Predictive Out-of-Step Protection and Control Scheme - PowerPoint PPT Presentation

1 / 67
About This Presentation
Title:

Predictive Out-of-Step Protection and Control Scheme

Description:

Predictive Out-of-Step Protection and Control Scheme Based on Real-Time Phasor Measurement Application By Alla Deronja, P.E. Senior System Protection Engineer – PowerPoint PPT presentation

Number of Views:591
Avg rating:3.0/5.0
Slides: 68
Provided by: pespsrcO9
Category:

less

Transcript and Presenter's Notes

Title: Predictive Out-of-Step Protection and Control Scheme


1
  • Predictive Out-of-Step Protection and Control
    Scheme
  • Based on Real-Time
  • Phasor Measurement Application
  • By Alla Deronja, P.E.
  • Senior System Protection Engineer
  • American Transmission Company
  • Milwaukee, Wisconsin

2
  • This presentation is focused on demonstration of
    applying
  • the concept of real-time measurements in a
    transmission
  • system to perform system protection and control
    functions
  • in a predictive - or adaptive - manner to account
    for the
  • system operating conditions at any time.
  • Objectives
  • Real-time measurements and adaptive/predictive
    protection.
  • Predictive out-of-step protection scheme based
    on real-time measurements.
  • Practical application.

3
  • As a system protection engineer, I am interested
    in
  • applying real-time phasor measurement technology
    to
  • perform system protection, control and tripping
    functions
  • to achieve a protection systems adaptability to
    account
  • for all possible system operating conditions.

4
  • The concept of adaptive relaying is that many
    relay
  • settings are dependent upon assumed conditions in
    the
  • power system. In order to cover all possible
    scenarios that
  • the protection system may have to face, the
    actual
  • protection settings are often not optimal for any
    particular
  • system state. If an optimal setting is desired
    for an
  • existing condition on the power system network,
    then it
  • becomes necessary for the setting to adapt itself
    to the
  • real-time system states as the system conditions
    vary
  • due to changing loads, network switching
    operations,
  • or faults.

5
  • A number of relaying functions are predicated
    upon an
  • assumed pattern of power system behavior during
  • transient stability oscillations and other
    dynamic
  • conditions. An example of such functions is
    out-of-step
  • protection.
  • A predictive out-of-step protection and control
    scheme
  • based on the real-time phasor measurement
    principle that
  • has inspired me to pursue my project proposal has
  • been already in operation for almost 20 years.

6
  • TOKYO ELECTRICS PREDICTIVE OUT-OF-STEP
    PROTECTION SYSTEM
  • The predictive out-of-step protection system by
    means
  • of observing phase differences between power
    centers
  • and based on the realtime phasor measurement
  • principle similar to the one I sought to install
    at my
  • company has been installed and successfully
    operated
  • by Tokyo Electric Power Company (TEPCO, Japan)
    since
  • February, 1989.

7
  • The bulk power system of TEPCO in presented in
    Fig.
  • 1. A major characteristic of this power system is
    that
  • the power generation areas are far from the
  • consumption areas. The eastern, northern, and
  • southeastern generator groups are linked by a
    bulk
  • power system comprising 500 kV double-circuit
  • transmission lines configured in duplex and
    triplex
  • routes and forming a trunk. The western
    generator
  • group and large local loads are thus linked to
    the bulk
  • power system via the substations marked as A1 and
    A2
  • in Fig. 1.

8
  • FIGURE 1. BULK POWER SYSTEM OF TEPCO

9
  • The western generator group tends to be heavily
  • loaded, and its own capacity cannot meet demand.
  • Power is received from the bulk power system to
    make
  • up the deficiency.
  • When a double fault occurs along both circuits of
    a
  • double-circuit line forming one route, the
    substations at
  • both ends of the line are disconnected and
    transmission
  • capability is interrupted. If a successive fault
    occurs
  • after reclosing, a slow cyclic power swing
    develops
  • between the western generator group and the bulk
  • power system.

10
  • The same situation occurs in the event of failure
    of a
  • bus-bar protective relay to operate during a
    bus-bar
  • fault. Over time, the phase difference of the
    generator
  • groups thus undergoes oscillating divergence. If
    this
  • condition is not corrected, an out-of-step
    condition will
  • begin to occur in various parts of the power
    system and
  • may lead to its total collapse.

11
  • In order to maintain the reliability of the power
    system
  • should such serious rare faults occur, a
    predictive
  • protection system that prevents total collapse of
    the
  • power system has been developed. This protection
  • system utilizes online data collected before and
    after
  • the onset of a system disturbance to determine
  • the characteristics of the power swing and
    predict an
  • out-of-step condition. The system operates during
    the
  • incubation period so that appropriate control can
    be
  • performed before the out-of-step condition occurs.

