Title: FY09 Tactical Plan Status Report for Engineering Support
1FY09 Tactical Plan Status Report for Engineering
Support
Engineering Doc 2819
Engineering Support Doc 2241
- Gustavo Cancelo
- March 31, 2009
2Resolution of Past Action Items
- Action items
- Nova DAQ timescale and available resources. Needs
software development to enable hardware work to
proceed. - We have resumed the engineering work for NOVA.
For software support, we were told that there'd
be computing professionals available some time
next spring/summer to work on it as other
projects are ramping down. - Issue Computing Facilities FTE request.
- Rick Kwarciany has spent 70 of his time on
Computing facilities. - Where does Simon K. go in budget?
- LHC scientific research and ESE dept Management.
3Summary of Project Performance(for the period
01-Oct-2008 through 31-March-09)
Project Deliverable / Milestone Initial Completion Target Complete (0,25,50,75,100) Current Completion target or milestone
CDF D0 Ongoing 95 of budgeted When TeV turns off.
CMS commissioning and upgrade Ongoing 44 of budgeted effort
NOvA Restarted in FY09 12 IPND Jan. 2010
COUPP FY09 60 By end of FY09
SNAP CCD test stand Ongoing 100 done
SNAP SOC Ongoing On schedule
Computing facilities Ongoing 62 of budgeted effort
4Summary of Project Performance(for the period
01-Oct-2008 through 31-March-09)
Project Deliverable / Milestone Initial Completion Target Complete (0,25,50,75,100) Current Completion target or milestone
PREP and Equipment Support Ongoing 66
Engineering Tools and RD Ongoing 25
Vertex Detector RD Ongoing 15 4 plane telescope in June 09
New initiatives RD Ongoing 3
Accelerator Electronics Operations RD Ongoing 41 CC2 and 1st cryomodule (NML) 4 spoke cavities (Proj. X) in FY09
ILC LLRF RD Ongoing 31 9mA test in Sept. 09
5Financial Performance FTE Usage
Level 0 Activity Engineering Support Engineering Support Engineering Support Engineering Support Engineering Support of FY Complete of FY Complete 41.65
Personnel Usage (FTEs)
Allocation Allocation Allocation Actual YTD Actual YTD Actual YTD Current
Tactical Plan Level 1 Activity FTE-yrs FTE-mos FTE-mos FTE-yrs (Ave/mo.) FTE-mos FTE-mos Consumed YTD FY09 Forecast
Engineering Support
CDF DZero 0.5 6.00 6.00 0.475 5.7 5.7 95 140
CMS Operations SLHC upgrade 3.33 39.96 39.96 1.45 17.4 17.4 44 100
NovA 1.75 21.00 21.00 0.21 2.52 2.52 12 100
COUPP 1.17 14.04 14.04 0.706 8.472 8.472 60 100
SNAP CCD test stand and SOC 1.33 15.96 15.96 0.582 6.984 6.984 44 100
Computing facilities 0.33 3.96 3.96 0.205 2.46 2.46 62 gt100
Vertex Detector RD 1.5 18.00 18.00 0.228 2.736 2.736 15 85
RD on New Initiatives 0.67 8.04 8.04 0.021 0.252 0.252 3 100
Engineering tools 1.08 12.96 12.96 0.265 3.18 3.18 25 100
PREP 2.83 33.96 33.96 1.856 22.272 22.272 66 130
Accel. Electronics Ops RD 1.75 21.00 21.00 0.71 8.52 8.52 41 100
ILC 9mA test at DESY-FLASH 0.5 6.00 6.00 0.17 2.04 2.04 34 90
Total 16.74 200.88 200.88 6.88 82.54 82.54 41.65
6Financial Performance MS (Internal Funding)
Level 0 Activity Engineering Support Engineering Support Engineering Support Engineering Support of FY Complete of FY Complete of FY Complete 50 50
Operating Equipment MS CD Internal Funding CD Internal Funding CD Internal Funding CD Internal Funding
Operations MS Operations MS Operations MS Operations MS Operations MS Operations MS Operations MS Equipment MS Equipment MS Equipment MS Equipment MS Equipment MS Equipment MS Equipment MS
Tactical Plan Level 1 Activity FY Obligation Budget YTD Obligations RIPS YTD Obligations RIPS Spent Spent Current FY08 Forecast Current FY08 Forecast FY Obligation Budget YTD Obligations RIPS YTD Obligations RIPS Spent Spent Current FY08 Forecast Current FY08 Forecast
ESE Tools 97000 55770 55770 57 57 100 100 0
PREP 15920 0 0 0 0 100 100 0
Department Infrastructure 82835 11830 11830 14 14 100 100 0
Accelerator RD
LLRF 12,100 0 0 0 0 100 100 0
Total Engineering Support 207,855 67600 67600 33 33 100 100 0 0 0
7Project Highlights, Issues, and Concerns
- CDF D0
- CDF load box completed.
