Title: The Life Safety Specialist Surveyor
1The Life Safety Specialist Surveyor
Preparing for the Life Safety Specialist
Documentation Review and Facility Tour
Healthcare Engineering Consultants
2The Life Safety Specialist (LSS)
- It is likely that the LSS will arrive with the
team on the first or second day, less likely
later in the survey - For 2011, the LSS will usually be scheduled for
an additional day based on the scheduled time of
the previous survey - The LSS will spend several hours on dedicated
documentation review, but much more time on the
facility tour - Other responsibilities assigned to the LSS will
depend on the survey team member preferences and
responsibilities they may conduct the EC
Interview and Emergency Management tracers - The other survey team members will also observe
life safety issues, but not as detailed as the
LSS it is not likely that the nurse and
physician will request a ladder and flashlight! - If the LSS observes deficiencies outside of
their defined responsibility (example medical
records privacy or medication security), they
will report it to the other team members
Healthcare Engineering Consultants
3The LSS Documentation Review
Life Safety Specialist (LSS) surveyor
documentation responsibilities include at a
minimum LS.01.01.01 SOC and Life
Safety Code LS.01.02.01 Interim
life safety measures EC.02.03.05 Fire
system tests EC.02.05.07 Emergency
power systems EC.02.05.09 Medical gas
and vacuum systems Note In 2011, the Life Safety
Specialist may be assigned additional
responsibilities during the survey
Healthcare Engineering Consultants
4The LSS Documentation Review
- LS.01.01.01 SOC and Life Safety Code
- The SOC completion will be verified through the
Joint Commission Connect site (BBIs and PFIs) - Have the SOC notebook available for review
- The PFI documents from the previous survey may
be reviewed to verify completion of deficiencies
(have them available, if requested) - The compartmentation drawings will be reviewed
to assist in planning the facility tour - Life Safety Code compliance will be verified
during the facility tour
Healthcare Engineering Consultants
5The Statement of Conditions
How Should the Statement of Conditions (SOC)
Document be Completed?
Healthcare Engineering Consultants
6 The Statement of Conditions
- What is the SOC?
- The Statement of Conditions (SOC) is a document
that is required to be completed by every
healthcare facility that applies for
accreditation by the Joint Commission. It
references the 2000 edition of the Life Safety
Code and consists of the following sections - Basic Building Information (BBI) Form
electronic on Connect site - Life Safety Assessment (LSA) Form not
electronic - Plan for Improvement (PFI) Form electronic on
Connect site - BBIs, LSAs and PFIs are
- Note Other LSC editions may be selected, but
the entire edition must be followed
Healthcare Engineering Consultants
7 The Statement of Conditions
- SOC Notebook (Best Practice)
- A SOC notebook is strongly recommended to
contain hard copies of the SOC documents - The notebook should include at least the
following sections - Section 1 The SOC policy and responsibility
statement - Section 2 Current copies of the downloaded
BBI forms - Section 3 Accurate, color-coded
compartmentation prints - Section 4 The latest, completed LSA-type
document - Section 5 Current and previous, downloaded
PFI forms - Section 6 Any correspondence with the
Joint Commission, including equivalencies,
letters and emails
Healthcare Engineering Consultants
8 The Statement of Conditions
- Why Should I have an SOC Policy? (Best Practice)
- The SOC policy describes how the Statement of
Conditions program is organized for the facility - What Should the SOC Policy Include?
