Title: Analyzing ventilation requirements and the utilization efficiency of the Kidd Creek mine ventilation system
1Analyzing ventilation requirements and the
utilization efficiency of the Kidd Creek mine
ventilation system
12th North American/U.S. Mine Ventilation
Symposium Reno, Nevada, U.S.A., June 9-11, 2008
2Analyzing ventilation requirements and the
utilization efficiency of the Kidd Creek mine
ventilation system
- Stephen Hardcastle, Charles Kocsis Gary Li,
- CANMET MMSL, Sudbury, Canada
- Kingsley Hortin
- Hatch Associates, Sudbury, Canada
- (Formerly with Xstrata Copper, Kidd Creek,
Timmins, - Canada)
3Kidd Creek Mine
- Northern Ontario
- Started as Open Pit in 1966
- Mines 1, 2, 3 now Mine D(Planned to Level
102 _at_ 3,110m) - Developed to Level 91 (2,770m)
- gt7,000 tpd copper sulphide from Mines 3 D
- 200 diesel units (gt38,000hp)50 Production units
(gt14,000hp)
4Kidd VentilationSurface
SVR Exhaust Fan1,300kW (1,750hp)
New NVS Exhaust Fans2 x 2,600kW (3,500hp)
5Kidd VentilationUnderground/Combined
- New Underground Booster Fans,2 x 3,000kW
(4,000hp) at 60 Level1,800m below surface
- Total Installed Primary System FanMotor Power
13,600kW (?18,300hp) - Operational Capacity 1,220m3/s(?2.6Mcfm)
X 25
- Very Significant Operating Cost
- Exhaust Air Plug (_at_7m Ø) wouldwrap around the
Earth 25x per year
6Ventilation Reviews
- Objective - to reduce cost/improve efficiency
- Initial brainstorming review
- Need to address routing of air to avoidhigh
resistance fan assisted routes - SVR system redundant with respect toMines 3 D
- More detailed review needed to assessefficiency
and the need for increasedventilation management - 1,500kW (2,000hp) Fan Power removed
X
7Detailed Reviews
- Available Data
- Long-term production plans such as
- a month by month, 18-month schedule of activity
- a year by year, 10 year tonnage plan
- Historical data of daily equipment activity
recordedby mines personnel - Design Criteria
- 0.06 m3/s per kW diesel engine power(?100cfm/bhp)
8Generalized Activities
- PRODUCTIONToro 1400 LHD (325hp)
14.5m3/sShotcrete Hauler (240hp) 10.7m3/s
- DRILLINGCubex Aries ITH (147hp) 6.6m3/sKubota
M6800 Tractor (68hp) 3.0m3/s
- MISCELLANEOUS14.5m3/s sufficient for standard
LHD
9Future Requirements
- Iteration 1
- Predictive based upon 18-month plan
- Global 20 allowance for leakage
non-activelevels - Extrapolated based upon tonnage
- Minimum flowm3/s
- 1,220m3/s capacity should be sufficient
10Future Requirements
- Iteration 1 Possible Caveats
- Leakage of auxiliary systems ignored
- No allowance to prevent recirculation at
auxiliaryfans - 20 allowance to inactive areas/leakage may
beinsufficient considering number of leaks - Failing to provide sufficient air to
non-productiveareas for support activity - Assumes timely redistribution of airflow
- Experience indicates 2 production LHDs as
aregular occurrence
11Future Requirements
- Iteration 2
- Predictive 18-month plan extrapolation
- Production ?29m3/s, Drilling ? 14m3/s,Miscellaneo
us ? 20.7m3/s Non-active ? 3.5m3/s - System leakage 20
- Minimum flowm3/s, Total includingleakage
- 1,220m3/s capacity remains sufficient
- Still based upon working to an idealized plan
12Past Requirements
- Retrospective based upon production records
- SIMS end of shift data
Work Duration
Shift
- Data exportable to Microsoft Excel
13Past Requirements
- Pivot Table conditional analysis
- Equipment identified and associated
airflowrequirement allocated to a mining level
(or levels) - Assume concurrent activity and sum
requirementsper level per shift - Adjust to prevent recirculation at auxiliary
fani.e. where only a single vehicle operated - Allot minimum leakage flow sufficient for
smallservice vehicle (tractor) - Determine maximum flow needed for each levelper
averaging period month, week, day
14Past Requirements
Pivot Table month based analysis of 36 Levels
- On average - each level active 316 days/year
31 of 36 levels active/day - Flow requirements, 3.5 to 114m3/s, average 27m3/s
