Title: Presentation of Status WP 4 Innovative dismantling strategies and procedures
1Presentation of StatusWP 4 -Innovative
dismantling strategiesand procedures
- Presented by USTRATH
- with participation and contributions of
- IITB, LEYAL, MM, NASOL, UoP
- SHIPDISMANTL - 6th Technical Meeting/Mid-Term
Meeting, - 6 7 September 2007, Ydra
2Presentation Outline
- WP 4 Objectives
- Technical Progress
- Open issues for decision
- Closure Plan for WP4
- Discussion
3Objectives of WP4
- Optimal design of a prototype Shipdismantling
(SD) facility - Optimisations according to the D4.1 of a given
yard related to Full-SD, and Partial-SD
4Overview of WP4
- Start date M06 (Sep05) actual Feb06
- End date M24 (Jan07) (ext-M27/Apr07)
- Reporting
- D4.1 (due M18/Sep07 (ext-M24/Jan07), USTRATH) gt
Draft submitted for review - D4.2 (due M24/Jan07 (ext-M27/Apr07) , USTRATH)
gt started, in progress - D4.3 (due M24/Jan07 (ext-M27/Apr07), USTRATH) gt
started, in progress - Partners (m-m)
- UGS (15)
- LEYAL (6)
- NASOL (5.5)
- UoP (5)
- IITB (5)
- MM (2.5)
- KCC (1)
- Budget (40 m-m) D4.1 (22) D4.2 (9) D4.3 (9)
5WP 4 Current Status
- Completed Tasks (Draft Deliverable under review)
- Task 4.1 Generic guidelines for the optimization
of design, construction and operation of ship
dismantling facilities - Ongoing Tasks
- Task 4.2 Optimization according to the generic
principles introduced in 4.1 of a given
dismantling yard related to the full ship
dismantling - Task 4.3 Optimization according to the generic
principles introduced in 4.1 of a given
dismantling yard related to the partial ship
dismantling
6Task 4.1 Generic Guidelines forOptimal SD
Facilities
- Deliverable 4.1, by USTRATH (Original Work Plan)
- ST4.1.1 Docking facilities
- ST4.1.2 Equipment recovery
- ST4.1.3 Pre-cleaning
- ST4.1.4 SD process zones
- ST4.1.5 Storage and support facilities
- ST4.1.6 Design by simulation (Cost energy)
7WP4 Problems/issues
- Schedule over-run due to scope change and scope
creep in the Task4.1 - Need for ongoing update of list of layout design
parameters, and technology - Data availability issues
- Actions taken
- Extended schedule
- Integration of document structure with DSS
- Selection/analysis of a case ship (product data)
8WP - 4
WP - 5
9Work Plan Original v. Updated
end Sep06
end Jan07
Updated Original
10Progress Update
Feb07
Sep07
End Aug05
End Feb06
Sep06
11WP4 Schedule, Deliverables Milestones
D4.1 Generic guidelines for optimal ship breaking
facilities (m18)
M4.1 Selection and optimization of Leyal docking
system
M4.2 Generic guidelines for optimal structure of
dismantling facilities
D4.2 Optimal design and re-organisation of Leyal
dismantling facilities (m24)
D4.3 Optimal design and re-organisation of
NAFTOSOL dismantling facilities
M4.3 Reports on amendment of current facilities
12- Report of
- Technical Progress
13Work-in-progress (as of Mid-term Meeting,
February 2007)
- ST 4.1.6 simulation modelling for facility design
- Concurrent development of hierarchical model by
USTRAT UoP - This is being done for
- Generic SD Workflows
- Selected layout variants (Baseline 3)
- Selected technology scenarios (x 4)
- Output measures design parameters
- Input vessel Case ship 1
14Work Performed (M30)
- D4.1 (Facility development guidelines) kept open
for feedbacks - Simulation models developed for
- Revenue for value streams
- Liquids flow
- Hazardous materials (WIP)
- Mobile shear for SD
- Technical reports (guidelines) for above
simulation models - Meeting with LEYAL resimulation models
15Open Issues for Decision
- Use of individual simulation models (UGS Models)
- Decision on whether to integrate with UoP Generic
Model (Original Plan) or to keep UGS models for
stand-alone use (worst case scenario) - For integration availability of resources at UoP
- User access to simulation models (Both UoP and
UGS models) web-based access (original plan) or
stand-alone (run-time) mode - Database update/population issues how
LEYAL/NASOL provided real data to simulation
model be handled in the DSS?
