The International Linear Collider - PowerPoint PPT Presentation

1 / 45
About This Presentation
Title:

The International Linear Collider

Description:

The International Linear Collider – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 46
Provided by: barry182
Category:

less

Transcript and Presenter's Notes

Title: The International Linear Collider


1
  • The International Linear Collider

Gerry Dugan ILC/GDE and Cornell University
2
Why ee- Collisions?
  • elementary particles
  • well-defined
  • energy,
  • angular momentum
  • uses full COM energy
  • produces particles democratically
  • can mostly fully reconstruct events

3
A Rich History as a Powerful Probe
4
The Energy Frontier
5
International Linear Collider The Global Design
EffortMission
  • Produce a design for the ILC that includes a
    detailed design concept, performance assessments,
    reliable international costing, an
    industrialization plan , siting analysis, as well
    as detector concepts and scope.
  • Coordinate worldwide prioritized proposal driven
    R D efforts (to demonstrate and improve the
    performance, reduce the costs, attain the
    required reliability, etc.)

6
GDE Organization
7
Formation of the Global Design Effort
  • Director Barry Barish Appointed in March 2005
  • Appointed Regional Directors (Gerry Dugan
    (Americas), Fumihiko Takasaki (Asia), Brian
    Foster (Europe))
  • Three regional directors have identified GDE
    members (with agreement from BB)
  • Currently 66 members, representing approximately
    25 FTE
  • GDE Central Team consists of
  • core accelerator physics experts
  • 3 CFS experts (1 per region)
  • 3 costing engineers (1 per region)
  • 3 communicators (1 per region)
  • representatives from World Wide Study

8
GDE Central team
Chris Adolphsen, SLAC Deepa Angal-Kalinin,
CCLRC Jean-Luc Baldy, CERN Philip Bambade, LAL,
Orsay Barry Barish, Caltech (the boss) Wilhelm
Bialowons, DESY Grahame Blair, Royal Holloway Jim
Brau, University of Oregon Karsten Buesser,
DESY Elizabeth Clements, Fermilab Michael
Danilov, ITEP Jean-Pierre Delahaye, CERN (EU dep.
dir.) Gerald Dugan, Cornell University (Americas
dir.) Atsushi Enomoto, KEK Brian Foster, Oxford
University (EU dir.) Warren Funk, JLAB Jie Gao,
IHEP Peter Garbincius, Fermilab Terry Garvey,
LAL-IN2P3 Susanna Guiducci, INFN Hitoshi Hayano,
KEK Tom Himel, SLAC Maxine Hronek, Fermilab Bob
Kephart, Fermilab Eun San Kim, Pohang Acc
Lab Hyoung Suk Kim, Kyungpook Natl Univ Shane
Koscielniak, TRIUMF Kyoshi Kubo, KEK Vic Kuchler,
Fermilab Masao Kuriki, KEK Lutz Lilje, DESY
Tom Markiewicz, SLAC David Miller, Univ College
of London Shekhar Mishra, Fermilab Youhei Morita,
KEK Alex Mueller, LAL-IN2P3 Norihito Ohnchi,
KEK Hasan Padamsee, Cornell University Carlo
Pagani, DESY Nan Phinney, SLAC Dieter Proch,
DESY Pantaleo Raimondi, INFN Tor Raubenheimer,
SLAC Francois Richard, LAL-IN2P3 Marc Ross,
SLAC Perrine Royole-Degieux, GDE/LAL Kenji Saito,
KEK Andrei Seryi, SLAC Daniel Schulte, CERN John
Sheppard, SLAC Tetsuo Shidara, KEK Sasha
Skrinsky, Budker Institute Fumihiko Takasaki, KEK
(Asia dir.) Laurent Jean Tavian, CERN Nobuhiro
Terunuma, KEK Nobu Toge, KEK Nick Walker, DESY
(EU dep. dir.) William Willis, Columbia
University Andy Wolski, LBL Hitoshi Yamamoto,
Tohoku Univ Kaoru Yokoya, KEK 66 members
9
  • International Linear Collider Timeline

