Analyzing ventilation requirements and the utilization efficiency of the Kidd Creek mine ventilation system - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

Analyzing ventilation requirements and the utilization efficiency of the Kidd Creek mine ventilation system

Description:

... Kidd Ventilation Surface Kidd Ventilation Underground/Combined New Underground Booster Fans ... 14.5m3/s Shotcrete Hauler (240hp) 10.7m3/s DRILLING Cubex ... – PowerPoint PPT presentation

Number of Views:438
Avg rating:3.0/5.0
Slides: 30
Provided by: GM85
Category:

less

Transcript and Presenter's Notes

Title: Analyzing ventilation requirements and the utilization efficiency of the Kidd Creek mine ventilation system


1
Analyzing ventilation requirements and the
utilization efficiency of the Kidd Creek mine
ventilation system
12th North American/U.S. Mine Ventilation
Symposium Reno, Nevada, U.S.A., June 9-11, 2008
2
Analyzing ventilation requirements and the
utilization efficiency of the Kidd Creek mine
ventilation system
  • Stephen Hardcastle, Charles Kocsis Gary Li,
  • CANMET MMSL, Sudbury, Canada
  • Kingsley Hortin
  • Hatch Associates, Sudbury, Canada
  • (Formerly with Xstrata Copper, Kidd Creek,
    Timmins,
  • Canada)

3
Kidd Creek Mine
  • Northern Ontario
  • Started as Open Pit in 1966
  • Mines 1, 2, 3 now Mine D(Planned to Level
    102 _at_ 3,110m)
  • Developed to Level 91 (2,770m)
  • gt7,000 tpd copper sulphide from Mines 3 D
  • 200 diesel units (gt38,000hp)50 Production units
    (gt14,000hp)

4
Kidd VentilationSurface
SVR Exhaust Fan1,300kW (1,750hp)
New NVS Exhaust Fans2 x 2,600kW (3,500hp)
5
Kidd VentilationUnderground/Combined
  • New Underground Booster Fans,2 x 3,000kW
    (4,000hp) at 60 Level1,800m below surface
  • Total Installed Primary System FanMotor Power
    13,600kW (?18,300hp)
  • Operational Capacity 1,220m3/s(?2.6Mcfm)

X 25
  • Very Significant Operating Cost
  • Exhaust Air Plug (_at_7m Ø) wouldwrap around the
    Earth 25x per year

6
Ventilation Reviews
  • Objective - to reduce cost/improve efficiency
  • Initial brainstorming review
  • Need to address routing of air to avoidhigh
    resistance fan assisted routes
  • SVR system redundant with respect toMines 3 D
  • More detailed review needed to assessefficiency
    and the need for increasedventilation management
  • 1,500kW (2,000hp) Fan Power removed

X
7
Detailed Reviews
  • Available Data
  • Long-term production plans such as
  • a month by month, 18-month schedule of activity
  • a year by year, 10 year tonnage plan
  • Historical data of daily equipment activity
    recordedby mines personnel
  • Design Criteria
  • 0.06 m3/s per kW diesel engine power(?100cfm/bhp)

8
Generalized Activities
  • PRODUCTIONToro 1400 LHD (325hp)
    14.5m3/sShotcrete Hauler (240hp) 10.7m3/s
  • DRILLINGCubex Aries ITH (147hp) 6.6m3/sKubota
    M6800 Tractor (68hp) 3.0m3/s
  • MISCELLANEOUS14.5m3/s sufficient for standard
    LHD

9
Future Requirements
  • Iteration 1
  • Predictive based upon 18-month plan
  • Global 20 allowance for leakage
    non-activelevels
  • Extrapolated based upon tonnage
  • Minimum flowm3/s
  • 1,220m3/s capacity should be sufficient

10
Future Requirements
  • Iteration 1 Possible Caveats
  • Leakage of auxiliary systems ignored
  • No allowance to prevent recirculation at
    auxiliaryfans
  • 20 allowance to inactive areas/leakage may
    beinsufficient considering number of leaks
  • Failing to provide sufficient air to
    non-productiveareas for support activity
  • Assumes timely redistribution of airflow
  • Experience indicates 2 production LHDs as
    aregular occurrence

11
Future Requirements
  • Iteration 2
  • Predictive 18-month plan extrapolation
  • Production ?29m3/s, Drilling ? 14m3/s,Miscellaneo
    us ? 20.7m3/s Non-active ? 3.5m3/s
  • System leakage 20
  • Minimum flowm3/s, Total includingleakage
  • 1,220m3/s capacity remains sufficient
  • Still based upon working to an idealized plan