- Who is responsible for completing and
maintaining the SOC - How often the SOC documents are reviewed
- Who reviews the SOC documents for timeliness
- PFI guidelines (when does a work order become a
PFI?) - Whether a BMP is implemented
- Whether an above-the-ceiling program is in
place - How the SOC documents are organized
Healthcare Engineering Consultants
9 Statement of Conditions Document
The current Statement of Conditions hard copy
document is dated 5/2004 and can still be
downloaded from JointCommission.org for the LSA
form (do not use the BBI or PFI hard copies
they are obsolete)
Healthcare Engineering Consultants
10 Statement of Conditions Document
- Notes About the e-BBI Form
- List on the e-BBI cover page every occupancy
that will be surveyed, even for business
occupancies (make sure that the BBI and survey
list match!) - The e-BBI questionnaires are only required for
ambulatory, hotel/ dormitory and healthcare
occupancies - Fill in the comments section regarding SOC
preparer, location of building drawings, mixed
occupancies, equivalencies, special building
features or local AHJ requirements to the BBI - If multiple occupancies are entered, the
greatest percentage defaults to the BBI form, so
multiple BBI entries are required - Be sure to download the electronic version of
the BBI form before it is saved so that a
back-up is available, and place a copy in the
SOC Notebook
Healthcare Engineering Consultants
11 Statement of Conditions Document
- Compartmentation Requirements
- Mixed Occupancies (LSC 19.1.2.1)
- Sections of health care facilities shall
be permitted to be classified as other
occupancies, provided that they meet the
following conditions - They are not intended to serve health care
occupants for purposes of housing, treatment, or
customary access by patients incapable of
self-preservation - They are separated from the health care occupancy
by a fire rating of at least 2 hours - Separation between ambulatory and business
occupancies only requires a 1 hour rating (LSC
21.1.2.1)
Healthcare Engineering Consultants
12 Statement of Conditions Document
e-BBI Form Buildings
Be sure to complete for all healthcare and
ambulatory facilities Optional for business
occupancies, but strongly suggested for the cover
page
Healthcare Engineering Consultants
13 Statement of Conditions Document
e-BBI Form - Healthcare
Refer to instructions related to stories in
the Life Safety Code Note instructions related
to building construction type (occupancy)
Building age is important due to significant
code changes
Healthcare Engineering Consultants
14 Statement of Conditions Document
e-BBI Form page 2 1991 date significant due to
sprinkler requirement Emergency power fuel
type important due to wet stacking
Healthcare Engineering Consultants
15 Statement of Conditions Document
e-BBI Form page 3 Previous inspections
data provides valuable information to the survey
team! Be sure to list local or regional
requirements (example limited generator testing
due to high pollution days) in the Comments
section at the bottom of the form as well as
other requested information
Healthcare Engineering Consultants
16 Statement of Conditions Document
- LSA Form (is not electronic)
- Is a voluntary assessment tool, although some
assessment is required at least annually - Is not required for Business Occupancies
- The Joint Commission surveyor normally expects
some type of form, document or evaluation to be
completed - Dated 5/2004, so a cover sheet that is signed
annually is recommended - Can still be downloaded from the Joint
Commission home page website (search Statement
of Conditions) - Can use PPR form or similar for the LSA document
- Comments in LSA must match PFI deficiencies
Healthcare Engineering Consultants
17 Statement of Conditions Document
Life Safety Building Compartmentation Drawings
Blue smoke barrier Green 1 hour fire wall
(hazardous area) Red 2 hour fire wall
Note Color-coded drawing is best practice
Healthcare Engineering Consultants
18 Statement of Conditions Document
- Notes About the PFI Forms
- The forms should not be used for operational
deficiencies, such as exit lights burned out,
doors out of minor adjustment or small
penetrations that can be easily filled these
should be completed using the routine work order
system - The normal trigger time from a work order to
PFI is 45 days - Document the PFIs on a continuing basis be
sure that the PFI log is up-to-date and ready to
be reviewed by the surveyor - Dont forget to enter the projected start and
completion dates and the actual completion date - Failure to meet the completion dates without a
delay approval results in Conditional
Accreditation 6 months after the projected
completion date has passed! - If applicable, keep any previously signed PFI
copies available
Healthcare Engineering Consultants
19 Statement of Conditions Document
The first page for the electronic PFI forms is
used to list the deficiencies Notice that a No
Deficiencies option is available (and should be
completed, if applicable)
Healthcare Engineering Consultants
20 Statement of Conditions Document
The second page for the electronic PFI forms is
used to indicate the deficiency resolutions Dont
forget to complete all of the requested
information, including the proposed action,
source of funds and the projected start and
completion dates The projected completion dates
can be altered until they are frozen before or
during the actual survey! Comments for each PFI
should include a note regarding the
implementation of ILSMs!
Healthcare Engineering Consultants
21 Statement of Conditions Document
The listing document simply provides a summary
of all of the deficiencies that have been
recorded on the PFI form for tracking purposes
keep a copy of this in the SOC notebook for
reference purposes
Healthcare Engineering Consultants
22The Life Safety Specialist Documentation Review
Should I Implement and Document a Building
Maintenance Program (BMP)?