15Past Requirements
Pivot Table week based analysis of 36 Levels
- On average - each level active 252 days/year
25 of 36 levels active/day - Lower average level airflow requirement of 19m3/s
16Past Requirements
Pivot Table daily based analysis of 36 Levels
- On average - each level active 174 days/year
17.5 of 36 levels active/day - Level airflow requirement now averages 11m3/s
17Past Requirements
- Pivot Table Analysis Differences/Caveats
- Potential double accounting same vehicle
morethan one location this can happen - Multiple vehicles, up to 5, generate high demands
- Available data provides duration but no
time-stamp - Consequently it was not possible to determine
whether the activity was concurrent or
sequential - This backward analysis, based upon observed
discontinuous activity, highlights maximum demand - The previous forward analyses were based upon
idealized continuous averaged activity
18Efficiency/Redundancy
- System Efficiency ? Utilization Efficiency
- An efficient System is one with minimal leakage
regardless of whether the air distribution is
appropriate - Utilization/redundancy is a function of whether
the distribution meets/exceeds production demands - All a question of definition
- Todays production air could be tomorrow's
leakage - Production demand is that by day, week or month?
19Airflow RequirementsLower Mine Mines 3 D
Monthly average with diesel backfill 1,261m3/s
Mine Delivery Capacity 1,220m3/s
Demand greater than available supply hence
perceived problems
Airflow requirement based upon monthly
distribution with diesel based backfill
20Airflow RequirementsLower Mine Mines 3 D
Monthly average with pastefill 983m3/s
Airflow requirement based upon monthly
distribution with pastefill
21Airflow RequirementsLower Mine Mines 3 D
Weekly average with pastefill 681m3/s
Airflow requirement based upon weekly
distribution with pastefill
22Airflow RequirementsLower Mine Mines 3 D
Daily average with pastefill 400m3/s
Airflow requirement based upon daily distribution
with pastefill
23Airflow RequirementsLower Mine Mines 3 D
24Analysis Findings
- Historical analysis shows the dynamic nature of
production in a base metal mine constant change - Hence perceived under performance/inadequacy
- Future plan based requirements are optimistic
- Airflow distribution need to be managed to limit
total volume of air supplied - significant
benefits - More frequent redistribution lowers the
redundancy - the optimum would be daily - Redistribution frequency needs to be more often
than future planning period to operate within the
design capacity
25Ventilation Management
- Primary system is automated
- Secondary system control is being considered
26Ventilation Management
- Mine introduced more frequent redistribution of
- secondary airflow adjustment of primary system
- Production Engineering schedule upcoming
activities automatically producing airflow demands
- Ventilation Department reviews requirements and
produce an action plan - Operations Group implement changes prior to the
commencement of the next weeks work activities
27Realized Benefits
- Power Savings from .
- Elimination of a surface fan (initial review)
- Numerous auxiliary fans turned off on inactive
levels - Reduced demand/lower operating point for the 2 x
3000kW boosters - On average the mine now operates on 930 m3/s
which is 23 less than delivered at the start of
the review process
The number of ventilation related complaints has
decreased
28Conclusions
- Base metal mining is never constant
- Ventilation needs vary with changing activity
- Overall demand depends on how often the
ventilation is adjusted - Significant differences between operational needs
if airflows are redistributed daily, weekly or
monthly - Long range plans are idealized averages -
actual operation is different - Both Forward and Backward analyses have a place -
both can have limitations - Ventilation management can save power money -
it can also be simple
29Acknowledgements Xstrata Copper Kidd Creek
Mine