12
  • The western area can be islanded (Fig. 2) from
    the bulk
  • power system at points (a) or (b) and (a) or
    (b) before
  • out-of-step occurs and then operated
    independently.
  • This eliminates power swing between the generator
  • groups of the two systems and restores stability.
  • The separation point is selected based on the
    power
  • flow at pre-determined points for separation
    before the
  • fault.

13
  • FIGURE 2. SIMPLIFIED MODEL OF TRUNK LINE
  • AND GENERATORS

14
  • The protection scheme is outlined in Fig. 3. The
    status
  • of each generator group (east, north, southeast,
    west)
  • is obtained by measuring the bus-bar voltages of
  • neighboring substations as representative values.
    From
  • these, the phase differences between the western
  • generator group and the bulk power system are
  • obtained. From the phase difference values, the
  • corresponding values for 200 ms in the future are
  • predicted. If the latter exceed the setting value
    (?limit),
  • the respective generator groups are judged to be
  • unstable.

15
  • FIGURE 3. OUTLINE OF PROTECTION SCHEME

16
  • The two out of three logic is employed to judge
  • instability of all the groups and to prevent
    unwanted
  • operation in the event of an out-of-step of one
  • generator group within the bulk power system. In
    order
  • to initiate system separation, the current swing
  • detection element must operate based on the
    current
  • flowing through the transformers of the linkage
  • substations A1 and A2 between the bulk power
    system
  • and the western area (Fig. 1).

17
  • When the two out of three generator groups have
    been
  • determined to be unstable and the current swing
  • detection element has operated, the islanding
    command
  • is issued from the Central Equipment to the
    separation
  • point. The trip command is executed if the
    current
  • swing detection element in the RTU has operated
    on
  • the current flowing through that point. The
    current
  • swing detection element is provided as a
    fail-safe
  • measure for the protection calculation based on
    phase
  • difference.

18
  • To achieve flexibility in dealing with various
    operating
  • conditions of the western area, the present
    protection
  • system is divided into completely separate duplex
  • systems System 1 and System 2. System 1 handles
  • separation at points (a) and (b) in Fig. 2, and
    System 2
  • at points (a) and (b).
  • System 2 is nearly identical to System 1 so that
  • System 1 will be only described.

19
  • System 1 comprises a Central Equipment (Phasor
    Data
  • Concentrator) at Substation A1 and Remote
    Terminal
  • Units RTUs (Phasor Measurement Units PMUs) at
  • Substations B1, C, D, and E (Fig. 4).
  • The RTUs simultaneously sample bus-bar voltages
    at
  • 600 Hz. The sampled real-time data is transmitted
    to
  • the Central Equipment (CE) via the data
    transmission
  • system (a communication channel). In addition,
    the
  • current flowing through the system separation
    point (b)
  • at Substation B1 is measured then, the power
    flow
  • value is calculated and transmitted to the CE.

20
  • FIGURE 4. BASIC CONFIGURATION OF SYSTEM 1
  • PROTECTION SYSTEM

21
  • At substation A1, the current and power flow
    values
  • through the system separation point (a) and
    through
  • the transformer are measured. The CE calculates
    the
  • real-time phase difference and predicted future
    phase
  • difference and selects the system separation
    point using
  • this online data. The circuit breaker command is
    issued
  • for either point (a) or (b) as selected by the CE
  • calculation on the measured data.

22
  • The entire system configuration is presented in
    Fig. 5.
  • All devices are based on 16-bit microprocessors.
    The
  • microprocessor has data transmission,
    self-diagnostic
  • and calculating functions provided by the CE.
    Data
  • transmission between the CE and RTUs is carried
    out
  • synchronously via a duplex digital microwave
    link. The
  • data transmission speed of this system is 56 kbps.

23
  • FIGURE 5. OVERALL CONFIGURATION
  • OF
    PROTECTION SYSTEM

24
  • The data from one RTU of the C, D, and E
    substations
  • is sent to both CE of the same system via the
    data
  • transmission system. Each CE receives the data
    for both
  • RTUs of each generator group, but only one set of
    data
  • is normally employed. If an abnormality occurs,
    the CE
  • can switch to the other RTUs data. The purpose
    of this
  • two-fold redundancy is to decrease system
    downtime
  • since long-distance transmission with multiple
    spans is
  • employed.

