Team Member: - PowerPoint PPT Presentation

1 / 57
About This Presentation
Title:

Team Member:

Description:

... in all flexural members expect slab and footing where the ... 26 kip Concentrated load ... develop their strength. Reinforcement requirements ... – PowerPoint PPT presentation

Number of Views:119
Avg rating:3.0/5.0
Slides: 58
Provided by: alne6
Category:

less

Transcript and Presenter's Notes

Title: Team Member:


1
Design of Concrete Girder Bridge
UNITED ARAB EMIRATES UNIVERSITY College of
Engineering Civil Environmental Engineering
Department
Graduation Project II
  • Team Member
  • Ahmed Al-Shehhi 200000069
  • Waleed Al-Alawi 200101647
  • Abdullah Al-Neyadi 200101637
  • Hassan Al-Hassani 200005052
  • Projects advisor Bilal El-Ariss

2
Presentation outline
  • Executive Summary
  • Introduction
  • Background theory
  • Methods and Techniques
  • Analysis of pier cap
  • Design of bridge deck ,girders and pier cap
  • Results and discussions
  • Conclusions and recommendations

3
Executive Summary
  • Analysis and design of a concrete girder bridge
  • Graduation project I
  • Graduation project II
  • Pier cap analysis
  • Design of bridge deck , girders and pier cap

4
Executive Summary
  • Software used
  • SAP2000
  • Analysis and determine bending moments and shear
    forces
  • PROKON
  • Compute the reinforcement areas needed for the
    shear and moments, and the dimensions of the
    different components of the bridge

5
Introduction
  • Project description
  • Bridge location

6
Introduction
  • Project description
  • Continuous girder bridges .
  • Two lanes in each direction and two shoulders and
    carries the traffic in two directions .
  • Two span girders .

7
Introduction
  • Bridge Dimensions

198 ft Total Bridge length
2 No. of spans
99 ft Length of span
60.74 ft Total bridge width
12.635 ft Two lanes each lane width
3.75 ft Side walk width
8 No. of girders
7.22 ft Distance between girders
5.1 ft Cantilever length
8
Introduction
  • AASHTO specifications
  • American Concrete Institute (ACI) code

9
Introduction
  • Bridge location
  • Abu Samra Bridge is located on the high way
    between Abu Dhabi and Al-Ain .

10

Background Theory
  • Reinforcement requirements
  • Design method
  • Reinforcement requirements due to flexure
  • Reinforcement requirements due to Shear
  • T-Girder

11
Design method
  • The method which will be used in our project is
    the ultimate-strength design method.
  • It's called now ultimate strength design.
  • The working dead and live loads are multiplied by
    certain load factors and the resulting values are
    called factored loads.

12
Reinforcement requirements due to flexure
  • The reinforcing bars will be distributed as
    follows
  • This reinforcing may not be spaced farther on
    center than 3 times the slab thickness.
  • A percentage of the main positive moment
    reinforcement which is perpendicular to the
    traffic shall be distributed in the parallel
    direction of the traffic

13
Reinforcement requirements due to flexure
  • Spacing limits for reinforcement
  • For cast-in-place concrete the clear distance
    between parallel bars in a layer shall not be
    less that 1.5 bar diameter.
  • Not less than1.5 times the maximum size of the
    coarse aggregate or 1.5 inches.

14
Reinforcement requirements due to flexure
  • Positive Moment Reinforcement
  • At least one-third the positive moment
    reinforcement in simple members and one-fourth
    the positive moment reinforcement in continuous
    members shall extend along the same face of the
    members into the support in beams, such
    reinforcement shall extend into the support at
    least 6 inches.
  • The development length
  • The reinforcement bars must be extended some
    distance back into the support and out into the
    beam to anchor them or develop their strength.

15
Reinforcement requirements due to Shear
  • The failure of reinforced concrete beams in shear
    are quite different form their failures in
    bending.
  • Shear failures occur suddenly with little or no
    advance warning.
  • If pure shear is produced in a member, a
    principal tensile stress of equal magnitude will
    be produced on another plane.

16
Types of Shear Reinforcement
  • Stirrups perpendicular to the axis of the member
    or making an angle of the member or making and
    angle of 45 degrees or more with the longitudinal
    tension reinforcement.
  • Welded wire fabric with wires located
    perpendicular to the axis of the member.
  • Longitudinal reinforcement with a bent portion
    making an angle of 30 degrees or more with
    longitudinal tension reinforcement.
  • Combinations of stirrups and bent longitudinal
    reinforcement.
  • Spirals.

