Summary of Issues Chesapeake Bay Program Water Quality Steering Committee Meetings - PowerPoint PPT Presentation

About This Presentation
Title:

Summary of Issues Chesapeake Bay Program Water Quality Steering Committee Meetings

Description:

Summary of Issues Chesapeake Bay Program Water Quality Steering Committee Meetings November 14, 2006 Region 3 Issues Covered in the Meeting Issue 1, 7 & 8: Issuance ... – PowerPoint PPT presentation

Number of Views:61
Avg rating:3.0/5.0
Slides: 42
Provided by: TetraT5
Category:

less

Transcript and Presenter's Notes

Title: Summary of Issues Chesapeake Bay Program Water Quality Steering Committee Meetings


1
Summary of Issues Chesapeake Bay Program Water
Quality Steering Committee Meetings
November 14, 2006
2
Issues Covered in the Meeting
  • Issue 1, 7 8 Issuance of the Bay TMDL
  • Issue 9 Who leads the public participation
    process?
  • Issues 11 12 Regulated and unregulated TMDL
    loads simulated in the Chesapeake Bay Model and
    the planned allocation to sources
  • Issue 23 Schedule for TMDL Development

3
Issue 1Issuance of the Bay TMDL
4
Issuance of the Bay TMDL - Overview
  • Five Options
  • Developed Individually by each State
  • Developed Together Submitted Individually
  • Developed by Virginia (or Bay States)
  • Developed by EPA for all States
  • Developed by the States and Submitted Jointly
  • All Options States Working Together on TMDL
  • EPAs Contractor Writes TMDL Report
  • Only Requirement Approved Bay TMDL Established by
    May 1, 2010 (VA) or 2011 (EPA)

5
Issuance - Option 1 TMDL Developed individually
by Each State
  • Advantages
  • Flexibility to States in Composition
    Presentation of TMDL
  • Demonstrates States Commitment to the Bay
  • Disadvantages
  • Legal Strength of Allocating Loads to Protect
    Downstream Criteria
  • TMDL Contested in 7 States, 7 Different Opinions
    on TMDL
  • Costs Associated 7 Defenses
  • EPA Approves 7 TMDLs
  • Goes Against Partnership Approach
  • Appears States are Developing TMDL Alone

6
Issuance Option 2 TMDL developed Together but
Submitted Individually
  • Advantages
  • Flexibility Scheduling TMDL Activities (e.g.,
    public participation, submission and approval)
  • Disadvantages
  • Legal Strength of Allocating Loads to Protect
    Downstream Criteria
  • Goes Against Bay Partnership Approach
  • TMDL Contested in 7 States, 7 Different Opinions
    on TMDL
  • Costs Associated 7 Defenses
  • EPA will need to approve 7 documents

7
Issuance Option 3 TMDL Developed by Virginia
(or Bay States)
  • Advantages
  • One Document for Approval
  • Streamline Public Participation Process (i.e.,
    meetings only required in Virginia
  • Disadvantages
  • Challenges Regarding VAs Authority in Upstream
    Waters
  • Goes Against Bay Partnership Approach
  • Stakeholders in Other States Limited Opportunity
    to Comment
  • Negative Impact on Palatability of TMDL to
    Stakeholders

8
Issuance Option 4 TMDL Developed by EPA for
All States
  • Advantages
  • Strongest Against Legal Challenges Regarding
    Upstream and Downstream State Criteria
  • Challenges in Federal Court Only
  • One Opinion
  • The Federal Record of Review Basis of Defense
  • No Submission or Approval Process
  • EPA Assist in Public Participation Process, State
    Lead
  • Document Authored by one entity (EPA), Speak w
    One Voice
  • Disadvantages
  • Correspondence w Partnership Approach
  • Comfort w Establishment of TMDL by Federal
    Government

9
Issuance Option 5 TMDL Developed by the States
and Submitted Jointly
  • Advantages
  • Applies Partnership Approach
  • States Responsible for their Public Participation
  • One Document for Approval
  • Consistency in the TMDL report
  • Demonstrates Commitment of all Bay States to WQ
    in Bay
  • Disadvantages
  • TMDL Contested in 7 States, 7 Different Opinions
    on TMDL
  • Costs Associated 7 Defenses
  • Coordination for Public Participation Difficult
    Logistically