25
  • The method of obtaining the phase difference
    between
  • two points (western generator group and bulk
    power
  • system) from simultaneously sampled voltage data
    is as
  • follows.
  • In Fig. 6, representative voltage waveform
    sampling
  • values for a bus-bar in the vicinity of the
    northern
  • generator group (C in Fig. 6) and the western
  • generator group (B in Fig. 6) are shown.

26
  • FIGURE 6. EXAMPLE OF VOLTAGE WAVEFORM SAMPLING
  • DATA FOR TWO SUBSTATIONS

27
  • The phase difference, ?n, at present time n can
    be
  • obtained from the voltage data VBn, VBn-3, VCn,
    and
  • VCn-3 for the present time and three previous
  • samples as follows

28
  • Thus,
  • In order to simplify the calculation by replacing
    X Xi
  • with a first-order approximation obtained via
    Taylor
  • Series, the phase difference can be obtained by
  • where 0 ? X ? 1

29
  • If X ? 1, the following additional equation is
    used to
  • perform the calculation.
  • If X ? 0, the following additional equation is
    used to
  • perform the calculation.
  • Since the approximation error is on the order of
    10-2,
  • accuracy is sufficient for practical use.

30
  • The phase difference ? between the two areas can
    be
  • approximated by the following equation.
  • where,
  • ?0 is initial value of phase difference ?,
  • ? is angular frequency of ?,
  • ? is damping constant,
  • A is amplitude.
  • This equation interprets the power swing mode as
    a
  • sine wave that diverges or converges.

31
  • Using the phase difference values for the present
    time
  • and previous time, the future phase difference
    value
  • can be predicted. The predicted phase difference
    ? for
  • time TH in the future is derived from eight
    pieces of
  • data (Fig. 7) and calculated as follows

32
  • FIGURE 7. METHOD OF PREDICTING
  • PHASE
    DIFFERENCE

33
  • Values of 200 ms and 100 ms were selected for TH
    and
  • TK (a time interval before the present time in
    Fig. 7),
  • respectively, in order to predict accurately and
    to
  • provide an acceptable operating time.
  • A simulation of the present prediction algorithm
  • calculation is given in Fig. 8. The results agree
    well
  • with the present phase difference value and the
  • predicted future value at 200 ms.

34
  • FIGURE 8. SAMPLE CALCULATION OF
  • PHASE DIFFERENCE

35
  • When the obtained predicted phase difference
    value ?
  • exceeds the setting value ?limit, it is judged
    that the
  • power swing between the two generator groups is
  • unstable. The value for ?limit is determined by
    computer
  • simulation under varying conditions and must
    guarantee
  • operation when the system is unstable and prevent
  • operation when the system is stable.
  • The table in Fig. 9 shows the results of computer
  • simulation for several system operating patterns.
    ?limit is
  • set to 100?.

36
  • FIGURE 9. SIMULATION RESULTS

37
  • In order to guarantee fail-safe operation of the
    scheme,
  • an input different from the voltage input, the
    current
  • input, is used to detect the swing. Its logic
    shown in
  • Fig. 10 comprises a rate of change detection
    block to
  • determine whether power swing is present and a
  • magnitude of change detection block to detect the
    size
  • of the current fluctuation. The element operates
    on the
  • AND of these two blocks.

38
  • FIGURE 10. CURRENT SWING DETECTOR

39
  • The operation of the current swing detector is
  • presented in Fig. 11. The magnitude of change
  • detection block operates when the measured
    current
  • fluctuation magnitude is greater than its
    sensitivity
  • setting ISET during maximum power swing period
    ?Tmax.
  • The values for ISET and ?Tmax are determined by
  • computer simulation, and ISET is set for ?Tmax3
    sec.

40
  • FIGURE 11. PRINCIPLE OF CURRENT SWING DETECTION

41
  • The element detects when the slope of the
    difference of
  • the r.m.s. current value during the small
    interval ?t
  • (?I/?t) is greater than constant K and continues
    longer
  • than operation delay time T1 in order to operate
  • when the size of the current swing is greater
    than ISET
  • during a sine wave that is smaller than ?Tmax. To
  • prevent dropout in the vicinity of extreme values
    of the
  • sine wave, the OFF delay timer T2 (reset delay)
    is set to
  • 1 sec when ?t40 ms and T1200 ms.

42
  • A computer simulation was run for a double three-
  • phase-to-ground fault of a double circuit
    transmission
  • line (1 route) in the trunk with a subsequent
  • failure of three-pole reclosing with synchronism
    check.
  • The results are presented in Fig. 12.
  • The power swing has a tendency toward divergence
  • without a protection system (Fig. 12a). In this
    case,
  • out-of-step is likely after 10 sec, and this
    process would
  • continue to extend and eventually cause a
    conventional
  • out-of-step relay to operate and separate the
    western
  • area after about 13.5 sec.