12
Past Requirements
  • Retrospective based upon production records
  • SIMS end of shift data

Work Duration
Shift
  • Data exportable to Microsoft Excel

13
Past Requirements
  • Pivot Table conditional analysis
  • Equipment identified and associated
    airflowrequirement allocated to a mining level
    (or levels)
  • Assume concurrent activity and sum
    requirementsper level per shift
  • Adjust to prevent recirculation at auxiliary
    fani.e. where only a single vehicle operated
  • Allot minimum leakage flow sufficient for
    smallservice vehicle (tractor)
  • Determine maximum flow needed for each levelper
    averaging period month, week, day

14
Past Requirements
Pivot Table month based analysis of 36 Levels
  • On average - each level active 316 days/year
    31 of 36 levels active/day
  • Flow requirements, 3.5 to 114m3/s, average 27m3/s

15
Past Requirements
Pivot Table week based analysis of 36 Levels
  • On average - each level active 252 days/year
    25 of 36 levels active/day
  • Lower average level airflow requirement of 19m3/s

16
Past Requirements
Pivot Table daily based analysis of 36 Levels
  • On average - each level active 174 days/year
    17.5 of 36 levels active/day
  • Level airflow requirement now averages 11m3/s

17
Past Requirements
  • Pivot Table Analysis Differences/Caveats
  • Potential double accounting same vehicle
    morethan one location this can happen
  • Multiple vehicles, up to 5, generate high demands
  • Available data provides duration but no
    time-stamp
  • Consequently it was not possible to determine
    whether the activity was concurrent or
    sequential
  • This backward analysis, based upon observed
    discontinuous activity, highlights maximum demand
  • The previous forward analyses were based upon
    idealized continuous averaged activity

18
Efficiency/Redundancy
  • System Efficiency ? Utilization Efficiency
  • An efficient System is one with minimal leakage
    regardless of whether the air distribution is
    appropriate
  • Utilization/redundancy is a function of whether
    the distribution meets/exceeds production demands
  • All a question of definition
  • Todays production air could be tomorrow's
    leakage
  • Production demand is that by day, week or month?

19
Airflow RequirementsLower Mine Mines 3 D
Monthly average with diesel backfill 1,261m3/s
Mine Delivery Capacity 1,220m3/s
Demand greater than available supply hence
perceived problems
Airflow requirement based upon monthly
distribution with diesel based backfill
20
Airflow RequirementsLower Mine Mines 3 D
Monthly average with pastefill 983m3/s
Airflow requirement based upon monthly
distribution with pastefill
21
Airflow RequirementsLower Mine Mines 3 D
Weekly average with pastefill 681m3/s
Airflow requirement based upon weekly
distribution with pastefill
22
Airflow RequirementsLower Mine Mines 3 D
Daily average with pastefill 400m3/s
Airflow requirement based upon daily distribution
with pastefill
23
Airflow RequirementsLower Mine Mines 3 D
24
Analysis Findings
  • Historical analysis shows the dynamic nature of
    production in a base metal mine constant change
  • Hence perceived under performance/inadequacy
  • Future plan based requirements are optimistic
  • Airflow distribution need to be managed to limit
    total volume of air supplied - significant
    benefits
  • More frequent redistribution lowers the
    redundancy - the optimum would be daily
  • Redistribution frequency needs to be more often
    than future planning period to operate within the
    design capacity

25
Ventilation Management
  • Primary system is automated
  • Secondary system control is being considered

26
Ventilation Management
  • Mine introduced more frequent redistribution of
  • secondary airflow adjustment of primary system
  • Production Engineering schedule upcoming
    activities automatically producing airflow demands
  • Ventilation Department reviews requirements and
    produce an action plan
  • Operations Group implement changes prior to the
    commencement of the next weeks work activities

27
Realized Benefits
  • Power Savings from .
  • Elimination of a surface fan (initial review)
  • Numerous auxiliary fans turned off on inactive
    levels
  • Reduced demand/lower operating point for the 2 x
    3000kW boosters
  • On average the mine now operates on 930 m3/s
    which is 23 less than delivered at the start of
    the review process

The number of ventilation related complaints has
decreased
28
Conclusions
  • Base metal mining is never constant
  • Ventilation needs vary with changing activity
  • Overall demand depends on how often the
    ventilation is adjusted
  • Significant differences between operational needs
    if airflows are redistributed daily, weekly or
    monthly
  • Long range plans are idealized averages -
    actual operation is different
  • Both Forward and Backward analyses have a place -
    both can have limitations
  • Ventilation management can save power money -
    it can also be simple

29
Acknowledgements Xstrata Copper Kidd Creek
Mine
Write a Comment
User Comments (0)
About PowerShow.com