10
Issuance Chosen Approach
  • TMDL Developed by EPA for all States
  • Strongest Option
  • Easiest to Defend Protecting Downstream Criteria
  • Subject to Federal Court Only
  • Defended via Record of Decision
  • One Decision
  • Simplest Logistically

11
Issue 5 Who Leads the Public Participation
Process?
12
Who Leads the Public Participation Process?
  • Four Options Lead Agency
  • Each State in Charge of Own Public Outreach
  • EPA Leads Public Outreach, State Representative
    Present at their State Meetings
  • Public Outreach Led by each State EPA Region 3
    Assistance
  • Virginia (Bay States) Leads Public Participation

13
Option 1 Each State Leads Own Public Outreach
  • Advantages
  • Easiest Logistically
  • Stakeholders Commenting to Their State Agency
  • Disadvantages
  • Ensure Each States Public Outreach Coincides w
    TMDL Issuance
  • States EPA not Speaking w One Voice may have
    Contradictions
  • Duplication of Work, Each State Drafting
    Responses
  • Goes Against Partnership Approach

14
Option 2 EPA in Charge of Public Outreach
  • Advantages
  • Logistically Simple
  • Single Comment Response Period
  • EPA Acts as Repository Comments Responds to All
    Comments (Except on State Exclusive Issues)
  • Disadvantages
  • Goes Against Partnership Approach
  • EPA not as Experienced Working w Stakeholders as
    States
  • Difficulty of EPA Regional Staff Coordinate
    Participate in Meetings
  • EPA Viewed as Outsider

15
Option 3 Public Outreach Led by Each State w EPA
Regional Assistance
  • Advantages
  • Familiarity w Stakeholders in Charge of Process
  • TMDL Workgroup Responds to Comments Consistency
  • States Formulate Own Public Outreach, EPA and
    Contractor Attend Meetings Ensure Consistent
    Messages
  • Coincides w TMDL Issued by EPA
  • Disadvantages
  • Multiple Jurisdictions Coordinating Outreach
  • TMDL Workgroup Coordinating Responses, Might
    Extend Response Time

16
Option 4 Virginia (Bay States) in Charge of
Public Outreach
  • Advantages
  • Responsibility in Hands of One Agency, Simplifies
    Logistics Reduces Conflicting Messages
  • Disadvantages
  • Goes Against Partnership Approach
  • VAs Lack of Experience Working w Other State
    Stakeholders
  • Perception VA Dictating Actions in Upstream
    Waters
  • Other States Stakeholders Excluded from Process?
  • Not Consistent w Most TMDL Issuance Options

17
Public Outreach - Chosen Approach
  • Public Outreach Run by States w EPA Assistance

18
The Amount of Outreach Efforts
  • Options Number of Comment Periods
  • Single Comment Period After Draft TMDL
  • Multiple Comment Periods
  • States Chooses Number of Comment Periods

19
Option 1 Single Comment Period after Draft
  • Advantages
  • Simplest Option
  • One Comment and Response Period
  • Complies with EPA regulations for Public Outreach
  • Disadvantages
  • Less Opportunity for Providing Data Information
    for Use in TMDL
  • Less Time to Build Consensus w Public
  • Fulfillment to Public Outreach Process in All
    States

20
Option 2 Multiple comment periods
  • Advantages
  • Allows Solicitation of Additional Data
    Information
  • Public Sees Impact of Comments on TMDL Process
  • Addressing Concerns Early Lowers TMDLs
    Susceptibility to Litigation?
  • Disadvantages
  • Logistics
  • Cost and Time Associated w Public Outreach
  • Multiple Sets of Comments
  • Opening Portions of TMDL to Public Comment that
    Should Not Be
  • First Meetings Need to be Established Soon
  • Is it to Early for Acknowledgement?