43
  • FIGURE 12. EVALUATION BY COMPUTER SIMULATION

44
  • Even after separation, the power swing would also
  • continue in the bulk power system.
  • In contrast, when the protection system is
    employed
  • as shown in Fig. 12b, the western area is
    separated
  • after 6.6 sec, and the power swing of the bulk
    power
  • system starts to converge. The western area is
    then
  • operated independently, and another control
    system
  • such as under-frequency load shedding adjusts the
  • power supply and demand balance.

45
  • The present protection system also underwent a
    field
  • test. The power system configuration and test
    results
  • are presented in Fig. 13. A circuit breaker at
    point (c) is
  • being closed to configure the western power
    system as
  • a loop system.The predicted and measured phase
  • difference values were observed. The predicted
    phase
  • difference values before and after closing of the
    circuit
  • breaker agreed well with the measured values.

46
b) Example of phase difference swing detection
  • FIGURE 13. CONTENT AND RESULTS OF FIELD TEST

47
  • EXAMPLE OF
  • OUT-OF-STEP PROTECTION SCHEME
  • POSSIBLE UPGRADE UTILIZING
  • SYNCHROPHASOR MEASUREMENTS
  • The company I am representing - American
    Transmission
  • Company - utilizes an out-of-step protection
    scheme,
  • which I sought to upgrade to make it adaptive -
    or
  • predictive - using the real-time synchrophasor
  • measurement principle and newest hardware
    available.

48
  • The existing ATC Northern transmission system has
  • limited power transfer capabilities from
    Michigans Upper
  • Peninsula (UP) generation to a key bulk power
  • transmission substation due to its inadequate
    transmission
  • and generation infrastructure.
  • Several completed major projects have improved
    the
  • system. However, it remains weak and still
    requires the
  • use of a special protection scheme to block
  • unstable power swings by tripping UP generation
    for
  • critical faults on the transmission system.

49
  • Two pairs of power swing relays SEL-68 are
    installed at
  • the key bulk power transmission substation to
    backup the
  • UP generations SPS operations. Each pair is
    installed to
  • trip in series for redundancy to prevent a
    misoperation
  • should one of the relays fail.
  • The power swing relays are time-delayed to allow
  • operation of the primary SPS. If the primary SPS
    fails to
  • operate, the power swing relays are designed to
    separate
  • the ATC power system into two islands the UP and
    the
  • Wisconsin bulk power system.

50
  • For unstable power swings to the south of the key
    bulk
  • power transmission substation caused by an excess
    of the
  • UP generation, one pair of the SEL-68 relays will
    trip the
  • three southern lines of the power transmission
    corridor.
  • For unstable power swings to the north of the
  • substation caused by a deficiency of the UP
    generation,
  • the second pair of the SEL-68 relays will trip
    the three
  • northern lines of the power transmission corridor.

51
  • FIGURE 14. CURRENT ATC POWER SWING RELAY SCHEME

52
  • The existing out-of-step protective relays are
    SEL-68,
  • the 1987 years vintage. Their principle of
    operation is
  • based on comparing in the central location the
    voltage
  • phasor angles on two buses that present two
    different
  • systems which, if not synchronized, will have to
    be split
  • by the out-of-step relaying.

53
  • FIGURE 15. POWER SYSTEM
    MODEL

54
  • DELTA (?) is the angle between source E1 and
    source
  • E2, and V and I are the relays voltage and
    current,
  • respectively.
  • E1VjX1I
  • E2VjX2I
  • The angle DELTA between these phasors is found as
  • follows
  • AjBE1(E2)

55
  • Where A is the real part of the complex product
    of E1
  • and the complex conjugate of E2
  • B is the imaginary part.
  • Then, DELTA inverse cotangent (A/B)
  • DELTA-double-dot is found from DELTA-dot by
    filtered
  • first derivatives.

56
  • DELTA, DELTA-dot, and DELTA-double-dot are used
    by
  • the relay SEL-68 to assess system stability by
    examining
  • their loci in two planes (figures 16 and 17).

