Title: Summary of Issues Chesapeake Bay Program Water Quality Steering Committee Meetings
1Summary of Issues Chesapeake Bay Program Water
Quality Steering Committee Meetings
November 14, 2006
2Issues Covered in the Meeting
- Issue 1, 7 8 Issuance of the Bay TMDL
- Issue 9 Who leads the public participation
process? - Issues 11 12 Regulated and unregulated TMDL
loads simulated in the Chesapeake Bay Model and
the planned allocation to sources - Issue 23 Schedule for TMDL Development
3Issue 1Issuance of the Bay TMDL
4Issuance of the Bay TMDL - Overview
- Five Options
- Developed Individually by each State
- Developed Together Submitted Individually
- Developed by Virginia (or Bay States)
- Developed by EPA for all States
- Developed by the States and Submitted Jointly
- All Options States Working Together on TMDL
- EPAs Contractor Writes TMDL Report
- Only Requirement Approved Bay TMDL Established by
May 1, 2010 (VA) or 2011 (EPA)
5Issuance - Option 1 TMDL Developed individually
by Each State
- Advantages
- Flexibility to States in Composition
Presentation of TMDL - Demonstrates States Commitment to the Bay
- Disadvantages
- Legal Strength of Allocating Loads to Protect
Downstream Criteria - TMDL Contested in 7 States, 7 Different Opinions
on TMDL - Costs Associated 7 Defenses
- EPA Approves 7 TMDLs
- Goes Against Partnership Approach
- Appears States are Developing TMDL Alone
6Issuance Option 2 TMDL developed Together but
Submitted Individually
- Advantages
- Flexibility Scheduling TMDL Activities (e.g.,
public participation, submission and approval) - Disadvantages
- Legal Strength of Allocating Loads to Protect
Downstream Criteria - Goes Against Bay Partnership Approach
- TMDL Contested in 7 States, 7 Different Opinions
on TMDL - Costs Associated 7 Defenses
- EPA will need to approve 7 documents
7Issuance Option 3 TMDL Developed by Virginia
(or Bay States)
- Advantages
- One Document for Approval
- Streamline Public Participation Process (i.e.,
meetings only required in Virginia - Disadvantages
- Challenges Regarding VAs Authority in Upstream
Waters - Goes Against Bay Partnership Approach
- Stakeholders in Other States Limited Opportunity
to Comment - Negative Impact on Palatability of TMDL to
Stakeholders
8Issuance Option 4 TMDL Developed by EPA for
All States
- Advantages
- Strongest Against Legal Challenges Regarding
Upstream and Downstream State Criteria - Challenges in Federal Court Only
- One Opinion
- The Federal Record of Review Basis of Defense
- No Submission or Approval Process
- EPA Assist in Public Participation Process, State
Lead - Document Authored by one entity (EPA), Speak w
One Voice - Disadvantages
- Correspondence w Partnership Approach
- Comfort w Establishment of TMDL by Federal
Government
9Issuance Option 5 TMDL Developed by the States
and Submitted Jointly
- Advantages
- Applies Partnership Approach
- States Responsible for their Public Participation
- One Document for Approval
- Consistency in the TMDL report
- Demonstrates Commitment of all Bay States to WQ
in Bay - Disadvantages
- TMDL Contested in 7 States, 7 Different Opinions
on TMDL - Costs Associated 7 Defenses
- Coordination for Public Participation Difficult
Logistically
10Issuance Chosen Approach
- TMDL Developed by EPA for all States
- Strongest Option
- Easiest to Defend Protecting Downstream Criteria
- Subject to Federal Court Only
- Defended via Record of Decision
- One Decision
- Simplest Logistically
11Issue 5 Who Leads the Public Participation
Process?
12Who Leads the Public Participation Process?
- Four Options Lead Agency
- Each State in Charge of Own Public Outreach
- EPA Leads Public Outreach, State Representative
Present at their State Meetings - Public Outreach Led by each State EPA Region 3
Assistance - Virginia (Bay States) Leads Public Participation
13Option 1 Each State Leads Own Public Outreach
- Advantages
- Easiest Logistically
- Stakeholders Commenting to Their State Agency
- Disadvantages
- Ensure Each States Public Outreach Coincides w
TMDL Issuance - States EPA not Speaking w One Voice may have
Contradictions - Duplication of Work, Each State Drafting
Responses - Goes Against Partnership Approach
14Option 2 EPA in Charge of Public Outreach
- Advantages
- Logistically Simple
- Single Comment Response Period
- EPA Acts as Repository Comments Responds to All
Comments (Except on State Exclusive Issues) - Disadvantages
- Goes Against Partnership Approach
- EPA not as Experienced Working w Stakeholders as
States - Difficulty of EPA Regional Staff Coordinate
Participate in Meetings - EPA Viewed as Outsider
15Option 3 Public Outreach Led by Each State w EPA
Regional Assistance
- Advantages
- Familiarity w Stakeholders in Charge of Process
- TMDL Workgroup Responds to Comments Consistency
- States Formulate Own Public Outreach, EPA and
Contractor Attend Meetings Ensure Consistent
Messages - Coincides w TMDL Issued by EPA
- Disadvantages
- Multiple Jurisdictions Coordinating Outreach
- TMDL Workgroup Coordinating Responses, Might
Extend Response Time
16Option 4 Virginia (Bay States) in Charge of
Public Outreach
- Advantages
- Responsibility in Hands of One Agency, Simplifies
Logistics Reduces Conflicting Messages - Disadvantages
- Goes Against Partnership Approach
- VAs Lack of Experience Working w Other State
Stakeholders - Perception VA Dictating Actions in Upstream
Waters - Other States Stakeholders Excluded from Process?
