66 - PowerPoint PPT Presentation

About This Presentation
Title:

66

Description:

1981--PCCP Condition Assessment and Inspection Program began--first used Visual ... Inspection includes visual and sounding, sonic/ultrasonic, electromagnetic ... – PowerPoint PPT presentation

Number of Views:59
Avg rating:3.0/5.0
Slides: 16
Provided by: Rand206
Category:
Tags: inspection

less

Transcript and Presenter's Notes

Title: 66


1
66 Water Main Break on River Roadand PCCP
Program
2
River Road 66-Inch FailureTimeline
  • December 23
  • Water Main Failed at 750am
  • CCT Emergency Call Center Notified Internal WSSC,
  • Both County Fire Boards and Health Departments
  • Main Shutdown
  • Ross Contracting Awarded Contract for Repair
  • December 24
  • Pepco Completed Power Line Repair
  • Ross Started Pipe Repairs
  • December 24-26
  • Washington Gas Repairs 24-inch Gas Main
  • December 26
  • WSSC Internally Inspected 1600 ft. of 66-Inch
  • December 30
  • WSSC Internally Inspected additional 400 ft. of
    66-Inch
  • Repairs/Cleaning of Cabin John Branch
  • December 31
  • Completed pipe repairs, began chlorination

3
WSSC Water Transmission and Distribution System

4
Sustainability Plan by Pipe Size
  • Composition and Miles of Pipe in WSSC System/Life
    Cycle
  • Pipe lt 16-- about 4500 miles of Ductile, Cast
    Iron, Unlined Cast Iron
  • Pipe gt 16 about 1000 miles of Steel, Cast Iron,
    Ductile Iron, PCCP
  • Life Expectancy--60 Years for Unlined Cast Iron
  • Life Expectancy--75-100 Years for Steel, Ductile
    Iron, Cast Iron, PCCP
  • Inspection/Monitoring/Repair/Replacement
  • Pipe lt 16 Current Water Reconstruction Program
  • Ramp up to 60 miles a year
  • Repair/Replace Based on Age, Maintenance History,
    Fire Flow Issues
  • Pipe 16 36 Adding to our Water
    Reconstruction Program
  • Ramp up to 15 miles
  • Cast Iron has low break rate, but aging is
    factor now
  • Pipe Above 36 Inspection and Monitoring are Key
  • - Iron -- Corrosion control, Valve Fire
    Hydrant MX
  • - PCCP -- Problematic Fails Catastrophically
    Without Warning

5
PCCP Program History
  • 1981--PCCP Condition Assessment and Inspection
    Program began--first used Visual and Sounding to
    identify deteriorated areas and delaminations
  • Late 1980s--WSSC worked with consultants and
    studied applicable non-destructive testing
    methods
  • Mid-1990s--Sonic/Ultrasonic Pulse Echo was
    adapted to PCCP and added to the
    Program--identifies micro-cracking and concrete
    out of compression.
  • 2001--Electromagnetic (RFEC/TC) testing was added
    to the Program--estimates number of broken
    pre-stressing wires in each pipe section
  • Early 2007, permanent Acoustical Fiber Optic
    (AFO) monitoring first installed-- monitors wire
    breaks following a baseline condition assessment
  • In late 2008, acoustical leak detection methods
    were added to the Program to be performed prior
    to dewatering for the inspections
  • Approximately 116 miles internally inspected to
    date AFO currently installed in 16.9 miles

6
PCCP Inspection History

7
PCCP Current Program
  • WSSC has a total of 357 miles of Pre-stressed
    Concrete Cylinder Pipe (PCCP) Water Mains
    including
  • 57 miles 54 and Greater
  • 86 miles 36 through 48
  • 214 miles 16 through 30
  • Annual inspection plan is based on risk rating
    assigned to 36 and larger (143 miles)
  • Risk rating based on pipe diameter, age, land
    use, operational criticality, repair history and
    date last inspected
  • Program focuses on mains 54-inch and
    greater--considered a higher risk due to their
    diameter, operational criticality, and highest
    consequence of failure
  • Current state of the industry for non-destructive
    PCCP inspection techniques requires manual
    operation and manned entry into the pipelines to
    perform the inspections     
  • Virtually all WSSC PCCP water mains 54-Inch and
    greater have been inspected 1-3 times the more
    problematic mains have been inspected 4-5 times