Healthcare Engineering Consultants
23 The Building Maintenance Program (BMP)
- Is voluntary no scoring benefit in 2011
- No longer requires a measure of effectiveness
- Measurement system can use random samples
- Results should be used to determine revisions to
inspection or test frequencies - Information should be provided to the hospital
safety committee if changes are made to the
program - Is basically a PM program for the buildings
- Is still considered a Best Practice
Healthcare Engineering Consultants
24Fire System Tests
- Points to Remember
- Clearly define supervisory devices (fire pump,
low air pressure on dry or pre-action systems and
water tank level indicators expected) - Tamper and flow device test intervals increase
to quarterly on 7/1/11 - Inventory all doors on magnetic releasing
devices and document test results - Document tests results for each individual heat
and smoke detector, pull box and audible and
visual device -
Healthcare Engineering Consultants
25Fire System Tests
- Points to Remember
- Document receipt time of fire alarm signal to
local fire department or receiving station - Document static and residual pressure readings
for main drain tests and time back to static
pressure (best practice) - Visually inspect fire department connections
quarterly - The 5-year standpipe test was added to the
requirements in 2009 - Indicate the day and month of portable fire
extinguisher checks
Healthcare Engineering Consultants
26Fire System Tests
Points to Remember Dont forget to implement and
document Interim Fire System Measures (IFSM),
when required
- If the occupant hoses have been removed, keep a
copy of the approval letter from the AHJ - Place inaccessible smoke and fire dampers on the
PFI for a 6-year, renewable period (for tracking
purposes only) - Document that duct detectors trip the
air-handling units - Only applies to vertical and horizontal smoke
and fire doors, not security doors or curtains
Healthcare Engineering Consultants
27Fire System Test Monitoring
Best Practice for Monitoring Compliance
Healthcare Engineering Consultants
28Fire System Test Monitoring
Healthcare Engineering Consultants
29The LSS Documentation Review
- EC.02.05.07 Emergency Generators
- Perform and document weekly generator visual
checks (NFPA 110) - Perform and document monthly generator tests
between 20 and 40 days and with at least 30 of
the rated load for 30 minutes - Document that all automatic transfer switches
are exercised monthly - Conduct annual load bank tests if the 30 load
is not achieved and manifold temperatures are not
sufficient (possible change from the 2 hour to a
1.5 hour test in 2011 not yet approved) - Combining the annual and trienniel tests can be
performed by starting the load at 30 of
nameplate for the first 30 minutes of the test - Document the static or dynamic 4-hour trienniel
test for all generators - Test fuel oil quality annually, unless fuel is
consumed from the entire tank (NFPA 110) - Utilize Interim Emergency Power Measures
(IEPM) when necessary - Note Refer to NFPA 99 and 110 for more
information
Healthcare Engineering Consultants
30The LSS Documentation Review
- EC.02.05.07 Emergency Battery Lights
- Required in all anesthetizing locations (NFPA
70 517.63 ) Task Light! - administration of nonflammable inhalation
anesthetic agents - in the course of examination or treatment
- Note Grandfathering usually permitted
in existing ORs - Required in Level 1 or Level 2 EPS equipment
locations (NFPA 110 7.3.1) Task
Light! - Required in business occupancies for egress
lighting where emergency power is not required or
not available (NFPA 101 7.9.1.1) Egress Light! - Monthly push-to-test required for all battery
installations - Differentiate between task lighting and
egress lighting - Annual battery replacement in lieu of 90-minute
discharge test - Note 10 of lights must be tested for 90 minutes
annually, even if the batteries are changed.
Healthcare Engineering Consultants
31The LSS Documentation Review
- EC.02.05.07 Stored Emergency Power Supply
Systems (SEPSS) - Standard applies to Level 1 systems (NFPA 111
4.5.1) - Level 1 failure of the equipment to
perform could result in - loss of human life or serious injuries
- Testing requires
- 1. Quarterly functional test (5 minutes or
class specification) - 2. Annual full-load test for 60 of SEPSS
class duration - Note 1 NFPA 111 requires a monthly inspection,
quarterly functional test and annual full load
test for full class duration for Level 1 systems
- Note 2 The Joint Commission references exit
lighting, life support ventilation, fire
detection and alarm systems, and public
communications systems as Level 1 systems, but
most are not SEPPS systems
Healthcare Engineering Consultants
32The LSS Documentation Review
- EC.02.05.09 Medical Gas and Vacuum Systems
- Medical gas and vacuum system preventive
maintenance - program is required (facility must define
PM) and must include - - Bulk medical gas and vacuum system
components and source valve - - Master signal panels and area alarms
- - Automatic pressure switches and shutoff
valves - - Flexible connectors and outlets
- Testing per NFPA 99 is required for new
installation, - modification or repair (cross-connections,
purity, pressure) - Main supply valves and area shut-off valves
must be - accessible and clearly labeled
- Utilize Interim Medical Gas Measures (IMGM)
when necessary - Note Significant changes to NFPA 99 are likely
to occur when the next vote occurs at the NFPA
Annual Meeting
Healthcare Engineering Consultants
33The LSS Documentation Review
- EC.02.05.09 Medical Gas and Vacuum Systems
- Certification of installers and verifiers per
ASSE 6000 series is - required
- Medical air quality must meet NFPA 99
requirements below
Parameter Limit Value
Pressure dew point 39 degrees F
Carbon monoxide 10 ppm
Carbon dioxide 500 ppm
Gaseous hydrocarbons 25 ppm (as methane)
Halogenated hydrocarbons 2 ppm
Healthcare Engineering Consultants
34 The LSS Documentation Review
- Medical Gas and Vacuum System PM Recommendations
Note The recommendations provided in the chart
to the right are from NFPA 99, the 2005 edition,
Appendix C, section 5.2. Tests that are required
due to new system installations, renovations or
repair are listed in chapter 5 of NFPA 99
Healthcare Engineering Consultants
35 The LSS Documentation Review
Interim Utility System Measures (IFSM, IEPM,
IMGM)
Best Practice! Strongly recommended to
document that interim measures have been
implemented to compensate for utility systems
that are taken out of service
Healthcare Engineering Consultants
36The LSS Facility Tour
- Typical Tour Sequence
- Start on the roof, penthouse, mechanical
equipment rooms - Take the most traveled stairwell from the top
to the bottom - Take the elevator back up to the top patient
floor - Check smoke/ fire doors and compartmentation
features - Inspect chutes, storage areas, utility chases,
hazardous areas - Continue down to the lower and basement levels to
specific areas, such as the kitchen, loading
dock, fire pump, emergency generators, fire
annunciator panel, compressed gas and infectious
waste storage - Complete checklist, or until problems are found!