- Load Box version 3 automates testing of CAEN high
voltage modules. It automates the manual testing
and can be remotely run by computer. It captures
and stores the measurements that previously had
to be hand entered. CDF was closely involved with
the specifications and design of this module so
it was maximally useful to them. - 6 built.
- 4 in use at CDF.
- 1 at ESE for software development.
- 1 spare.
- We are ready for shutdown activities
- CDF requested maintenance work on 70 more CAEN
power supplies. We have done this work before. It
will take 1 FTE month. The major issue is to
replace Hank Connor if hes not back at the time,
but Rick Malhum and Tom Boes are now up to speed
with this modules.
8Project Highlights, Issues, and Concerns
- NOvA
- Restarted previous hardware effort.
- Greg Deuerling replaces Bill Haynes on the timing
system. - We decided to use a common monitor processor for
both the DCM and timing system so adding DCM
processor to Timing Distribution Unit design. - GPS parts for IPND being acquired this month.
- Neal Wilcer is learning VHDL and will help
implementing the timing system firmware.
9Project Highlights, Issues, and Concerns
- SNAP CCD readout test stand.
- Completed. We developed a test card adapted for a
SNAP CCD, a preamplifier and a flex circuit for
inside the Dewar. - All projects were done on schedule. Met or
exceeded the expected performance and did not
need patches or second iterations. The FNAL SNAP
CCD packaging project leader, Tom Deihl sent an
email of acknowledgement to CD. - SNAP SOC.
- An 800 task WBS has been created for the
operations of the SOC. - Resource estimates are underway.
- Vince is collaborating with the DOE JDEM project
office at LBNL as they and NASA move towards a
mission definition.
10Project Highlights, Issues, and Concerns
- PREP and Equipment Support
- PREP added some CAMAC modules to upgrade
controller capabilities. - Need to look at high voltage capabilities for the
future - The steep slope at the beginning of 07 correlates
with smaller input queue. - Smaller fluctuations reflect normal experiment
request dynamics.
CDF emptied some cabinets and made the input
queue spike
11PREP metrics
- Steady flow of modules checked out. Average of
37.3 over last 12 month period. - http//cdorg.fnal.gov/ese/ESE_PREP_Metrics.html
- has information by user, FNAL division, project,
etc.
12Project Highlights, Issues, and Concerns
- COUPP
- Two COUPP LED Interface Modules (CLIM) running,
one at COUPP test stand. These are the snapshot
illumination for the cameras. - Camera interface CLIM boards mostly debugged.
Schedule to be deployed to the experiment next
week. - End of hardware development.
- We will support the collaboration software
development and testing.
13Project Highlights, Issues, and Concerns
- Computing facilities
- Data Center Management Rick Kwarciany working at
70 of his time. He generated an engineering
plan and WBS. - Currently working on over temperature shutdown
system. - Rick demoed a system prototype for facilities
group. Made changes to code as per suggestions
from the group. Worked with system installation
vendor to get needed information for bid. - The current bid is too high. We need to get
per-room cost below 30K.
14Project Highlights, Issues, and Concerns
- CMS commissioning
- Simon working on commissioning.
- Power Distribution for CMS Tracker Upgrades
- CAPTAN hardware developed for pixel device
performance impact studies under DC-DC conversion
power delivery. - Initial hardware testing performed with L. Perera
(University of Iowa). - Issue Testing may require acquisition of common
components such as used at CERN, Aachen, Bristol.
15Project Highlights, Issues, and Concerns
- Versatile Links Common Project (SLHC)
- Representative samples of optical transceivers
(850 nm, multimode and 1310 nm, single mode) have
been procured. - Automated test development for Versatile Links
Common Project (Characterization of Back End
Components). - Moving to parallel optics test development (array
transmitters and receivers) - Issue Testing limited or slowed by equipment.