17
Shear strength
  • Design of cross section subject to shear shall be
    based on
  • Where Vn nominal shear strength
  • Vu factored shear force at the section
    considered

18
Shear strength provided by concrete
  • For members subjected to shear and flexure only
    (Vc) is computed by
  • Where bw the width of web
  • d the distance from the extreme compression
    fiber to the centroid of the longitudinal tension
    reinforcement.

19
Shear strength provided by Shear Reinforcement
  • When shear reinforcement perpendicular to the
    axis of the member is used
  • Where Av the area of shear reinforcement with in
    distance s.
  • S Spacing between stirrups
  • Shear Strength Vs shall not be taken greater than

20
Minimum shear reinforcement
  • A minimum area of shear reinforcement shall be
    provided in all flexural members expect slab and
    footing where the factored shear force Vu exceeds
    one-half the shear strength
    provided by concrete 1/2.
  • The area provided shall not be less than
  • Where b and s are in inches.

21
Minimum shear reinforcement
  • Spacing of Shear Reinforcement
  • Spacing of shear reinforcement placed
    perpendicular to the axis of the member shall not
    exceed d/2 of 24 inches.
  • Shrinkage temperature reinforcement
  • Reinforcement for shrinkage and temperature
    stress shall be provided near exposed surfaces of
    walls and slabs not otherwise reinforced.
  • The total area of reinforcement provided shall be
    at least 1/8 square inch per foot in each
    direction.
  • The spacing of shrinkage and temperature
    reinforcement shall not exceed three times the
    wall or slab thickness, or 18 inches

22
Girder ( T Section )
  • The Total width of slab effective as a T-girder
    flange shall not exceed one-fourth of the span
    length of the girder.
  • The effective flange width overhanging on each
    side of the web shall not exceed six times the
    thickness of the slab or one-half the clear
    distance to the next web.

23
Recommended Minimum Depths for Constant Depth
Members.
24
Analysis of Pier Cap
25
Analysis of Pier Cap
  • Dead load of pier cap
  • Live load of pier cap

26
Dead load of pier cap
  • Estimate the thickness
  • L 50.54 ft
  • Length of span 25.27 ft
  • Minimum thickness of the bridge cap piers
  • Width (b) 0.5 Depth 3 ft

27
Dead load of pier cap
  • Own weight of pier cap Density of conc. area
    1
  • 150 Ib/ft 3 (6 3) 1
  • 2700 Ib/ft
  • Uniform wheel load wheel load S/6 Impact
    factor
  • 26 kip
  • Concentrated load from interior girder
  • 490 Ib
  • Concentrated load from interior girder
  • 546 Ib

28
Dead load of pier cap
Dead load
B.M.D
Shear force diagram
29
Live load of pier cap
  • Use several cases by distributing the wheel
    trucks.
  • Take the maximum wheel load 18000 Ib
  • Find the reactions in each supports for all
    cases.
  • Take the maximum values of reaction.

30
Live load of pier cap
  • These are the following cases
  • Case 1 Full shift left
  • Case 2 Full shift right
  • Case 3 Centre to left
  • Case 4 Centre to right
  • Case 5 one truck centre to left
  • Case 6 one truck to left
  • Case 7 one truck centre to right
  • Case 8 one truck to right

31
Live load of pier cap
  • Example of calculationsCase 3 Centre to left

32
Live load of pier cap
Uniform wheel load
  • ? M2 0
  • R1 ( 26 2.95 ) / 7.22 10.6 k
  • ? Fy 0
  • 10.6 R2 26 0
  • R2 15.4 k
  • ? M3 0
  • R2 ( 26 4.17 ) / 7.22 15 k
  • ? Fy 0
  • 15 R3 26 0
  • R3 11 k