2005 2006 2007 2008
2009 2010
Global Design Effort
Project
Baseline configuration
Reference Design
Technical Design
ILC RD Program
Expression of Interest to Host
International Mgmt
10
Global Design Effort organization-International
Management Phase
11
Starting Point for the GDE
Superconducting RF Main Linac
12
Parameters for the ILC
  • Ecm adjustable from 200 500 GeV
  • Luminosity ? ?Ldt 500 fb-1 in 4 years
  • Ability to scan between 200 and 500 GeV
  • Energy stability and precision below 0.1
  • Electron polarization of at least 80
  • The machine must be upgradeable to 1 TeV

13
Scope of the 500 GeV machine
  • Main linacs length 21 km, 20,000 RF cavities
    (total)
  • RF power 600 10-MW klystrons and modulators
    (total)
  • Cryoplants 6 plants, cooling power 30 kW (_at_4K)
    each
  • Beam delivery length 3 km, 200 magnets
    (total)
  • Damping ring circumference 6 km, 400 magnets
    (each)
  • Beam power 22 MW total
  • Site power 200 MW total
  • Site footprint length 47 km (for option to
    future upgrade to 1 TeV)
  • Bunch profile at IP 500 x 6 nm, about 300
    microns long

14
Accelerator Physics Challenges
  • Developing efficient high gradient
    superconducting RF systems
  • Requires efficient RF systems, capable of
    accelerating high power beams (MW) with small
    beam spots (nm).
  • Achieving nm scale high-power beam spots
  • Requires generating high intensity beams of
    electrons and positrons
  • Damping the beams to ultra-low emittance in
    damping rings
  • Transporting the beams to the collision point
    without significant emittance growth or
    uncontrolled beam jitter
  • Cleanly dumping the used beams.

15
Affordability challenges
Civil
SCRF Linac
16
GDE Design Approach
Create a baseline configuration for the machine
Document a concept for ILC machine with a
complete layout, parameters, etc. defined by the
end of 2005. This process continued much of the
design work of the past decade, including the
recent ILC workshops at KEK (Nov. 2004) and
Snowmass (Aug. 2005).
17
GDE Baseline Design
  • Make forward looking choices, consistent with
    attaining performance goals, and understood well
    enough to do a conceptual design and reliable
    costing by end of 2006. Technical and cost
    considerations will be an integral part in making
    these choices.
  • Establish alternate configurations which may
    have cost and or performance benefits, but which
    need further RD for validation.
  • - Baseline is under configuration control,with
    a defined process for changes to the baseline.

18
ILC Baseline Configuration
  • Configuration for 500 GeV machine with
    expandability to 1 TeV
  • Some details locations of low energy
    acceleration crossing angles are not indicated
    in this cartoon.

19
ILC Baseline Layout
20
ILC Baseline Layout-IR area
21
Baseline Gradient
22
The Main Linac Configuration
  • Klystron 10 MW (alternative sheet beam
    klystron)
  • RF Configuration 3 Cryomodules, each with 8
    cavities
  • Quads one every 24 cavities is enough

23
Other Features of the Baseline
  • Positron Source Helical Undulator with
    Polarized beams

24
ILC Siting and Conventional Facilities
  • The design is intimately tied to the features of
    the site
  • 1 tunnels or 2 tunnels?
  • Deep or shallow?
  • Laser straight linac or follow earths curvature
    in segments?
  • GDE ILC Design will be done to samples sites in
    the three regions
  • North American sample site will be near Fermilab
  • Japan and Europe are to determine sample sites by
    the end of 2005

25
Americas Sample Site
  • Design to sample sites from each region
  • Americas near Fermilab
  • Japan
  • Europe CERN DESY
  • Illinois Site depth 135m
  • Glacially derived deposits overlaying Bedrock.
    The concerned rock layers are from top to bottom
    the Silurian dolomite, Maquoketa dolomitic shale,
    and the Galena-Platteville dolomites.