- Not Consistent w Most TMDL Issuance Options
17Public Outreach - Chosen Approach
- Public Outreach Run by States w EPA Assistance
18The Amount of Outreach Efforts
- Options Number of Comment Periods
- Single Comment Period After Draft TMDL
- Multiple Comment Periods
- States Chooses Number of Comment Periods
19Option 1 Single Comment Period after Draft
- Advantages
- Simplest Option
- One Comment and Response Period
- Complies with EPA regulations for Public Outreach
- Disadvantages
- Less Opportunity for Providing Data Information
for Use in TMDL - Less Time to Build Consensus w Public
- Fulfillment to Public Outreach Process in All
States
20Option 2 Multiple comment periods
- Advantages
- Allows Solicitation of Additional Data
Information - Public Sees Impact of Comments on TMDL Process
- Addressing Concerns Early Lowers TMDLs
Susceptibility to Litigation? - Disadvantages
- Logistics
- Cost and Time Associated w Public Outreach
- Multiple Sets of Comments
- Opening Portions of TMDL to Public Comment that
Should Not Be - First Meetings Need to be Established Soon
- Is it to Early for Acknowledgement?
21Option 3 States choose number of comment periods
- Advantages
- Meets States EPA Requirements for Public
Participation - States Choose Option Most Comfortable With
- Logistically Between Other 2 Options
- Disadvantages
- Stakeholders Commenting in Another State?
- Impacts of Notice in One State on Another State
- One states Announcement Notifies Entire
Watershed
22Chosen Approach TBD
- TMDL Workgroup has not Come to Consensus on this
Number of Outreach Periods
23Issues 7 8Regulated and Unregulated TMDL
Loads Simulated in the Chesapeake Bay Model and
the Planned Allocation to Sources
24Regulated and Unregulated TMDL Loads Simulated in
the Chesapeake Bay Model and Planned Allocation
to Sources - Overview
- Regulated sources that will be included in the
wasteload allocation (WLA) - Municipal and industrial wastewater treatment
facilities - Combined sewer overflows (CSOs)
- Sanitary sewer overflows (SSOs)
- Municipal separate storm sewer systems (MS4s)
- Construction sites
- Confined animal feeding operations (CAFOs)
- Non-regulated sources that will be included in
the load allocation (LA) - Agricultural animals
- Agricultural cropland and pasture
- Non-MS4 regulated stormwater runoff
- Septic systems
- Oceanic input of nutrients
- Oceanic input of sediment
- Upland above and below fall-line sediment sources
- Shoreline sediment sources
25Regulated Nutrient and Sediment Sources -
Municipal and industrial wastewater treatment
facilities
- Simulation in the Phase 5 Watershed Model
- Model includes a database of about 815
industrial, municipal and federal facilities
discharging to the surface waters in the
watershed - Database includes monthly flow and monthly
average concentrations for TN, NH3, NO2NO3, TON,
TP, PO4, TOP, TSS, BOD and DO (for each facility
outfall) - Grouping of major and minor dischargers developed
by each state. States encouraged to provide flow
and concentration data for minor facilities
(usually flow lt 0.4 MGD), but this information
largely missing from the model. Best estimate is
that 5 of total Chesapeake point source flow is
missing from the Model - River segments simulated as a completely mixed
reactor and all of the point source loads in a
reach are summed for each of the river segments
and input as a daily load
26Regulated Nutrient and Sediment Sources -
Municipal and industrial wastewater treatment
facilities
- Recommended Allocation Approach
- Municipal and industrial dischargers,
particularly the major dischargers, may receive
individual and unique WLAs within a Tributary
Strategy. Major dischargers can be allocated at
the river-segment scale (smallest segmentation
scale). - Minor dischargers must be allocated as a group of
dischargers unless the point source database is
upgraded to include an estimated record of these
dischargers. The smallest grouping for minor
dischargers not included in the model input data
is at the state level, as flow and load data by
river segment are not available.