33
Live load of pier cap
  • Reactions for eight cases

R8 R7 R6 R5 R4 R3 R2 R1
47.61 14.59 30.39 30.4 32 33.15 20.67 52.72 Cases 1
52.72 19.41 32.95 32.05 30.39 30.4 29.1 32.98 Cases 2
32.2 12.6 30.576 30.39 30.39 30.576 34.6 21.92 Cases 3
17.18 8.82 34.76 10.98 10.98 19.41 15.4 10.6 Cases 4
0 0 0 2.4 25 12.2 0 0 Case 5
0 0 0 0 0 14.5 29.4 24.6 Case 6
0 0 11.1 27.9 20.2 0 0 0 Case 7
10.8 12.2 23.4 0 0 0 0 0 Case 8
34
Maximum Values in Dead Load
Distance Maximum Shear Force
25.27 ft 104.57 kips
   
Distance Maximum positive moment
16.2346 ft 138.72 k-ft
   
Distance Maximum negative moment
25.27 ft 245.59 k-ft
35
Maximum Values in Live Load
  • Found the maximum in the same position of maximum
    dead load

Maximum Case 8 Case 7 Case 6 Case 5 Case 4 Case 3 Case 2 Case 1  
166.92 k 51.88 k 51.88 k 52.56 k 13.9 k 166.26 k 166.15 k 166.92 k 165.85 k Max. shear force
281.89 k-ft 48.63 k-ft Zero 7.52 k-ft Zero 270.27 k-ft 274.2 k-ft 281.89 k-ft 261.44 k-ft Max. positive moment
510.36 k-ft 60.1 k-ft 60.1 k-ft 70.47 k-ft 65.01 k-ft 510.36 k-ft 509.3 k-ft 502.89 k-ft 504.3 k-ft Max. negative moment
36
Maximum Values in Live Load
Maximum shear force in case 2
Maximum positive moment in case 2
37
Ultimate Moment Shear
271.49 k DL shear LL shear
420.61 k-ft DL pos. moment LL pos. moment
755.95 k-ft DL neg. moment LL neg. moment
38
Design Stage
39
Design of girder bridge
  • Design of slab by using Prokon software
  • Design the girders using manual calculation
    method
  • Design the pier cap by using Prokon software.

40
Design of Slab (Inputs)
  • Use PROKON for slab
  • Inputs Slab cross section

41
Design of Slab (Inputs)
42
Design of Slab (Inputs)
43
Design of Slab (Inputs)
44
Design of Slab (Outputs)
45
Design of Slab (Outputs)
  • Area of steel (As)

Bars As (Top) mm2 Bars As (Bottom) mm2
4 ? 22 1430 5 ? 16 924 Cantilever
8 ? 10 564 4 ? 16 614 Middle
46
Design of Girder (Inputs)
  • Use Hand Calculations Method

Negative Positive
2033.73 KN-m 4745.37 KN-m Interior
2033.73 KN-m 4745.37 KN-m Exterior
47
Design of Girder
  • Positive section
  • The following equations were used to compute Area
    of steel needed for the section (As)
  • Fy 420 MPa
  • Fc 21 MPa
  • Mu 4745 KN-m
  • b 2200.656 mm
  • d 1601.4 mm

48
Design of Girder
49
Design of Girder
  • Minimum Spacing of stirrups Maximum of
  • 600 mm
  • .
  • Use minimum Spacing (S) 600mm

50
Design of Girder
51
Design of Pier Cap (Inputs)
  • Using Prokon software to design
  • Inputs
  • Parameters
  • Fcu,
  • Fy,
  • D.L and L.L factors
  • density of concrete
  • Length of each span 7.7 m

52
Design of Pier Cap (Inputs)
53
Design of Pier Cap (Outputs)
54
Design of Pier Cap (Outputs)
  • Minimum spacing s maximum of (depth
    cover)/2 (1829-
    50)/2 890 mm

  • 600 mm
  • So minimum spacing (s) 890 mm.
  • Minimum number of bars length of span /
    Spacing 7700 / 890 8.6 9 bars
  • Take 10mm Stirrups diameter for the pier cap

55
Design of Pier Cap (Outputs)
56
Design of Pier Cap (Outputs)
bars As- Bottom (mm2) bars As-Top (mm2)  
9 10 0 9 43 12,000 Middle
9 13 889 10 19 2560 First End
57
Conclusion
  • Finish the analysis of pier cap.
  • Finish the design of superstructure for a girder
    bridge
  • Use SAP2000 and Prokon programs in design
  • The objective of GPII is fulfilled
  • Learn main concepts on structural analysis and
    design
Write a Comment
User Comments (0)
About PowerShow.com