
- Failure of one shut down the associated furnace
- ICI 2.5
- Loss of level 2 interface
- Operations could continue, but less efficient
9Consequences of Device Failures (Contd)
- Link Expansion Satellites
- Failure of one LES shutdown of one furnace
- Failure of any two LESs shut down entire hot
mill - Other LIL Devices
- Failure might shut down a furnace zone
- Minor and temporary impact on operations
10Migration Plan
- Phase I Console Migration to Siemens PCS7 OS
- Interface to LILs through ICI 320s
- Customized solution to mimic ACS operation
- Parallel Console Operation During Prove-Out
- Phase II Replace PSCs with Siemens PCS7 AS
- Removes controllers that have highest failure risk
11Migration Plan (Contd)
- Phase III Replace Level 2 Interface
- Removes ICI 2.5
- Phase IV Replacement of Remaining LIL Controls
- Can be accomplished one device at a time
- Final system is a integrated PCS7 DCS solution
12Customer Requirements
- Phase I Implementation Without Downtime
- Closely Mimic ACS Navigation and Control
- Navigate to screens by entering screen numbers
- Navigate between furnace A and furnace B lower
level screens without moving through screen
hierarchy - Control using fixed window no pop-ups
- Final Migration to a Distributed Control System
- Single Database
- Common HMI/Control engineering tool
13Project Team
- Wayne Medoff Mittal Steel
- 68 Hot Mill Process Engineer
- Vince Danna Mittal Steel
- 68 Hot Mill Instrument Technician
- Rob Duke Applied Control Engineering
- Process Control Engineer
- Dave Erby Applied Control Engineering
- Process Control Engineer
- Alex Shields Applied Control Engineering
- Project Manager
14Phase I Architecture
- Redundant PCS7 OS Servers
- Also act as client stations
- Connect ICI 320s to each Local Instrument Link
- Two on each LIL for redundant communications
- Spare devices used no capital cost
- Parallel Operation of ACS and PCS7 OS Until Final
Acceptance
15Phase I Architecture Drawing Parallel Operator
Stations
Applied Control Engineering, Inc.
16Tag Database Creation Flow Chart
17Objective Single Database with All Console and
Tag Address Information
- Uploaded ACS configuration
- Used MYCAD to obtain dBase format database
- File contained animation information, but only
HLL addresses - Uploaded LES configuration
- Printed configuration to text file
- Converted information to Excel
- Imported into dBase tables
- Combined ACS and LES Information
- Merged through a series of queries
- Result combined ACS/LES database with all
console and LIL address information
18Objective Extract ACS/LES Information to Create
File that can be Imported into PCS7 Database
Automation Utility
- Identify ACS/LES parameters that will be required
for PCS7 OS configuration - Assign required parameters to elements within
structures - LIL_DISC
- LIL_ANLG
- LIL_LOOP
- Develop application to query ACS/LES database and
manipulate and map required information to proper
format for import - Default values
- Addressing information
- Data extrapolation
- Non-global information
19Combined ACS/LES Database
20Point Template
21Press the magic button to build PCS7 points
22Then A Miracle Occurs
Applied Control Engineering, Inc.
23Import File for the OPC DBA
24Not really a miracleLots and Lots of code
behind the magic button
25Tag Database Creation Flow Chart
26PCS7 OS OPC Database Automation Utility
- Imported files produced by migration tool into
the OPC DBA - Block icons not used (attributes, including
symbol type, could not be assigned) - Screen hierarchy defined
- Tags are assigned primary graphics
27PCS7 OPC DBA Utility
28PCS7 OPC DBA Utility
29LIL OPC Server Limitations
- No file import capability
- Cannot copy devices or folders
- Scaling for all analog tags had to be entered
manually - Not supported for devices other than the 353
(although it communicates to all LIL devices)
30LIL OPC Server Configuration
- Create one of each type of device as template
- Manually enter device name
- Manually create subfolders
- Manually create elements
- Manually scale analog tags
- Create instances of device templates
- Manually enter device name
- Manually create subfolders
- Copy elements into subfolders from device
template - Manually scale analog tags
31LIL OPC Server Configuration
32LIL OPC Server Configuration
33Discrete Point Communication Issues
- Problem
- PCS7 OS recognized LIL OPC Server discrete tags
as integers values (based on bit location) - Some discretes (those above the 8th place in the
word) would never toggle to True. - Solution
- Read into PCS7 as integers
- Treat zero values as False
- Treat any non-zero value as True
34PCS7 OS Customization
- Animation Using Legacy Database Parameters
- Visibility
- Color
- Decimal Places
- Action
- Navigation
- Hot Key for immediately jumping to a screen
number, regardless of position in hierarchy - Scripting to modify left/right navigation buttons
to move to same screen on other furnace - Control
- Embedded window rather than pop-ups
- Populated by discrete, analog, or loop faceplate
as appropriate
35Typical Process Graphic
36Animation of Number of Decimal Places
37The PCS7 OS Request Queue
- Behavior
- PCS7 Request Queue jam-packed when any screen
using symbols was used - PCS7 Request Queue jam-packed when global alarm
acknowledgement configured
38The PCS7 OS Request Queue
- Consequences
- No Operator request can be processed until queue
clears - Waits could be as long as 10 minutes
- If queue got too full, system would freeze-up,
requiring a re-boot
39The PCS7 OS Request Queue
- Solution
- Wherever possible, reconfigure screens to direct
addressing vs. use of symbols - Add functionality to screens to reduce the need
for picture window functionality - Add a line in the system registry to change the
polling time for the request queue - Add a line in the system registry to change the
polling time for alarms
40Project Status
- Configuration complete
- PCS7 OS operating in parallel to ACS consoles
- Turnover after operator and maintenance training
completed
41Final Phase I Architecture
Applied Control Engineering, Inc.
42Contact
- Alex Shields
- Project Manager
- Applied Control Engineering, Inc.
- The Mill at White Clay
- 700 Creek View Drive
- Newark, DE 19711
- alex.shields_at_ace-net.com
- 302-738-8800 (office)
- 443-745-3363 (cell)
43(No Transcript)