Title: Noise Prototype Development Plan
1 Noise Prototype Development Plan University of
Birmingham David Hoyland Senior Electronics
Design Engineer Astrophysics and Space Research
Group
2 Key Events and Milestones
- Now
- Conceptual Design is underway
- January 04 Approve Design Concept
- Start Detailed Design
- Development Prototype part manufacture
- OSEM Manufacturing Study
- February 05 Choose OSEM manufacturer
- Produce mfg data and test procedures
- Design Test Jigs and Fixtures
- September 05 PDR
- October 05 OSEM manufacturing contracts placed
- Procurement
- Manufacture Test Jigs and Fixtures
- Noise prototype Manufacture (Electronics
manufacture totally in house) - April 06 Quad Suspension OSEM and Electronics
Delivery - To Coincide with Quad assembly at RAL (start
13/4/6) - June 06 Triple suspension OSEM and Electronics
Delivery - To coincide with Triple assembly at LASTI (start
2/6/06)
3Simplified OSEM Noise Prototype Production Plan
Choose Industrial Manufacturing Partners
Agree Manufacturing And test Flow and
understand any Limitations
Productionise to suit Manufacturing process
Detailed Design/Prototype
Generate Production Data Package
OSEM Production Data to RAL
Analyse any Production problems
Produce 209 Noise Prototypes
Produce 60 Noise Prototypes
OSEM Manufacturing partners to be chosen by
UOB/RAL
4Simplified Noise Prototype Electronics Production
Plan
Productionise to suit SMT/reflow/thro
hole Manufacturing process
Detailed Design/prototype
Generate Production Data Package
Prep for main Production
Produce 40 8 Noise Prototypes Channels
Analyse Production Yield
5Development Plan Details