Title: PGE Delivery and Data Processing Plans for the Version 4.0 Software Release
1PGE Delivery and Data Processing Plansfor
theVersion 4.0 Software Release
- Steven Friedman
- AIRS Science Processing
- March 30, 2004
2Topics
- Version 4.0 Schedule
- Version 4.0 Data Processing Plans
- Routine Data Processing at GSFC DAAC
- Data Processing at AIRS TLSCF
- Version 4.0 Reprocessing Considerations
3 Strange Archeological Sites in the LA Area
4Version 4.0 Schedule Key Objectives
- Version 4.0 to include enhanced validation
coverage area - Extends coverage to land areas
- Expands latitude range beyond ?40
- Feature Set Enhancements to include
- Level 1
- AIRS IR Calibration enhancements - New gains,
limits, etc. Geolocation, Potential
algorithmic upgrades (?) - Microwave Calibration enhancements,
Algorithmic upgrades (?) - Level 2 the key ingredient to V4.0
- Further improvement beyond V3.0 and V3.5
baselines - Incorporates many performance enhancements
- Includes better retrieval algorithm, handling of
outliers, QA - Final feature set must be solidified by early
summer!
5V4.0 Timeline
6Version 4.0 Milestones
- V4.0 Next Release to DAAC NOAA
- Prototyping Ends 6/01/04
- Final Inputs to CCB 6/01/04 Last day to propose
updates - Development Period Ends 7/05/04
- Initial Build V4.0 7/06/04 Anomalies / small
changes - V4.0 Operational Begin Validation
DP 7/21/04 Critical anomalies ONLY! - Delivery to DAAC NOAA 8/31/04
- V4.0 Operational Begin Processing 9/30/04
- V3.5 Interim Release to NOAA 4/16/04 Improved
L2, QA - V3.7 Internal JPL Benchmark 5/03/04 L3 Test,
L2 In-process
- Please keep in mind
- All scheduled milestones are established to
ensure that we deliver a quality V4.0 product on
schedule. - There will always be new and better improvements,
and there are other releases planned for the
future.
7Routine Data Processing at the GSFC DAACwith V4.0
- With V4.0 the GSFC DAAC will process
- Level 0 through Level 2 PGEs Browse PGEs
- Level 1B calibrated radiances, QA subsets,
daily browse - Level 2 retrieval standard,, retrieval
support, CC radiances daily browse (retrieval
and CC) - Level 3 PGE 3 new standard products for V4.0
- Daily, 8-day, and monthly additional products
planned for later releases - Subsetted data sets
- Considering developing new subsetted radiance
data sets
8Routine Data Processing at the GSFC DAACwith
V4.0 (contd.)
- With V4.0 the GSFC DAAC will also process
- Match-Up PGE (products delivered to JPL ONLY!)
- Radiosonde Match-Up supports trending analysis
- Fixed-location Match-Ups
- Dedicated Validation Sites
- 5 special validation sets ACAR, ACFT, Dobson,
Dobson_P, Yoe - No Dynamic Match-Ups will be performed at the
GSFC DAAC a new fixed-location Match-Up is
being developed fixed buoys
9Data Processing at the AIRS TLSCFwith V4.0
- Beginning with V4.0 the JPL TLSCF will
- Stop baseline processing Level 0 through
Level 1B Match-Up - Continue to process Focus Days (nominally, 48-day
intervals) starts with Level 0 producing the
following products - Level 1A all AIRS, AIRS VIS, and AMSU products
- Level 1B calibrated radiances, QA subsets, daily
browse - Level 2 retrieval standard, CC radiances,
retrieval support, daily browse (retrieval
and CC) - Level 3 daily product
- Continue to process other data as necessary
- Support continued software development test
- Support validation campaigns
- We will order additional Level 0 and/or Level 1B
as needed
10Data Ingest at the AIRS TLSCFwith V4.0
- Beginning with V4.0 the JPL TLSCF will
- Stop ingesting Level 0 from the GSFC DAAC on a
daily basis - Continue ingesting Level 0 from the GSFC DAAC for
- All Focus Days
- Special campaigns
- Continue ingesting products from the GSFC DAAC
- All Level 2 standard retrieval products
- All Daily Browse Products Level 1B and Level 2
- Radiosonde Match-Up Products
- Occasionally ingest 20 granules of all Levels 0,1
and 2 products(support spot checking) - Begin ingesting Level 3 and fixed-site Match-Up
Products - Continue ingesting selected granules from NOAA
NRT process
11Processing and Reprocessing at the GSFC DAAC
with V4.0
- GSFC DAAC will begin processing with V4.0 when
the release becomes operational - All forward processing will be performed with
V4.0 - Reprocessing will commence providing coverage
back toAugust 31, 2002 and can be accomplished
by - Marching backwards towards August 31, 2002? or
- Marching forwards from August 31, 2002?
- Reprocessing includes rerunning all data from
Level 0 Performs Level 1A 1B, Level 2,
Match-Up and Browse PGEs - For AIRS, allocated processing resources are 3x
- 1x dedicated to forward processing
- 2x dedicated to reprocessing
- It will take approximately 1¼ years to complete
reprocessing(may be less time, given Level 2
performance improvements)
12Reprocessing Considerations after V4.0
- After V4.0, reprocessing will not keep up with
annual upgrades - Continuous improvement of PGEs, delivered to DAAC
on an incremental basis deliveries scheduled
annually - Our desire to produce the best possible product
versus the DAACs desire to produce complete
collections - Something has to give and processor resources
are fixed - Either we hold back deliveries to pace
reprocessing or we consider a hybrid
approach after V4.0 - Could we consider stabilizing Level 1A(?) and
Level 1B(?) with V4.0 until the last reprocessing
cycle at end of mission? - Allow table upgrades, but delay science algorithm
changes - Would dedicate processor resources to Level 2
reprocessing
13V3.0 Reprocessing Status at the GSFC DAAC
- Processing status as of March 22, 2004
2004
2003
Calendar Day of Year
Solid bars indicate unprocessed data.
14(No Transcript)