Title: Planning III Estimating Software Size


1
Topic 5
  • Planning III Estimating Software Size
  • ??? ?????? ???

2
Lecture Overview
  • 5.1 Background
  • 5.2 Popular Estimating Methods
  • 5.3 Proxy-based Estimating
  • 5.4 The PROBE Size Estimating Method
  • 5.5 Object Categories
  • 5.6 Estimating Considerations
  • 5.7 Summary
  • 5.8 Exercises

3
5.1 Background
4
5.1 Background 1
  • Why Estimate Size?
  • Size estimates allow you to make better plans.
  • Plan better for the resources, tasks, and
    schedule.
  • The quality of a plan depends on that of the size
    estimate.
  • The more details you have, the more accurate the
    estimation will be.
  • For a large software job, divide it into separate
    elements.
  • Size estimates assist you in tracking progress.
  • You can
  • judge when the job scope changes.
  • better measure the work.

5
Background 2
  • Estimating models in other fields
  • have a large historical base.
  • are widely used.
  • generate detailed planning data.
  • require a size estimate as input.

6
Project Planning Framework
  • The framework is shown in Figure 5.1.
  • Size estimating compare the design elements with
    the historical size data to make estimates.
  • Accurate size estimation will lead to accurate
    resource estimation.

7
Fig. 5.1 Project Planning Framework
8
Estimating Experience
  • Studies show that
  • size estimation errors may be as high as 100 or
    even more.
  • Only 22 professionals make estimates.
  • Usually people have a larger estimation error
    percentage (up to 400) in early phase, and then
    the percentage declines (25 or less) in later
    phases.
  • Serious size estimation errors result in poor
    resource estimates and unrealistic project
    schedules.
  • Fortunately, the size estimation skill can be
    learned and improved.

9
Size Estimating Criteria
  • A widely used method should be
  • structured and trainable.
  • usable during all development and maintenance
    phases.
  • usable for all types of software product
    elements.
  • suitable for statistical analysis.
  • adaptable to the types of your future work.
  • able to judge the accuracy of the estimates.

10
5.2 Popular Size Estimating Methods
11
5.2 Popular Size Estimating Methods
  • Four popular methods
  • Wideband-Delphi
  • Fuzzy-Logic
  • Standard-Component
  • Function-Point
  • Their concepts form the foundation of the PROBE
    (Proxy-based Estimating) method used with the PSP.

12
Wideband-Delphi Method 1
  • Originated by Rand Co. and refined by Boehm.
  • Based on the Delphi process, which usually
    contains several cycles.
  • Several experts (estimators) and a moderator are
    involved in the process.
  • Each expert makes an independent estimate and
    submit it to the moderator in each cycle.
  • The moderator coordinates the estimation process
    for these experts whose estimates are anonymous
    to all others.
  • The process runs until experts estimates
    converge on a consensus result.

13
Wideband-Delphi Method 2
  • The methods process is as follows
  • A group of experts is each given the programs
    specifications and estimation forms.
  • They meet to discuss project goals, assumptions,
    and estimation issues.
  • They then each anonymously list project tasks and
    estimation size.
  • The estimates are given to the moderator, who
    tabulates the results and returns them to the
    experts, as illustrated in Figure 5.2.

14
Fig. 5.2 The Chart Used in Wideband-Delphi
15
Wideband-Delphi Method 3
  • Only each experts personal estimate is
    identified all others are anonymous.
  • The experts meet to discuss the results. They
    each review the tasks they have defined but not
    their size estimates.
  • The cycle continues at step 3 until the estimates
    converge to within an acceptable range.

16
Wideband-Delphi Method 4
  • Advantages
  • can produce accurate results
  • uses organizations skills
  • works for any size products.
  • Disadvantages
  • relies on a few experts
  • time consuming
  • subject to common biases

17
Fuzzy-Logic Method 1
  • Estimators compare the planned program with prior
    programs and select the most appropriate size
    category.
  • Preparing for this method
  • gather sufficient size data on previously
    developed programs
  • subdivide these data into size categories and
    subcategories
  • provide a meaningful number of program examples
    in each size category and subcategory
  • extend the size ranges up or down as you get
    further data
  • Table 5.1 shows the example.