26
GDE Reference Design and Technical Design
  • A reference design and cost estimate will be
    carried out in 2006. A parametric design and
    costing approach will be used.
  • Technical performance and physics performance
    will be evaluated for the reference design.
  • Subsequently, in 2007 and beyond, a full
    Technical Design will be developed, based on a
    specific site, including a fully-developed cost
    estimate, and supported by a global RD program.
  • The goal is to have the project ready for a
    construction start decision around 2010.

27
Reference Design Report Matrix
28
Preliminary unofficial draft tentative RDR
schedule (not yet confirmed)
  • Jan 19-20 KEK meeting. Orient Area systems
    managers, define layouts and ML basic unit
  • Feb 13-14 FNAL mtg Review ML and BDS optic,
    Iterate availability budgets, Agree to RDR
    Outline and writing assignments, Review costing
    methodology for SC cryomodules
  • March 9-11 GDE, Bangalore Review costing
    procedures esp. SC cryomodules, Review AS
    progress and plans, Review design parameter
    balance, Review TS and GS progress and plans
    including resources, Review status on costing
    major linac items, Review/optimize linac civil
    layout after soliciting comments from experts
  • April (tbc) DESY mtg Review RF power,
    cryomodule, and cavity TS, Review e-, e, RTML
    optics, DR Optics, Presentation on LLRF and beam
    instrumentation systems and cost estimates
  • July 19-23 GDE, Vancouver Review ILC design and
    cost, Review AS physics studies, Review write-up
    progress, propose cost trades and design
    modifications
  • Nov 6-8 GDE, Valencia Finalize RDR

29
Test Facility at KEK
30
Test Facility at SLAC
31
TESLA Test Facility Linac - DESY
240 MeV
120 MeV
16 MeV
4 MeV
32
Cryomodule string test ILCTA-NML at Fermilab
New Muon Lab (NML)
FNPL Photo-Injector
  • Building a dedicated ILC cryomodule string test
    facility in the New Muon Lab
  • Building is cleaned out except for removal of CCM
    ( in progress)
  • Started to install cryogenic system
  • Move FNPL Photo-injector to provide electron beam
    (Late FY06)
  • Upgraded FNPL will provide beam tests of ILC
    cryomodules

33
(No Transcript)
34
ILC Costs
  • The ILC will be built as an international joint
    project, in which the three regions will
    contribute mainly in kind (specific components)
  • The general concept is that the host country pays
    for most of the civil work and support
    infrastructure. This will be 25 of the total.
    This extra contribution by the host must be at a
    level where it is attractive to host the ILC.
    The high tech part of the project (75) will be
    equally shared by the three regions (at least
    that is the present thinking)
  • Cost estimates must be done in the context of the
    in-kind contribution model.
  • The cost estimate should provide a realistic and
    sufficient basis for the regions to make their
    decision on the scope of their involvement and
    to select the desirable systems/components for
    them to manufacture.
  • An example of how this has been done is the ITER
    project

35
International Thermonuclear Experimental Reactor
36
ITER cost estimate
  • Define procurement packages-information needed
    by suppliers to prepare contracts.
  • Obtain estimates from suppliers in different
    regions.
  • ITER project Central Team compares and
    re-evaluates estimates from the different
    regions.
  • The Evaluated Cost Estimates are expressed in
    a globally unified virtual money, i.e. ITER Unit
    Account (IUA) . (1000 in Jan, 1989)
  • These cost estimates are based on world market
    prices for standard material and equipment, and
    rates in IUA/hr for assembly labor and
    manufacturing support.

37
ITER cost estimate
  • This approach is taken to remove variations in
    costs due to differences in estimating practices
    and exchange rates in the several regions. This
    approach is most valid for items for which
    manufacturing processes are well defined.
  • The detailed basic data in IUA can be used for
    cost optimization and cost reduction studies.
  • These data are the basis on which the allotment
    of in-kind contributions to each region is made.
  • Because the cost borne by a given region to
    supply its in-kind contribution will in general
    differ from the nominal cost in translated IUA,
    the actual cost of the ITER project will never be
    known.