21
Option 3 States choose number of comment periods
  • Advantages
  • Meets States EPA Requirements for Public
    Participation
  • States Choose Option Most Comfortable With
  • Logistically Between Other 2 Options
  • Disadvantages
  • Stakeholders Commenting in Another State?
  • Impacts of Notice in One State on Another State
  • One states Announcement Notifies Entire
    Watershed

22
Chosen Approach TBD
  • TMDL Workgroup has not Come to Consensus on this
    Number of Outreach Periods

23
Issues 7 8Regulated and Unregulated TMDL
Loads Simulated in the Chesapeake Bay Model and
the Planned Allocation to Sources
24
Regulated and Unregulated TMDL Loads Simulated in
the Chesapeake Bay Model and Planned Allocation
to Sources - Overview
  • Regulated sources that will be included in the
    wasteload allocation (WLA)
  • Municipal and industrial wastewater treatment
    facilities
  • Combined sewer overflows (CSOs)
  • Sanitary sewer overflows (SSOs)
  • Municipal separate storm sewer systems (MS4s)
  • Construction sites
  • Confined animal feeding operations (CAFOs)
  • Non-regulated sources that will be included in
    the load allocation (LA)
  • Agricultural animals
  • Agricultural cropland and pasture
  • Non-MS4 regulated stormwater runoff
  • Septic systems
  • Oceanic input of nutrients
  • Oceanic input of sediment
  • Upland above and below fall-line sediment sources
  • Shoreline sediment sources

25
Regulated Nutrient and Sediment Sources -
Municipal and industrial wastewater treatment
facilities
  • Simulation in the Phase 5 Watershed Model
  • Model includes a database of about 815
    industrial, municipal and federal facilities
    discharging to the surface waters in the
    watershed
  • Database includes monthly flow and monthly
    average concentrations for TN, NH3, NO2NO3, TON,
    TP, PO4, TOP, TSS, BOD and DO (for each facility
    outfall)
  • Grouping of major and minor dischargers developed
    by each state. States encouraged to provide flow
    and concentration data for minor facilities
    (usually flow lt 0.4 MGD), but this information
    largely missing from the model. Best estimate is
    that 5 of total Chesapeake point source flow is
    missing from the Model
  • River segments simulated as a completely mixed
    reactor and all of the point source loads in a
    reach are summed for each of the river segments
    and input as a daily load

26
Regulated Nutrient and Sediment Sources -
Municipal and industrial wastewater treatment
facilities
  • Recommended Allocation Approach
  • Municipal and industrial dischargers,
    particularly the major dischargers, may receive
    individual and unique WLAs within a Tributary
    Strategy. Major dischargers can be allocated at
    the river-segment scale (smallest segmentation
    scale).
  • Minor dischargers must be allocated as a group of
    dischargers unless the point source database is
    upgraded to include an estimated record of these
    dischargers. The smallest grouping for minor
    dischargers not included in the model input data
    is at the state level, as flow and load data by
    river segment are not available.

27
Regulated Nutrient and Sediment Sources - CSOs
  • Simulation in the Phase 5 Watershed Model
  • An estimate of CSO loads from the District of
    Columbia (DC) is simulated in the Model
  • No other CSO information available
  • Recommended Allocation Approach
  • Other than DC, CSO input information for the
    watershed is lacking, therefore an estimate of
    CSO loading to the watershed in not supportable

28
Regulated Nutrient and Sediment Sources - SSOs
  • Simulation in the Phase 5 Watershed Model
  • Information on SSOs in the watershed is
    completely lacking
  • Recommended Allocation Approach
  • Without any information on SSOs in the watershed,
    and estimate of SSO loading is not supportable

29
Regulated Nutrient and Sediment Sources MS4s
  • Simulation in the Phase 5 Watershed Model
  • Model lacks location, size and discharge
    characteristics to simulate MS4 dischargers
    explicitly
  • MS4 Phase 1 and Phase 2 jurisdictions will
    represent MS4 area and assume the entire
    municipal region is in the MS4 area. With this
    information, the Model can simulate all developed
    land areas in the same manner, but post-process
    the developed land output data to estimate
    nutrient and sediment loads from the developed
    land in the MS4 areas.
  • Recommended Allocation Approach
  • If data are available on the area served by MS4s
    and the loads from MS4s at a land segment level
    then the Model can parse these loads from the
    generalized simulation of high intensity and low
    intensity developed land to separate WLA and LA
    loads of nutrients and sediment from developed
    (urban) land