18
Table 5.1 Example for Fuzzy-Logic Method
19
Fuzzy-Logic Method 2
  • Advantages
  • based on relevant historical data
  • easy to use
  • requires no special tools or training
  • provides reasonably good estimates in cases where
    new work is like prior experience

20
Fuzzy-Logic Method 3
  • Disadvantages
  • requires a lot of data
  • requires that the estimators be familiar with the
    historically developed programs
  • provides only a crude sizing
  • not useful for new program types
  • not useful for programs that are much larger or
    smaller than the historical data

21
Standard-Component Method 1
  • Use organizations historical data to determine
    the typical size of various types of components
  • subsystems, modules, screens, reports, etc.
  • For a new project
  • Judge the number of each type of components will
    likely be in the project.
  • Also determine the maximum and minimum numbers of
    each type of components you could image.

22
Standard-Component Method 2
  • Calculate the estimated number of each type with
  • (4likely number max. number min. number) / 6
  • The estimated size of each type is
  • its estimated number its typical size from
    historical data
  • Sum up the estimated size of all types to get the
    total size.

23
Table 5.2 Example of Component Estimating
For modules, its estimated size 932 17.5
16310.
24
Standard-Component Method 3
  • Advantages
  • based on relevant historical data
  • easy to use
  • requires no special tools or training
  • provides a rough estimate range
  • Disadvantages
  • must use large components early in a project
  • limited data on large components
  • hard to visualize component counts early in a
    project

25
Function-Point Method 1
  • Count the numbers of the 5 types of basic
    functions that the commercial application program
    will likely need by reviewing its requirements.
  • Inputs screens or forms through which to add new
    data or update existing data in the application
  • Outputs screens or reports that the application
    produces
  • Inquires screens used to ask for interrogation,
    assistance or information
  • Data files logical collection of records that
    the application updates
  • Interface e.g., files shared with other
    applications, shared databases, parameter lists,

26
Function-Point Method 2
  • Each type has a given weight.
  • Calculate the function points of the application
  • multiply the number of each type by its weight.
  • sum them up to get the total (unadjusted).
  • Use historical data on development cost and time
    per function point to make the estimates.

27
Table 5.3 Function-Point Categories
28
Table 5.4 Function-Point Category Example
29
Function-Point Method 3
  • To improve the estimation, adjust the function
    points by 14 influence factors.
  • The influence factor values are selected from 0
    (very simple) to 5 (very complex) by the judgment
    of the estimator.
  • Sum up these values.
  • Calculate the complexity multiplier
  • 0.650.01(sum of influence factor values)
  • Calculate adjusted function points
  • complexity multiplier unadjusted function
    points
  • The adjustment is between 35
  • Table 5.5 shows an example.

30
Table 5.5 An Example of Function-Point Influence
Factors
31
Function-Point Method 4
  • Advantages
  • a well-documented method
  • usable in the earliest requirements phase
  • independent of programming languages, product
    designs, development styles
  • having a large body of historical data
  • with an active user group

32
Function-Point Method 5
  • Disadvantages
  • cannot directly count an existing products
    function point content
  • without historical data, difficult to improve
    estimating skill
  • not reflect language, design, and style
    differences
  • designed for estimating commercial data
    processing applications

33
5.3 Proxy-based Estimating (PROBE)
34
5.3 Proxy-Based Estimating (PROBE)
  • In stead of direct estimating, a proxy is a
    substitute to help estimators judge product size.
  • Proxies, for example, can be objects, screens,
    files, scripts, document chapters, function
    points, and so on.

35
Criteria for a Good Proxy 1
  • The proxy size measurement (or estimate) should
    closely relate to the effort required to develop
    the product.
  • Use the correlation method (see Topic 15) to
    determine which proxy is a better predictor of
    product size or development effort.

36
Criteria for a Good Proxy 2
  • The proxy content of a product should be
    automatically countable.
  • Large amount of proxy data extracted from
    historical data is needed to define new
    estimates.
  • The proxy must be a physical entity that can be
    precisely defined and algorithmically identified.