16Closure Plan for WP4
- To be finished by
- mid-October07
- D4.1 updated version submission for closure
- Technical Notes (Individual Simulation Model
Reports) ready for all agreed sub-models - D4.2D4.3 draft available for comments
- end October07
- D4.2 D4.3 updated version submission for
closure - mid-November07
- D4.2 D4.3 finalised
- WP4 closed
17DisseminationSD Conference08
- Second International Conference on Shidismantling
of Obsolete Vessels - 15-16 September 2008, Glasgow
- Official Call for papers and details will be
distributed in October07
18WP4 Schedule, Deliverables Milestones
D4.1 Generic guidelines for optimal ship breaking
facilities (m18)
M4.1 Selection and optimization of Leyal docking
system
M4.2 Generic guidelines for optimal structure of
dismantling facilities
D4.2 Optimal design and re-organisation of Leyal
dismantling facilities (m24)
D4.3 Optimal design and re-organisation of
NAFTOSOL dismantling facilities
M4.3 Reports on amendment of current facilities
19D4.1 Generic Guidelines for Optimum Shipbreaking
Facilities
20Deliverable 4.1 - GENERIC GUIDELINES FOR OPTIMUM
SHIP-BREAKING FACILITIES Structure of the
Document
- 1 SUMMARY
- 2 INTRODUCTION
- 3 BACKGROUND OF THE SHIPDISMANTLING FACILITY
PROBLEM - 4 FACILITY AND LAYOUT DESIGN
- 5 MODELLING THE SHIPBREAKING FACILITY
- 6 MAIN TECHNOLOGY SCENARIOS
- 7 CAPACITY REQUIREMENTS AND PLANT EVALUATION
- 8 DESCRIPTION OF PLANT AND AREAS
- 9 MATERIAL HANDLING SYSTEMS
- 10 MANNING PROFILES AND ITS DISTRIBUTION
- 11 EVALUATION OF FACILITIES
- 12 CONCLUDING REMARKS
- 13 REFERENCES
- 14 APPENDIX
3.1 REVIEW OF SD FACILITY STUDIES 3.2 MODEL
LAYOUT FOR SD FACILITIES 3.3 Guidelines for
Processes and Operations
4.1 Hierarchy of Objectives in SD Facility
Development 4.2 Ranking of Objective Criteria
4.1.1 Health and Safety Risk (Level-1
Criteria) 4.1.2 Environmental Risk (Level-1
criteria) 4.1.3 Financial (Level-1
criteria) 4.1.4 Technical Performance (Level-1
criteria) 4.1.5 Externalities (Level-1
criteria) 4.1.6 Internalities (Level-1 criteria)
5.1 Overview of Ship Dismantling Process 5.2
Modelling of the Ship Dismantling Facility 5.3
Development of Layout Variants for the SD
Facility 5.4 Selection of Candidate Layouts for
Generic SD Facility
5.3.1 Modelling Principles of the Generic
Facility 5.3.2 Variant No.0 Baseline
Layout 5.3.3 Variant No.1 Wet
Basin 5.3.4 Variant No.2a Pier 5.3.5 Variant
No.2b Pier with central zone 5.3.6 Variant
No.2c Sideways pier 5.3.7 Variant No.3 Dry
dock 5.3.8 Variant No.4 Floating
dock 5.3.9 Variant No.5 Slipway 5.3.10 Variant
No.6 Ship-lift
6.1 Development of Initial Scenarios List and
Shortlisting 6.2 Main Technology Scenarios
7.1 Outline of the Capacity Evaluation
Methodology Adopted 7.2 Dynamic Simulation
8.1 De-coating Area 8.2 Primary Dismantling Zone
(Major Block Breaking) 8.3 Secondary Dismantling
Zone (Sub-block Breaking) 8.4 Hazardous Waste
Storage Areas 8.5 Non-hazardous Waste Storage
Areas 8.6 General Storage Areas
11.1 Layout Scorecard
11.1.1 Part 1 Sketch of Layout
Variant 11.1.2 Part 2 Layout Scorecard
213.3 Guidelines for Processes and Operations
- Available Background Knowledge ()
- Technical Guidelines by the Secretariat of the
Basel Convention - Safety and Health in Shipbreaking Guidelines, by
ILO - Implementation of EMS by OECD
- Regulatory Compliance Guide by EPA-USA
- Ship Recycling Process Draft Guidance by DEFRA,
UK - Ergonomic Interventions for Shipbreaking
processes by US-DHHS - Rules (WAC) for Shipbuilding, Ship repairing and
Shipbreaking, Washington State Department, Labor
and Industry - () Contents lists provided as an Annex of D4.1
22Work being done
- Second stage of Task involves modification of
Simulation models created in 4.1.6 - ST 4.2.4 simulation for Full-SD
- ST 4.3.3 simulation for Partial-SD
23WP4 Task Relations
T4.1 Generic Guidelines
Evaluation of Alternatives
Background Knowledge - SoA Guidelines
Hierarchy of Objectives
D4.1 Generic Guidelines
Layout Scorecard
Technology scenarios Layout variants
Technology scenarios Layout variants
T4.3 Optimisation Partial SD
T4.2 Optimisation Full SD
Simulation Model
updated
updated
D4.2 LEYAL
D4.3 NASOL
Product Data - Case ship
Manning requirements
24Simulation Model(s)
Process Specifd Models (UGS)
Generic Model (UoP)
Revenue of Value Streams
Hazardous Materials
Mobile Shrear
Liquids Flow
25SimModel Liquids Flow
26Model Output gt Decision Support
Simulation Model
27SimModel Revenue of Value Streams
28SimModel Revenue of Value Streams Model Output
gt Decision Support
- Unit Cost Info for Value Streams
- Steel
- Copper
- Zinc
- Bronze
- Machinery
- Electrical
- Joinery
- Minerals
- Plastics
- Liguids
- Chemicals/gas
- Plastics
- Others
- Cost and Revenue calculation for Value Streams
- Steel
- Copper
- Zinc
- Bronze
- Machinery
- Electrical
- Joinery
- Minerals
- Plastics
- Liguids
- Chemicals/gas
- Plastics
- Others
Simulation Model
29SimModel Mobile Shear for ShipDismantling
30