27Regulated Nutrient and Sediment Sources - CSOs
- Simulation in the Phase 5 Watershed Model
- An estimate of CSO loads from the District of
Columbia (DC) is simulated in the Model - No other CSO information available
- Recommended Allocation Approach
- Other than DC, CSO input information for the
watershed is lacking, therefore an estimate of
CSO loading to the watershed in not supportable
28Regulated Nutrient and Sediment Sources - SSOs
- Simulation in the Phase 5 Watershed Model
- Information on SSOs in the watershed is
completely lacking - Recommended Allocation Approach
- Without any information on SSOs in the watershed,
and estimate of SSO loading is not supportable
29Regulated Nutrient and Sediment Sources MS4s
- Simulation in the Phase 5 Watershed Model
- Model lacks location, size and discharge
characteristics to simulate MS4 dischargers
explicitly - MS4 Phase 1 and Phase 2 jurisdictions will
represent MS4 area and assume the entire
municipal region is in the MS4 area. With this
information, the Model can simulate all developed
land areas in the same manner, but post-process
the developed land output data to estimate
nutrient and sediment loads from the developed
land in the MS4 areas. - Recommended Allocation Approach
- If data are available on the area served by MS4s
and the loads from MS4s at a land segment level
then the Model can parse these loads from the
generalized simulation of high intensity and low
intensity developed land to separate WLA and LA
loads of nutrients and sediment from developed
(urban) land
30Regulated Nutrient and Sediment Sources
Construction sites
- Simulation in the Phase 5 Watershed Model
- Bare-construction land use is a transitional land
use as forest or agricultural land uses are
converted to developed land. Assumed that
bare-construction area is equal to 2.5 times the
annual change in imperviousness (as described in
Section 4 of the Phase 5 documentation) - Bare-construction erosion rate 40
tons/acre/year - Five phases of construction over the project
duration and only a portion of the site is
exposed during each construction phase - Annual average sediment yield estimated by
assuming the project duration is 1 year and the
40 tons/acre/year is adjusted based on the
portion of the site that is exposed or disturbed
at a specific time. Results in a rate of 24.4
tons/acre/year for construction areas prior to
implementation of erosion and sediment controls - Stormwater Phase 2 Rule directs states to
develop, implement and enforce a program to
reduce pollutants in runoff from construction
activities 1 acre. Estimated levels of
effectiveness of the erosion and sediment
controls for the different states are applied
over the Model simulation period
31Regulated Nutrient and Sediment Sources
Construction sites
- Recommended Allocation Approach
- The smallest unit of information on construction
site loads is at the land-segment scale. This is
the limit of Model quantification for this load.
32Regulated Nutrient and Sediment Sources CAFOs
- Simulation in the Phase 5 Watershed Model
- CAFOs are not simulated explicitly in the Model
- Location and numbers of animal units associated
with each CAFO is known - Post-processing will allow the extraction of the
nutrients from CAFO manure and will provide a
first-order estimate of CAFO loads - Recommended Allocation Approach
- The basis of the CAFO estimate is the simulation
of the fate and transport of manure, which is
calculated at the land-segment level. This is the
smallest scale of spatial assessment available
for CAFO loads with the Model.
33Non-Regulated Nutrient and Sediment Sources
Agricultural animals
- Simulation in the Phase 5 Watershed Model
- Agricultural animals simulated in the Model as a
manure source - Numbers and types of agricultural animals
tabulated from county Agricultural Census data - Handling of manure in terms of frequency and type
of collection, as well as the type and duration
of storage, is taken into account - A portion of the nitrogen in manure is
volatilized as ammonia during collection, storage
and field application. The ultimate fate of
manure is volatilization, loss and export to the
stream during handling and storage, or loss and
export to the stream during and after field
application - Recommended Allocation Approach
- The smallest unit of information on agricultural
animals is at the land-segment scale, which is
roughly equivalent to counties. This is the limit
of the Model quantification of the loads from
agricultural animals.
34Non-Regulated Nutrient and Sediment Sources
Agricultural cropland and pasture
- Simulation in the Phase 5 Watershed Model
- Cropland and pasture simulation based on
conditions indicated in the county Agricultural
Census - Cropland information includes types of crops
grown, crop rotations, timing of planting,
harvest, and other field operations and estimated
amounts of applied fertilizer and manure - Pasture information includes stocking rate
determined by the estimates of pasture land and
number of pastured animals - Recommended Allocation Approach
- The smallest unit of information on cropland and
pasture is at the land-segment scale, which is
roughly equivalent to counties. This is the limit
of the Model quantification of the loads from
cropland and pasture.