37
Criteria for a Good Proxy 3
  • The proxy should be easy to visualize at the
    beginning of a project.
  • The proxy should be customizable to the special
    need of using organizations.
  • Different product types may use different kind of
    proxies to estimate.
  • The proxy should be sensitive to any
    implementation variations that impact development
    costs or efforts.
  • for example, program languages, design styles,
    application types

38
Objects as Proxies 1
  • Objects in OO programming languages are a good
    candidate as proxies because they closely relate
    to development effort or resources.
  • Figures 5.3 and 5.4 show close correlation
    between estimated object LOC (Sobject size ) and
    actual program LOC.
  • Linear regression formula (See Topic 15 )
  • actual program LOC ß0 estimate object
    LOC ß1
  • Figures 5.5 and 5.6 show high correlation and
    significance between estimated object LOC and
    actual development hours.
  • Linear regression formula
  • actual development hours ß0 estimate
    object LOC ß1

39
Objects as Proxies 2
  • The PROBE method uses objects as proxies.
  • The PROBE method requires that estimators have
    historical data on the sizes of objects they have
    developed and that these data be divided into
    categories.

40
Fig. 5.3 Estimated Object LOC vs. Actual Program
LOC (10 Pascal Programs)
41
Fig. 5.4 Estimated Object LOC vs. Actual Program
LOC (25 C Programs)
42
Fig. 5.5 Estimated Pascal Object LOC vs. Actual
Development Hours with Correlation
0.934, Significance lt 0.005
43
Fig. 5.6 Estimated C Object LOC vs. Actual
Development Hours with Correlation
0.980, Significance lt 0.005
44
Estimating Object Size with Fuzzy-Logic Method
  • Judge the size of each object on a per-objects
    method basis with fuzzy-logic method.
  • decide the category of the object
  • judge how many methods it likely will contain
  • decide the size range it falls into
  • estimated object size ( of methods) (LOC of
    the size range)
  • Table 5.6 shows object category sizes in LOC
    per-objects method
  • For example, a medium-sized Pascal text object
    with 4 methods has about 66 (16.484) LOC.

45
Table 5.6 Object Category Sizes in LOC per Method
46
5.4 The PROBE Size Estimating Method
47
5.4 The PROBE Size Estimating Method
  • The PROBE size estimating procedure is shown in
    Figure 5.7.
  • In the procedure, a size estimating template,
    shown in Table 5.7, will be used.
  • Use the template to instruct how to estimate
    program size with the PROBE method and linear
    regression.

48
Fig. 5.7 The Procedure of PROBE Method
49
Table 5.7 Size Estimating Template and example 1
50
Table 5.7 Size Estimating Template and example 2
51
Size Estimating Template 1
  • Base Program the program you will enhance and
    perform any changes to it.
  • Base Size (B) the LOC of the base program
  • LOC Deleted (D) the LOC to be deleted from the
    base program
  • LOC Modified (M) the LOC to be modified in the
    base program

52
Size Estimating Template 2
  • Projected LOC (P) includes total base additions
    LOC (BA) and total new objects LOC (NO)
  • Base Additions the new functions to be added to
    the base program
  • New Objects the new objects to be added to the
    base program
  • New Reused Objects a new object planned to
    develop and general enough to put into the reuse
    library
  • (Note mark an with the new reused objects)
  • Reused Objects (R) the objects taken from the
    reuse library

53
Size Estimating Template 3
  • Calculations
  • Using actual new and changed LOC and estimated
    Object LOC (i.e., PM) from historical data to
    obtain regression parameters ß0, ß1
  • Estimated New and Changed LOC (N) use regression
    parameters to calculate
  • N ß0 ß1 (P M)
  • Estimated Total LOC (T) the estimated size of
    the final program

54
Size Estimating Template 4
  • Prediction Range using t distribution (See
    Section 15.5.2), a desired prediction interval
    percent, and the data for linear regression to
    calculate
  • Lower/Upper Prediction Interval the interval (N
    Range) within which the actual new and changed
    LOC is likely to fall
  • Prediction Interval Percent the percentage that
    the actual new and changed LOC is likely to fall
    within the interval

55
PROBE Step 1 Conceptual Design
  • The conceptual design establishes a preliminary
    design approach and names the expected product
    objects and their functions.
  • For an accurate estimate, estimators must refine
    the conceptual design to the level of objects.