30
Regulated Nutrient and Sediment Sources
Construction sites
  • Simulation in the Phase 5 Watershed Model
  • Bare-construction land use is a transitional land
    use as forest or agricultural land uses are
    converted to developed land. Assumed that
    bare-construction area is equal to 2.5 times the
    annual change in imperviousness (as described in
    Section 4 of the Phase 5 documentation)
  • Bare-construction erosion rate 40
    tons/acre/year
  • Five phases of construction over the project
    duration and only a portion of the site is
    exposed during each construction phase
  • Annual average sediment yield estimated by
    assuming the project duration is 1 year and the
    40 tons/acre/year is adjusted based on the
    portion of the site that is exposed or disturbed
    at a specific time. Results in a rate of 24.4
    tons/acre/year for construction areas prior to
    implementation of erosion and sediment controls
  • Stormwater Phase 2 Rule directs states to
    develop, implement and enforce a program to
    reduce pollutants in runoff from construction
    activities 1 acre. Estimated levels of
    effectiveness of the erosion and sediment
    controls for the different states are applied
    over the Model simulation period

31
Regulated Nutrient and Sediment Sources
Construction sites
  • Recommended Allocation Approach
  • The smallest unit of information on construction
    site loads is at the land-segment scale. This is
    the limit of Model quantification for this load.

32
Regulated Nutrient and Sediment Sources CAFOs
  • Simulation in the Phase 5 Watershed Model
  • CAFOs are not simulated explicitly in the Model
  • Location and numbers of animal units associated
    with each CAFO is known
  • Post-processing will allow the extraction of the
    nutrients from CAFO manure and will provide a
    first-order estimate of CAFO loads
  • Recommended Allocation Approach
  • The basis of the CAFO estimate is the simulation
    of the fate and transport of manure, which is
    calculated at the land-segment level. This is the
    smallest scale of spatial assessment available
    for CAFO loads with the Model.

33
Non-Regulated Nutrient and Sediment Sources
Agricultural animals
  • Simulation in the Phase 5 Watershed Model
  • Agricultural animals simulated in the Model as a
    manure source
  • Numbers and types of agricultural animals
    tabulated from county Agricultural Census data
  • Handling of manure in terms of frequency and type
    of collection, as well as the type and duration
    of storage, is taken into account
  • A portion of the nitrogen in manure is
    volatilized as ammonia during collection, storage
    and field application. The ultimate fate of
    manure is volatilization, loss and export to the
    stream during handling and storage, or loss and
    export to the stream during and after field
    application
  • Recommended Allocation Approach
  • The smallest unit of information on agricultural
    animals is at the land-segment scale, which is
    roughly equivalent to counties. This is the limit
    of the Model quantification of the loads from
    agricultural animals.

34
Non-Regulated Nutrient and Sediment Sources
Agricultural cropland and pasture
  • Simulation in the Phase 5 Watershed Model
  • Cropland and pasture simulation based on
    conditions indicated in the county Agricultural
    Census
  • Cropland information includes types of crops
    grown, crop rotations, timing of planting,
    harvest, and other field operations and estimated
    amounts of applied fertilizer and manure
  • Pasture information includes stocking rate
    determined by the estimates of pasture land and
    number of pastured animals
  • Recommended Allocation Approach
  • The smallest unit of information on cropland and
    pasture is at the land-segment scale, which is
    roughly equivalent to counties. This is the limit
    of the Model quantification of the loads from
    cropland and pasture.

35
Non-Regulated Nutrient and Sediment Sources
Non-MS4 regulated stormwater runoff
  • Simulation in the Phase 5 Watershed Model
  • Nutrient and sediment loads from developed land
    simulated at the land-segment scale
  • Recommended Allocation Approach
  • The smallest unit of information on developed
    land is at the land-segment scale, which is
    roughly equivalent to counties. This is the limit
    of the Model quantification of loads from non-MS4
    regulated stromwater runoff.