35Non-Regulated Nutrient and Sediment Sources
Non-MS4 regulated stormwater runoff
- Simulation in the Phase 5 Watershed Model
- Nutrient and sediment loads from developed land
simulated at the land-segment scale - Recommended Allocation Approach
- The smallest unit of information on developed
land is at the land-segment scale, which is
roughly equivalent to counties. This is the limit
of the Model quantification of loads from non-MS4
regulated stromwater runoff.
36Non-Regulated Nutrient and Sediment Sources
Septic systems
- Simulation in the Phase 5 Watershed Model
- Nutrient loads from septic systems based on US
census data for waste disposal systems associated
with households - Septic systems simulated as a nitrate load
discharged to the river segment. Phosphorus loads
assumed to be entirely attenuated by septic
systems - 4 kg nitrate/person/year at the edge of the
septic field based on assumptions of per capita
nitrogen waste and standard attenuation of
nitrogen in the septic systems - Attenuation of 60 of the nitrate loads between
the septic field and the edge of the river due to
attenuation in 1) anaerobic saturated soils, 2)
plant uptake and 3) low order streams before the
simulated reach - Nitrate loads from coastal plain septic systems
delivered directly to the Bay because there is no
simulation reach - Recommended Allocation Approach
- Model estimate of septic system loads is a
first-order estimate only and the finest spatial
scale available is at the level of the
land-segments
37Non-Regulated Nutrient and Sediment Sources
Oceanic input of nutrients
- Simulation in the Phase 5 Watershed Model
- Long-term ocean currents flow along the coast
adjacent to the Chesapeake Bay from north to
south - Upward pressures on coastal nutrient loads mostly
due to growth in coastal watersheds - Downward pressure on coastal nutrient loads may
come from nutrient reductions required by coastal
TMDLs, water quality controls on the Delaware
River and coastal waters, and reduced atmospheric
deposition of nitrogen to coastal waters - Recommended Allocation Approach
- The potential for reduced nutrient loads in
coastal waters will likely lead to improved water
quality, making attainment of the water quality
standards easier for all partners
38Non-Regulated Nutrient and Sediment Sources
Oceanic input of sediment
- Simulation in the Phase 5 Watershed Model
- Input of sediment to the Chesapeake Bay from the
ocean boundary is a natural geologic process that
is entirely uncontrollable - Recommended Allocation Approach
- Oceanic input of sediment loads at the mouth of
the Chesapeake Bay reduces clarity in lower Bay
shallow waters and will make achieving the
clarity standard more difficult. May increase
reductions needed in the WLAs and LAs in some
designated use areas
39Non-Regulated Nutrient and Sediment Sources
Upland above and below fall-line sediment sources
- Simulation in the Phase 5 Watershed Model
- Upland sediment loads come from the different
land uses in the watershed - Upland sediment loads also derived the scour of
sediment loads from rivers and streams in the
watershed, which are stored in low to high order
streams with lag times of decades to centuries - Sediment lag time also arises from mechanisms
specific to the Chesapeake watershed, such as the
development of water power sources created from
relatively low head dams, which have subsequently
filled in with sediment - Recommended Allocation Approach
- The smallest unit of information from most land
uses is at the land-segment scale, which is
roughly equivalent to counties. This is the limit
of the Model quantification of these sediment
loads.
40Non-Regulated Nutrient and Sediment Sources
Shore erosion sediment sources
- Simulation in the Phase 5 Watershed Model
- Shoreline erosion is a direct sediment load to
shallow tidal waters - Refined base estimate of shore erosion loads
developed for the Water Quality and Sediment
Transport Model (WQSTM) - Management practices that are environmentally
protective and reduce shore erosion loads have
been proposed. Efficiencies for these and other
shoreline management practices have been
developed by the Bay Program - Recommended Allocation Approach
- Shore erosion sediment loads are local in effect
and unlikely to extend beyond the influence of
the clarity designated use area, which is
equivalent to a Chesapeake Bay monitoring segment
(CB segment). The CB segment is the recommended
level of assessment for shore erosion loads.
41Non-Regulated Nutrient and Sediment Sources
Tidal resuspension of sediment sources
- Simulation in the Phase 5 Watershed Model
- Tidal resuspension of sediment simulated in the
WQSTM with a module that relates wind speed and
direction to the fetch, which translates wind
energy into wave energy - Wave resuspension of sediment will be simulated
in shallow waters - Management measures to reduce resuspension
include SAV planting and the establishment of
benthic filter-feeders. Efficiency of these
management practices has yet to be explored by
the Bay Program - Recommended Allocation Approach
- Sediment loads from resuspension are local in
effect and unlikely to extend beyond the
influence of the clarity designated use area,
which is equivalent to a CB segment. The CB
segment is the recommended level of assessment
for tidal resuspension loads.