56
PROBE Step 2 Identify Objects
  • Determine object type and size
  • if it is a new object, use fuzzy-logic method
    (see Section 5.3)
  • of methods (judging size using a per-method
    basis)
  • object type
  • relative size
  • LOC per method
  • estimated object size ( of method) (LOC per
    method)
  • (Note mark an with the new reused objects)
  • if the object is taken from the reuse library,
    determine
  • reuse object categories
  • object LOC

57
PROBE Step 3 Calculate Projected and Modified
LOC
  • Projected LOC (P)
  • Total Base Additions LOC (BA)
  • Total New Objects LOC (NO)
  • Using actual new and changed LOC and estimated
    object LOC (i.e., PM) from historical data to
    obtain regression parameters ß0, ß1
  • Estimated New and Changed LOC (N)
  • ß0 ß1 (PM)

58
PROBE Step 4 Estimate Program Size
  • Estimated program size
  • Base Size (B)
  • Estimated New and Changed LOC (N)
  • Reused Total LOC (R)
  • LOC Deleted (D)
  • LOC Modified (M)
  • LOC Modified (M) is subtracted because it is
    counted twice one in Base Size (B) and the other
    in Estimated New and Changed LOC (N).

59
PROBE Step 5 Calculate Prediction Interval 1
  • The purpose is to assess the quality of the
    estimate.
  • Use t distribution, a desired prediction interval
    percent, and the data for linear regression
    calculation to get
  • Prediction Range
  • Prediction Interval LPI, UPI
  • Within the prediction interval, the actual new
    and changed LOC is likely to fall with the
    selected percent.

60
PROBE Step 5 Calculate Prediction Interval 2
  • Prediction Interval LPI, UPI
  • Lower Prediction Interval (LPI)
  • Estimated New and Changed LOC (N) -
    Range
  • Upper Prediction Interval (UPI)
  • Estimated New and Changed LOC (N)
    Range

61
PROBE Step 5 Calculate Prediction Interval 3
  • Prediction Range using the data for linear
    regression calculation in Step 3
  • Where
  • xi is the estimated object LOC (i.e., PM) in
    historical data
  • xavg is the average of xi
  • xk is the estimated object LOC (i.e., PM) in the
    new program
  • yi is actual new and changed LOC in historical
    data

62
5.5 Object Categories
63
5.5 Object Categories
  • The PROBE method uses objects as proxies. It
    needs object categories and their sizes to judge
    the size of the new objects.
  • Table 5.6 shows the example that we want to
    produce.
  • for C and Object Pascal
  • object sizes per method are divided into 5 size
    ranges very small, small, medium, large, and
    very large.

64
Object Size Distribution
  • Assume historical object data are normally
    distributed.
  • Figure 5.8 shows the relation between the normal
    distribution and the size ranges.

65
Fig. 5.8 Normal Distribution with Size Ranges
s
66
Approaches
  • Two approaches
  • If the size data are close to normal
    distribution, use normal distribution in the
    calculation .
  • Otherwise, use normal distribution of natural log
    in the calculation.

67
Approach I Procedure with Original Data
  • Use historical data on objects
  • divide them into categories
  • calculate the size range midpoints for each
    category.
  • use statistical techniques of normal distribution
    in the calculation
  • The following is the procedure

68
Step 1 Classification
  • Divide objects in historical data into
    categories.
  • Basic object categories
  • logic, control
  • I/O, files, display
  • data, text, calculation
  • set-up, error handling

69
Step 2 Calculating LOC per Method
  • For each category, calculate the LOC per method
    of each object.
  • Table 5.9 shows the example for 13 objects
    belonging to the object category, text.