36
Non-Regulated Nutrient and Sediment Sources
Septic systems
  • Simulation in the Phase 5 Watershed Model
  • Nutrient loads from septic systems based on US
    census data for waste disposal systems associated
    with households
  • Septic systems simulated as a nitrate load
    discharged to the river segment. Phosphorus loads
    assumed to be entirely attenuated by septic
    systems
  • 4 kg nitrate/person/year at the edge of the
    septic field based on assumptions of per capita
    nitrogen waste and standard attenuation of
    nitrogen in the septic systems
  • Attenuation of 60 of the nitrate loads between
    the septic field and the edge of the river due to
    attenuation in 1) anaerobic saturated soils, 2)
    plant uptake and 3) low order streams before the
    simulated reach
  • Nitrate loads from coastal plain septic systems
    delivered directly to the Bay because there is no
    simulation reach
  • Recommended Allocation Approach
  • Model estimate of septic system loads is a
    first-order estimate only and the finest spatial
    scale available is at the level of the
    land-segments

37
Non-Regulated Nutrient and Sediment Sources
Oceanic input of nutrients
  • Simulation in the Phase 5 Watershed Model
  • Long-term ocean currents flow along the coast
    adjacent to the Chesapeake Bay from north to
    south
  • Upward pressures on coastal nutrient loads mostly
    due to growth in coastal watersheds
  • Downward pressure on coastal nutrient loads may
    come from nutrient reductions required by coastal
    TMDLs, water quality controls on the Delaware
    River and coastal waters, and reduced atmospheric
    deposition of nitrogen to coastal waters
  • Recommended Allocation Approach
  • The potential for reduced nutrient loads in
    coastal waters will likely lead to improved water
    quality, making attainment of the water quality
    standards easier for all partners

38
Non-Regulated Nutrient and Sediment Sources
Oceanic input of sediment
  • Simulation in the Phase 5 Watershed Model
  • Input of sediment to the Chesapeake Bay from the
    ocean boundary is a natural geologic process that
    is entirely uncontrollable
  • Recommended Allocation Approach
  • Oceanic input of sediment loads at the mouth of
    the Chesapeake Bay reduces clarity in lower Bay
    shallow waters and will make achieving the
    clarity standard more difficult. May increase
    reductions needed in the WLAs and LAs in some
    designated use areas

39
Non-Regulated Nutrient and Sediment Sources
Upland above and below fall-line sediment sources
  • Simulation in the Phase 5 Watershed Model
  • Upland sediment loads come from the different
    land uses in the watershed
  • Upland sediment loads also derived the scour of
    sediment loads from rivers and streams in the
    watershed, which are stored in low to high order
    streams with lag times of decades to centuries
  • Sediment lag time also arises from mechanisms
    specific to the Chesapeake watershed, such as the
    development of water power sources created from
    relatively low head dams, which have subsequently
    filled in with sediment
  • Recommended Allocation Approach
  • The smallest unit of information from most land
    uses is at the land-segment scale, which is
    roughly equivalent to counties. This is the limit
    of the Model quantification of these sediment
    loads.

40
Non-Regulated Nutrient and Sediment Sources
Shore erosion sediment sources
  • Simulation in the Phase 5 Watershed Model
  • Shoreline erosion is a direct sediment load to
    shallow tidal waters
  • Refined base estimate of shore erosion loads
    developed for the Water Quality and Sediment
    Transport Model (WQSTM)
  • Management practices that are environmentally
    protective and reduce shore erosion loads have
    been proposed. Efficiencies for these and other
    shoreline management practices have been
    developed by the Bay Program
  • Recommended Allocation Approach
  • Shore erosion sediment loads are local in effect
    and unlikely to extend beyond the influence of
    the clarity designated use area, which is
    equivalent to a Chesapeake Bay monitoring segment
    (CB segment). The CB segment is the recommended
    level of assessment for shore erosion loads.

41
Non-Regulated Nutrient and Sediment Sources
Tidal resuspension of sediment sources
  • Simulation in the Phase 5 Watershed Model
  • Tidal resuspension of sediment simulated in the
    WQSTM with a module that relates wind speed and
    direction to the fetch, which translates wind
    energy into wave energy
  • Wave resuspension of sediment will be simulated
    in shallow waters
  • Management measures to reduce resuspension
    include SAV planting and the establishment of
    benthic filter-feeders. Efficiency of these
    management practices has yet to be explored by
    the Bay Program
  • Recommended Allocation Approach
  • Sediment loads from resuspension are local in
    effect and unlikely to extend beyond the
    influence of the clarity designated use area,
    which is equivalent to a CB segment. The CB
    segment is the recommended level of assessment
    for tidal resuspension loads.
Write a Comment
User Comments (0)
About PowerShow.com