8
PCCP Current Program
  • Inspection includes visual and sounding,
    sonic/ultrasonic, electromagnetic survey,
    acoustical leak testing, long term acoustical
    monitoring
  • Establishes baseline condition, locates leaks,
    identifies needed repairs/replacements and
    planning for long term capital replacements
  • Engineering analysis done to determine if
    deteriorated pipes require replacement or can be
    repaired with carbon fiber internally or tendons
    externally
  • Permanent acoustical monitoring listens for
    additional wire break activity as early warning
    sign and establish rate of deterioration
  • Inspections take 2-3 months to perform
  • Shut down and dewater pipeline during colder
    months September through June when demand is
    lower
  • During higher water main break season
  • Cost per 12 miles for inspection and installation
    of Acoustical Fiber Optical Monitoring
  • 3 M

9
Inspection Interval and Annual Mileage
  • Preferred inspection interval for PCCP pipelines
    is 5 to 10 years 5 years for 48 and above to 10
    years for below 48
  • FY07 and FY08 PCCP Program mileage budget was 6
    miles inspection and 6 miles of installation of
    Acoustical Fiber Optic (AFO) monitoring results
    in inadequate and high risk 12 year inspection
    interval
  • At 12 miles per year, the 48 and larger
    pipelines would be on a near optimum inspection
    interval of 6 years 
  • In FY09, the Counties approved budget supplement
    to increase the PCCP mileage to 12 miles
    inspection miles and AFO installation 

10
Five Year Plan
  • FY09 12 Miles 1)Project 80 96-Inch and
    2)River Road 66-Inch
  • FY10 12 Miles 1)Rock Creek 54/60-Inch and
    2)Failed Mont. Co. 48-Inch
  • FY11 12 Miles 1)Mont. Co. High Zone 60-Inch
    and 2)White Oak 72-Inch
  • FY12 12 Miles 1)Prince Georges 54/60-Inch
    Supply Main, 2)Brightseat 54-Inch 3) I-270
  • FY13 18 Miles Mains less than 48-Inch

11
Looking Ahead
  • To close gap created by reduced inspection
    program in FY00 to FY06, increase mileage goals
    to 18 miles FY12- FY13 for 48 and larger
  • Steady-state inspections of 12 miles resumes in
    FY14
  • FY11 CIP Study/Design for Rehabilitation of
    60-Inch Adelphi Main
  • For diameters smaller than 48-inch, technology
    developments (estimated at FY12 and beyond) may
    allow
  • Unmanned inspections with the pipe full/partially
    full of water using current methods adapted to
    smaller pipe
  • May not require acoustical monitoring, be done at
    a lower cost in a shorter timeframe and at a 10
    year interval

12
Advancing Electromagnetic Techniques for PCCP lt
48-Inch
Adaption of Current Technology to Diameters
less than 48-inch.
Robotic (Unmanned) Electromagnetic P-Wave for
Small Diameter PCCP (lt 48)for use in Submerged
Conditions
13
Small Diameter Underwater Adaptable Visual
Inspection Tool
Fiber Optic Communication Cable/Tether
High Power Lighting and Cameras
  • Unmanned Underwater Small Diameter (lt 48)
  • Pipe Visual Inspection Tool Adaptable to other
    Technologies

14
Sustainable PCCP Program
  • A sustainable PCCP Inspection and Condition
    Assessment Program is Critical to the Mission of
    WSSC
  • A component of WSSCs Infrastructure Renewal Plan
  • Ensures timely inspection and repair of
    deteriorated pipe sections
  • Provides safer, more reliable water supply
  • Helps ensure the pipelines reach their intended
    useful life
  • Provides condition assessment for long term
    capital planning
  • Program must be a top budget priority and funded
    annually to assure public safety and reliability
    of the water supply

15
Questions
Write a Comment
User Comments (0)
About PowerShow.com