70
Table 5.8 Pascal Text Object LOC per Method
71
Step 3 Calculating Standard
Deviation
  • For each category, calculate the variance and
    standard deviation of the values from Step 2.
  • Variance s2 (1/n) ?i1..n(xi xavg )2
  • Standard Deviation v of Variance s
  • where xi (LOC per method) of each object of
    one specific category xavg denotes the average.
  • The following table shows the example.

72
Table 5.9 Pascal Text Object Standard Deviation
73
Step 4 Calculating Size Range
Midpoints
  • For each category, use the average xavg and
    standard deviation s to calculate the size range
    midpoints
  • VL xavg 2s
  • L xavg s
  • M xavg
  • S xavg s
  • VS xavg - 2s

74
Negative Size Range Midpoints
  • Table 5.10 shows the example of the size range
    midpoints and the 13 object sizes per method.
  • However, in this example, the VS midpoint is a
    negative number, which is not what we want and
    means that the object data are not normally
    distributed.

75
Table 5.10 Pascal Text Object and Size Ranges
76
Approach II Procedure with Natural Log of
Original Data
  • The trick to handle the negative size range
    midpoint is to calculate the natural log of the
    data.
  • The following is the procedure with the first 2
    steps same as the previous procedure.

77
Step 3 Calculating the Natural Log
and Average
  • For each category, calculate the natural log (ln)
    of the LOC per method of each object, and the
    average, avgln, of these log values.
  • Table 5.11 is the example for object category,
    text.

78
Table 5.11 Pascal Text Object ln (LOC per Method)
79
Step 4 Calculating Standard
Deviation
  • For each category, calculate the variance and
    standard deviation of these log values.
  • Variance s2 (1/n) ?i1..n(xi xavg )2
  • Standard Deviation v of Variance s
  • where xi ln (LOC per method) of each object
    of a category.

80
Step 5 Calculating the Log of Size
Range Midpoints
  • For each category, use average of log values and
    standard deviation to calculate the log of size
    range midpoints
  • ln(VL) avgln 2s
  • ln(L) avgln s
  • ln(M) avgln
  • ln(S) avgln s
  • ln(VS) avgln - 2s

81
Step 6 Calculating the Antilog
  • For each category, calculate the antilog to get
    the midpoints of the size ranges
  • VL eln(VL)
  • V eln(L)
  • M eln(M)
  • S eln(S)
  • VS eln(VS)
  • Table 5.12 shows the example of the size range
    midpoints and the 13 object sizes per method.

82
Table 5.12 Pascal Text Objects and Size Ranges
83
5.6 Estimating Considerations
84
5.6 Estimating Considerations 1
  • The PSP estimating objective is to improve your
    estimating ability by tracking and analyzing your
    estimates.
  • If your estimating process is stable, the linear
    regression method, based on the historical data
    gathered from consistently biased estimates, can
    make an accurate bias adjustment.
  • While you gain more experience and your process
    evolves, you should adjust your statistical
    calculations to include only the newer and more
    representative data and drop the old ones.

85
Estimating Considerations 2
  • Whenever your linear regression parameters appear
    unreasonable (e.g., ß1 far from 1.0, large ß0 ),
    use the averaging method to estimate.
  • This method uses a ratio to adjust size or time
    based on historical averages.
  • estimated program LOC estimated object LOC
    ratio
  • where ratio historical average
  • ?(final program LOC) / ? (estimated
    object LOC)

86
Estimating Considerations 3
  • To use the linear regression method, you must
    have at least three programs for which you have
    made object LOC estimates.
  • If you have at least three programs but enough
    historical estimate data,
  • obtain ß0 and ß1 from your actual size data
  • If you do not have enough historical data but at
    least one program,
  • use the averaging method

87
Estimating Considerations 4
  • You can learn to reduce the estimating bias by
    comparing, during postmortem, estimates made at
    each phase with their actual size.
  • To estimate unprecedented products, the best
    answer is to resist making firm estimates until
    you have completed a feasibility study and build
    some prototypes.