38
ILC Cost estimates
  • ILC cost estimates must be done in the context of
    a project implemented through in-kind
    contributions.
  • We will need to secure regional component cost
    estimates and evaluate these in terms of a
    globally defined cost unit. (ILC unit)
  • The complete cost estimate will be translatable
    into a given regions currency and cost
    estimating methodology.
  • Because of these differences, the projects cost
    on paper will appear different in different
    regions.

39
ILC cost estimate
  • Negotiations between the regions will decide the
    relative regional in-kind contributions, based on
    the values in ILC units.
  • The host region will bear the conventional
    construction costs.
  • In-kind contributions, which are the
    responsibility of the region to make good on
    their contribution, reduce the risk to the
    project.
  • Central resources must have shared
    responsibility, and responsibility for
    non-delivery by a region must be shared by the
    collaboration in a pre-agreed manner.
  • The true cost of the in-kind contributions will
    not be easily determined after completion of the
    project.
  • Cost reduction strategies must be worked out with
    regional or international industrial partners.

40
ILC Industrialization
  • Three industrial forums have been formed to
    support the industrialization of the ILC

Linear Collider Forum of Japan Linear Collider
Forum of America European Superconducting RF Forum
The purpose of the Industrial Forums is to bring
industry, national laboratories, and universities
together at an early stage to plan the ILC in an
industrial context.
41
Industrialization issues
  • ILC will be viewed as a project, not a
    sustainable business area, therefore it must be
    prepared to fund one time manufacturing
    engineering and tooling costs.
  • Long term funding uncertainties create barriers
    to major industry commitments to the ILC
  • In general, technology will flow from labs to
    small companies small companies will partner
    with larger ones for full scale production
  • ILC test facilities at key labs will accelerate
    tech transfer
  • Specifications can be a major cost driver and
    must be critically evaluated
  • Costs, risk and schedule are interrelated, must
    be understood and agreed to by everyone.

42
Industrialization issues
  • Infrastructure Issues
  • For industry to invest in the large
    infrastructure required for ILC there would have
    to be a follow-on business or market
  • the ILC project should plan on paying for the
    major infrastructure wherever it is built.
  • Early standardization is important
  • Can deal with whatever standards ILC chooses
  • Risks
  • Let industry make up its mind on risks
  • Perceived risks will influence the actual cost of
    contracts from industry

43
Cost Reductions viaindustrialization
  • Each industrial company is characterized by its
    own production technologies including production
    facility, engineering skill, etc.
  • When the design configuration and fabrication
    process of the ILC components fit to existing
    production technologies, cost may be reduced,
    because no additional investment is necessary.
  • Reviews of product design and fabrication
    processes are therefore very important.

44
Cost Reductions viaindustrialization
  • Cost at industry scale fabrication is lower than
    that at laboratory scale fabrication. But dont
    expect too much for cost reduction through mass
    production, because ILC is not large enough for
    getting meaningful learning effects.
  • Quantitative analysis, through industrial
    studies, is necessary.
  • Joint factories can avoiding duplicated
    investments
  • Electro-chemical polishing facility
  • EBW facility
  • Test facility using liquid helium
  • These facilities might be used by industry with a
    reasonable charge (rental factory). It does not
    matter whether these facilities are located
    on-site or off-site.

45
Conclusions
  • The International Linear Collider is a major new
    particle accelerator for the precision study of
    fundamental physics at the TeV scale using ee-
    colliding beams.
  • The project is being designed by an international
    team and will be executed as a fully
    international project, with participation from
    the Americas, Asia and Europe.
  • The project offers major new challenges in
    accelerator design and accelerator technology
    development, cost optimization, the development
    of effective management structures for global
    collaboration, and trans-national
    industrialization.
Write a Comment
User Comments (0)
About PowerShow.com