Effort lacks modern test equipment for signal
integrity and jitter characterization at
multi-gigabit per second data rates.
16Project Highlights, Issues, and Concerns
- Vertex Detector RD
- CAPTAN DAQ developed to support FPIX2,1, PSI46
readout devices. Also supports FNAL RD devices
(Vertically Integrated Pixels). - Preparations being made for readout of
multi-plane system at Meson Test Facility. - CAPTAN system being purchased by INFN-Lecce for
Si Strips Test Beam Telescope Instrumentation - Presentation at TIPP09, IEEE Real Time 2009
Conferences.
17Project Highlights, Issues, and Concerns
- New initiatives RD
- LAr for Dark matter is interested in having an
ESECON based test stand in 6 month time. - µ2e experiment has talked to us about a similar
readout system. - Both experiments share some requirements high
number of channels, fast analog signal
acquisition and processing. - Fast timing system Erik Ramberg, Mike Albrow,
are both pursuing a fast timing system with
better than 10ps resolution. Given that for the
LLRF we measure phase, hence timing, with
femtosecond resolution we proposed a similar
system. But we have limited resources to work on
this. - The Axion experiment is interested in our signal
processing and feedback control expertise. Also
in our hardware. - REX (Margaret V.) is interested in our Queuing
theory expertise to look at some computer cluster
bottlenecks. Same problem, not enough effort
available. I proposed Margaret to use a summer
student under my supervision .
18Project Highlights, Issues, and Concerns
- New initiatives RD
- Low noise readout for Dark Matter and other
applications. We have done some data acquisition
and data analysis. This is for now a short RD
project that could develop in something important
is we have good results. - Project X RF leaders want to make sure that CD
continues participating of the LLRF effort for
Project X. A major problem is controlling the
Vector Modulators (also called Fast Phase
Shifters).
19Project Highlights, Issues, and Concerns
- Accelerator Electronics Operations RD
- ESECON 10 boards produced. All in good health.
- 3 ESECON based systems are running at A0.
- 1 ESECON based systems is running with HTS at
Meson. - 1 ESECON based systems deployed and tested
without RF at NML. This system is for CC2 which
was moved there and will become operational in
Mid May 09. - 1 ESECON working at DESY being considered for the
3.9GHz system. - 1 ESECON loaned to ANL running our own LLRF Real
Time Simulator. - No ESECON hardware failures after working
collectively for over 10 years. - Operations Main issue is that our Controls
software (DOOCS) developer left the lab. Ron R.
is providing support until AD finds a
replacement. - In the mean time AD Controls is generating an
ESECON interface for ACNET. - Other RD tasks continue with firmware
development and simulations.
20Project Highlights, Issues, and Concerns
- ILC LLRF RD
- Fermilab and in particular CD is a key component
of the ILC 9mA test at FLASH. We have contributed
with shifts at FLASH, data analysis and
suggestions to improve the LLRF. Other
collaborators are DESY, ANL, KEK and SLAC. - The final test is in September when FLASH will be
given to the ILC 9mA test group for 2 weeks time.
- We are not sure that the LLRF will perform well
when the machine is pushed to limits that was
never pushed before (high gradients, long RF
pulses, heavy beam loading and high pulse
repetition rate). Some LLRF systems there are 10
years old and have speed and noise issues. - All LLRF systems are operated at a small closed
loop gain which does not provide good disturbance
rejection. - There is a manpower shortage at DESY to upgrade
these systems but some upgrade is planned.
21Issues, and Concerns
- Budget issue
- 0 for training. Wed like to fix this. Also IQA
interviewers are telling us that we need to
emphasize training as a way of improving Q. - Office and lab space
- Building managers have requested Rooms 327a,
327b, 369a , 369b , 369c , 369d in use by ESE. - This space is in use and very active. One office
(Neal W.), the ESECON test stand, the NOVA test
area. It is also the area we use for guests,
students, summer students. Area where we have all
purpose soldering tools and microscopes. - Our ESE task force is very likely to increase
with a Bardeen fellow, a possible Guest Engineer
for the SCRF program, an one or 2 summer students
from Italy.
22Tactical Plan Status Summary
- Status Summary
- Budget in good shape.
- Effort is being used as planned.
- We need 100K in equipment for the Versatile Link
project. - Some money for training.
- We need to find a solution to the office space
problem.