88
5.7 Summary
89
5.7 Summary 1
  • Accurate size estimate will help you to make
    better development plans.
  • Size estimating skill improve with practice.
  • A defined and measured process provides a
    repeatable basis for improvement.

90
Summary 2
  • With PROBE, estimates are based on one of
    following four methods
  • Method A regression with estimated object LOC
  • Method B regression with estimated new and
    changed LOC
  • Method C size or time adjustment based on
    historical averages (the averaging method)
  • Method D engineering judgment

91
Summary 3
  • Method A regression with estimated object LOC
  • use the relationship between estimated object LOC
    and
  • actual new and changed LOC
  • actual development time
  • The criteria for using this method are
  • 3 or more data points that are correlated (r2 gt
    0.5)
  • Reasonable regression parameters

92
Summary 4
  • Method B regression with estimated new and
    changed LOC
  • use the relationship between estimated new and
    changed LOC and
  • actual new and changed LOC
  • actual development time
  • The criteria for using this method are
  • 3 or more data points that are correlated (r2 gt
    0.5)
  • Reasonable regression parameters

93
Summary 5
  • Method C adjusting size or time based on
    historical averages.
  • the averaging method
  • easy to use
  • used when linear regression parameters (ß0, ß1)
    appear unreasonable (that is, methods A and B can
    not be used)
  • assuming that there is no fixed overhead
  • The criteria for using this method are
  • At least one data point is required.

94
Summary 6
  • Method D engineering Judgment with estimated
    object LOC
  • used in absence of historical data
  • using judgment from estimated object LOC to
    estimate
  • actual new and changed LOC
  • actual development time
  • used when methods A, B, and C can not be used

95
5.8 Exercises
96
Program 3A 1
  • Use PSP0.1 (see Appendix in Topic 4) to write
    program 3A.
  • Program 3A Requirements
  • Write a program to count
  • the total program LOC
  • the total LOC in each object
  • the number of methods in each object
  • If an object-oriented program is not used as the
    input, count
  • the total program LOC
  • the total LOC in each procedure or function

97
Program 3A 2
  • Use the counting standard produced by report
    exercise R1.
  • It is acceptable to enhance program 2A or to
    reuse some of its methods, procedures, or
    functions in developing this program.
  • Program 3A Testing
  • Thoroughly test the program.
  • At a minimum, test program 1A, 2A, and 3A.
  • Prepare a test report that includes a table as
    the format in Table 5.11.

98
Table 5.11 Test Result Format ? Program 3A
a) Format for object-oriented program designs
b) Format for non object-oriented program designs
99
Program 4A 1
  • Use PSP1 (see Appendix in this topic) to write
    program 4A.
  • Program 4A Requirements
  • Write a program to calculate the linear
    regression size-estimating parameters

100
Program 4A 2
  • Use the historical data of a set of n programs
    object LOC, xi, and new and changed LOC, yi.
  • Enhance the linked list of program 1A to hold the
    n data records, where each record has 2 real
    numbers.

101
Program 4A 3
  • Program 4A Testing
  • Thoroughly test the program.
  • At a minimum, test it with the 3 cases shown in
    Table 5.12
  • use the data for estimated object LOC and actual
    new and changed LOC.
  • use the data for estimated new and changed LOC
    and actual new and changed LOC.
  • use the data, estimated new and changed LOC and
    actual new and changed LOC, you have gathered for
    the programs 2A, 3A and 4A you have developed.
  • Prepare a test report that includes a table as
    the format in Table 5.13.

102
Table 5.12 Size Estimating Regression Data
 
103
Table 5.13 Test Result Format ? Program 4A
104
Appendix PSP 1
105
PSP1 Process Script 1
106
PSP1 Process Script 2
107
PSP1 Planning Script 1
108
PSP1 Planning Script 2
109
PSP1 Development Script 1
110
PSP1 Development Script 2
111
PSP1 Postmortem Script 1
112
PSP1 Postmortem Script 2
113
Size Estimating Template 1
114
Size Estimating Template 2
115
Test Report Template
116
PSP1 Project Plan Summary 1
117
PSP1 Project Plan Summary 2