57
  • FIGURE 16. DELTA VS. DELTA-DOT PLANE

58
  • FIGURE 17. DELTA-DOT VS. DELTA-DOUBLE-DOT
    PLANE

59
  • If tripping (or blocking) is initiated when the
    swing
  • trajectory crosses the TRIP-BLOCK DECISION LINE
    in
  • the DELTA vs. DELTA-dot plane (Fig. 16), then the
  • power circuit breaker has just the necessary time
    to
  • complete its operation before the TRIP-BLOCK
  • DECISION ANGLE (TBDA) is actually reached.
  • In Fig. 17, the loci for several different stable
    () and
  • unstable () swings are plotted at the moment
    that the
  • power angle crosses the TRIP-BLOCK DECISION LINE.

60
  • This explains how information from the two planes
  • (figures 16 and 17) is utilized by the SEL-68
    relay to
  • arrive at a TRIP-BLOCK (or, equivalently, STABLE-
  • UNSTABLE) decision. Examining the swing loci in
    the
  • DELTA vs. DELTA-dot plane permits the relay to
  • determine when the power angle has reached a pre-
  • determined value (TBDA), and plotting the loci in
    the
  • DELTA-dot vs. DELTA-double-dot plane at that
    instant
  • permits the stable/unstable decision.

61
  • The relays are designed to support four system
  • operating conditions, one normal and three
    alternative,
  • each based on pre-calculated system impedances.
  • It is clear that the power system can have more
    than
  • four operating conditions, and pre-calculated
    impedance
  • values, even updated on a regular basis, will
    never
  • provide the most accurate representation of the
    real
  • system configuration. A precedence for potential
  • misoperation or insecurity of the protection
    system has
  • been set.

62
  • Upon detection of an out-of-step condition, the
    next
  • step of the protection system is to permit
    selective
  • tripping for clearly unstable cases so that the
    power
  • system is separated in the islands with a
    reasonable
  • match between load and generation in each island.
    At
  • present, the places where tripping is permitted
    are pre-
  • determined based upon simulations performed
    during
  • system stability studies. Eventually, a more
    appropriate
  • procedure may be developed to determine both the
  • nature of an in-progress swing as well as
    desirable
  • locations for separation in real-time.

63
FIGURE 18. PREDICTIVE OUT-OF-STEP
PROTECTION SYSTEM
BASED ON REAL-TIME PHASOR MEASUREMENTS
64
  • Implementation of this scheme will require
    substantial
  • communication channel capacity. Phasors from the
    two
  • key places must be communicated to a central
    location
  • where stability swing evaluation and prediction
    are to
  • be carried out. After the prediction phase,
    direct trip
  • or block commands must be communicated locally
    and
  • to one remote substation. It seems almost certain
    that
  • fiber optic communication channels will be
    necessary
  • for adaptive features of this category to be
  • implemented.

65
  • REFERENCES
  • Y. Ohura, M. Suzuki, K. Yanagihashi, M. Yamaura,
    K. Omata, T. Nakamura, A predictive Out-of-Step
    Protection System Based on Observation of the
    Phase Difference Between Substations, IEEE
    Transactions on Power Delivery, Vol. 5, No. 4,
    November 1990.
  • 2. A. G. Phadke and J. S. Thorp, Computer
    Relaying for Power
  • Systems, Research Studies Press Ltd.
    ISBN 0 86380 074 2.
  • 3. G. Benmouyal, E. O. Schweitzer III, A.
    Gusman, Synchronized Phasor Measurement in
    Protective Relays for Protection, Control, and
    Analysis of Electric Power Systems.

66
  • REFERENCES (cont.)
  • 4. Ph. Denys, C. Counan, L. Hossenlopp, C.
    Holweck, Measurement of Voltage Phase for the
    French Future Defense Plan Against Losses of
    Synchronism, IEEE Transactions on Power
    Delivery, Vol. 7, No. 1, January 1992.
  • V. Centeno, J. De La Ree, A. G. Phadke, G.
    Mitchell, J. Murphy, R. Burnett, Adaptive
    Out-of-Step Relaying Using Phasor Measurement
    Techniques, IEEE Computer Applications in Power,
    October 1993.
  • 6. S. H. Horowitz and A. G. Phadke, Boosting
    Immunity to Blackouts, IEEE Power Energy
    magazine, September/October 2003.

67
  • REFERENCES (cont.)
  • Schweitzer Engineering Laboratories, SEL-68 Out
    of Step Blocking/Tripping Relay Swing Recorder.
    Instructional Manual, April 1986
  • 8. E. O. Scweitzer III, T. T. Newton, R. A.
    Baker, Power Swing Relay Also Records
    Disturbances, 13th Annual Western Protective
    Relay Conference, Spokane, WA, October 21-23, 1986
Write a Comment
User Comments (0)
About PowerShow.com