Healthcare Engineering Consultants
37The LSS Facility Tour
- Checklist for the Facility Building Tour
- Smoke and fire doors
- Check Closure, label rating, gaps,
undercuts, warpage, kick plate - Smoke and fire compartments
- Check Penetrations, proper sealant
- Roof and penthouse
- Check Contractor supplies, smoking,
exhaust fans labeled - Exit stairwells
- Check Door rating, closure, signage, exit
discharge - Linen/ trash chutes and receiving rooms
- Check Door rating, closure, fusible link,
chute blockage
Healthcare Engineering Consultants
38The LSS Facility Tour
- Checklist for the Hospital Building Tour (contd)
- Hazardous areas
- Check Storage of flammables, room rating,
door closer - Fire pump
- Check Controls turned on, valves open,
tampers OK - Fire annunciator panel
- Check Bypass, trouble, ground fault or
supervisory - Soiled linen rooms
- Check Proper storage, dirty separated from
clean
Healthcare Engineering Consultants
39The LSS Facility Tour
- Checklist for the Hospital Building Tour (contd)
- Medical waste storage
- Check Locked area, secure, sharps not
accessible - Loading dock
- Check Smoking, improper storage, powered
equipment - Kitchen area
- Check Cleanliness, storage, CO2 tanks,
refrigerator temps, K-type portable extinguishers
within 30 of fat fryer - PFI verification
- Check Previous PFIs have been resolved
as listed
Healthcare Engineering Consultants
40The LSS Facility Tour
- Checklist for the Hospital Building Tour (contd)
- ILSM verification
- Check Construction areas for ILSM
implementation - Mechanical equipment rooms
- Check Storage, unlabeled containers,
cigarettes, labeling - Emergency generators
- Check In auto mode, batteries/ charger,
fuel leaks - Medical gas systems
- Check Manifolds, medical air and vacuum
pumps
Healthcare Engineering Consultants
41The LSS Facility Tour
- Checklist for the Hospital Building Tour (contd)
- Compressed gas storage rooms
- Check Full and Empty separation, chained
or on racks - Egress corridors
- Check Equipment not in use, containers
gt 32 gallons - Eyewashes, showers and portable fire
extinguishers - Check Test dates on log or tag
- Chapel
- Check Candles, open flames
- Other?
Healthcare Engineering Consultants
42The LSS Facility Tour
Multiple Operational Deficiencies are Likely to
be Found During the Facility Tour
Healthcare Engineering Consultants
43 Operational Deficiencies
- Operating Features
- A clear space gt18 inches below sprinkler heads to
the top of storage must be maintained - Exception Perimeter wall shelving, unless
below the sprinkler (refer to NFPA 13) - Portable space heating devices are only permitted
in non-sleeping staff and employee areas, with
heating elements that do not exceed 212 degrees F
(LSC, 2009 edition, 19.7.8) - Combustible decorations are prohibited, unless
flame retardant (19.7.5.4) - Soiled linen or trash collection receptacles
shall not exceed 32 gallons in capacity
(19.7.5.5) - Exception Attended or in hazardous area
Healthcare Engineering Consultants
44 Operational Deficiencies
- Operating Features
- Holiday decoration policy and implementation
- Candles used in the chapel
- Furnishings, decorations or other objects may not
obstruct access, egress or block the visibility
of exits (7.1.10.2.1) - Exit doors must be free of mirrors, draperies or
hangings that may conceal, obscure or confuse the
direction of exit (7.5.2.2), and - Hallway Clutter!
Healthcare Engineering Consultants
45The Life Safety Specialist Surveyor
Questions?
Healthcare Engineering Consultants