Title: 66
166 Water Main Break on River Roadand PCCP
Program
2River Road 66-Inch FailureTimeline
-
- December 23
- Water Main Failed at 750am
- CCT Emergency Call Center Notified Internal WSSC,
- Both County Fire Boards and Health Departments
- Main Shutdown
- Ross Contracting Awarded Contract for Repair
- December 24
- Pepco Completed Power Line Repair
- Ross Started Pipe Repairs
- December 24-26
- Washington Gas Repairs 24-inch Gas Main
- December 26
- WSSC Internally Inspected 1600 ft. of 66-Inch
- December 30
- WSSC Internally Inspected additional 400 ft. of
66-Inch - Repairs/Cleaning of Cabin John Branch
- December 31
- Completed pipe repairs, began chlorination
3WSSC Water Transmission and Distribution System
4Sustainability Plan by Pipe Size
- Composition and Miles of Pipe in WSSC System/Life
Cycle - Pipe lt 16-- about 4500 miles of Ductile, Cast
Iron, Unlined Cast Iron - Pipe gt 16 about 1000 miles of Steel, Cast Iron,
Ductile Iron, PCCP - Life Expectancy--60 Years for Unlined Cast Iron
- Life Expectancy--75-100 Years for Steel, Ductile
Iron, Cast Iron, PCCP - Inspection/Monitoring/Repair/Replacement
- Pipe lt 16 Current Water Reconstruction Program
- Ramp up to 60 miles a year
- Repair/Replace Based on Age, Maintenance History,
Fire Flow Issues - Pipe 16 36 Adding to our Water
Reconstruction Program - Ramp up to 15 miles
- Cast Iron has low break rate, but aging is
factor now - Pipe Above 36 Inspection and Monitoring are Key
- - Iron -- Corrosion control, Valve Fire
Hydrant MX - - PCCP -- Problematic Fails Catastrophically
Without Warning
5PCCP Program History
- 1981--PCCP Condition Assessment and Inspection
Program began--first used Visual and Sounding to
identify deteriorated areas and delaminations - Late 1980s--WSSC worked with consultants and
studied applicable non-destructive testing
methods - Mid-1990s--Sonic/Ultrasonic Pulse Echo was
adapted to PCCP and added to the
Program--identifies micro-cracking and concrete
out of compression. - 2001--Electromagnetic (RFEC/TC) testing was added
to the Program--estimates number of broken
pre-stressing wires in each pipe section - Early 2007, permanent Acoustical Fiber Optic
(AFO) monitoring first installed-- monitors wire
breaks following a baseline condition assessment - In late 2008, acoustical leak detection methods
were added to the Program to be performed prior
to dewatering for the inspections - Approximately 116 miles internally inspected to
date AFO currently installed in 16.9 miles
6PCCP Inspection History
7PCCP Current Program
-
- WSSC has a total of 357 miles of Pre-stressed
Concrete Cylinder Pipe (PCCP) Water Mains
including - 57 miles 54 and Greater
- 86 miles 36 through 48
- 214 miles 16 through 30
- Annual inspection plan is based on risk rating
assigned to 36 and larger (143 miles) - Risk rating based on pipe diameter, age, land
use, operational criticality, repair history and
date last inspected - Program focuses on mains 54-inch and
greater--considered a higher risk due to their
diameter, operational criticality, and highest
consequence of failure - Current state of the industry for non-destructive
PCCP inspection techniques requires manual
operation and manned entry into the pipelines to
perform the inspections - Virtually all WSSC PCCP water mains 54-Inch and
greater have been inspected 1-3 times the more
problematic mains have been inspected 4-5 times
8PCCP Current Program
-
- Inspection includes visual and sounding,
sonic/ultrasonic, electromagnetic survey,
acoustical leak testing, long term acoustical
monitoring - Establishes baseline condition, locates leaks,
identifies needed repairs/replacements and
planning for long term capital replacements - Engineering analysis done to determine if
deteriorated pipes require replacement or can be
repaired with carbon fiber internally or tendons
externally - Permanent acoustical monitoring listens for
additional wire break activity as early warning
sign and establish rate of deterioration - Inspections take 2-3 months to perform
- Shut down and dewater pipeline during colder
months September through June when demand is
lower - During higher water main break season
- Cost per 12 miles for inspection and installation
of Acoustical Fiber Optical Monitoring - 3 M
9Inspection Interval and Annual Mileage
- Preferred inspection interval for PCCP pipelines
is 5 to 10 years 5 years for 48 and above to 10
years for below 48 - FY07 and FY08 PCCP Program mileage budget was 6
miles inspection and 6 miles of installation of
Acoustical Fiber Optic (AFO) monitoring results
in inadequate and high risk 12 year inspection
interval - At 12 miles per year, the 48 and larger
pipelines would be on a near optimum inspection
interval of 6 years - In FY09, the Counties approved budget supplement
to increase the PCCP mileage to 12 miles
inspection miles and AFO installation
10Five Year Plan
- FY09 12 Miles 1)Project 80 96-Inch and
2)River Road 66-Inch - FY10 12 Miles 1)Rock Creek 54/60-Inch and
2)Failed Mont. Co. 48-Inch - FY11 12 Miles 1)Mont. Co. High Zone 60-Inch
and 2)White Oak 72-Inch - FY12 12 Miles 1)Prince Georges 54/60-Inch
Supply Main, 2)Brightseat 54-Inch 3) I-270 - FY13 18 Miles Mains less than 48-Inch
11Looking Ahead
- To close gap created by reduced inspection
program in FY00 to FY06, increase mileage goals
to 18 miles FY12- FY13 for 48 and larger - Steady-state inspections of 12 miles resumes in
FY14 - FY11 CIP Study/Design for Rehabilitation of
60-Inch Adelphi Main - For diameters smaller than 48-inch, technology
developments (estimated at FY12 and beyond) may
allow - Unmanned inspections with the pipe full/partially
full of water using current methods adapted to
smaller pipe - May not require acoustical monitoring, be done at
a lower cost in a shorter timeframe and at a 10
year interval
12Advancing Electromagnetic Techniques for PCCP lt
48-Inch
Adaption of Current Technology to Diameters
less than 48-inch.
Robotic (Unmanned) Electromagnetic P-Wave for
Small Diameter PCCP (lt 48)for use in Submerged
Conditions
13Small Diameter Underwater Adaptable Visual
Inspection Tool
Fiber Optic Communication Cable/Tether
High Power Lighting and Cameras
- Unmanned Underwater Small Diameter (lt 48)
- Pipe Visual Inspection Tool Adaptable to other
Technologies
14Sustainable PCCP Program
- A sustainable PCCP Inspection and Condition
Assessment Program is Critical to the Mission of
WSSC - A component of WSSCs Infrastructure Renewal Plan
- Ensures timely inspection and repair of
deteriorated pipe sections - Provides safer, more reliable water supply
- Helps ensure the pipelines reach their intended
useful life - Provides condition assessment for long term
capital planning - Program must be a top budget priority and funded
annually to assure public safety and reliability
of the water supply
15Questions