Title: New Zealand Transport Agency and NZIHT 9th Annual Conference
1 New Zealand Transport Agency and NZIHT 9th
Annual Conference Improving the Road Network
Right Price, Done the Right Way, at the Right
Time Road Infrastructure Financing For Safe,
Reliable and Affordable Transport 12 14 October
2008 NAPIER NEW ZEALAND Nazir Alli
379701
2Needs To Be Addressed
- ? Decaying infrastructure services
- ? Poor service delivery
- ? Meeting basic needs
- ? New infrastructure services
- ? Inability to obtain finance for capital
investments
3Financing
- Government
- Traditionally
- Social goods
- Nominal cost recovery
4Private Sector (?)
- Fear
- Natural monopoly
- Payback period
- Political risks
5Options
- Service Contracts - limited benefits
- Management Contracts
- Concessioning - the first step to private
participation - BOT, BOO etc - direct private involvement
- Divestment - another route to full-fledged
private participation
6Allocation of Responsibilities
7(No Transcript)
8Selecting Option
- Government objectives
- What needs addressing?
- What will government do?
- Countrys attractiveness to private investor
9Why PPPs?
- ? Financing requirements outstrip resources
available from tax-based revenues - ? Government negotiates investments through
diverse sources through private sector - ? Cost effective and appropriately adapted
- ? Improvements and preservation beyond MTEF
horizon
10Considerations
- ? Compare the results of PPP process with public
sector ownership - - BUT use an appropriate private sector cost
of funds in governments instance - - look to market comparables
- ? If private sector assumes real risks, it is
impractical to hold private sector to government
cost of funds
11Considerations (Cont.)
- ? Extra Cost of private financing is what
government is paying to off-load project risk - ? Procurement analysis must ask the question
- - Is government being charged the right price
to off-load these risks?
12Relative Cost of Funds
- ? What do the public and private cost of
financing reflect? - ? Government bond financing
- - rates reflect the risk that government will
not be able to tax citizens to extent needed to
cover outlays i.e. its power to tax
13 Relative Cost of Funds (Cont.)
- ? Private sector financing
- - rates reflect the capital markets judgment
as to the riskiness of investing in the debt
and equity securities of the project i.e.
projects or companies - ? Risk of project exist
- no matter who owns it!
14Challenge
- ? Determine optimum mixture of public and private
resources - - optimum method of providing a public good at
acceptable levels of quality and price - ? Determine if public sector can deliver service
(manage risk) at lower cost than private sector
15Risk Regime
- ? Traffic
- ? Financial
- ? Political
- ? Pre-development
- ? Construction
- ? Operation
- ? Commercial
- ? Legal
- ? Societal concerns
16SOCIETAL CONCERNS
-
- - Income transfers
- - Environmental problems
- - Attitude towards taxation
- both by government and
- citizens
- - Role of government
-
17Typical Project Structure
Sponsors
Loan Security
Equity investment
Financiers
Government (the grantor)
Project Company (SPV) (Concessionaire)
Concession
Roads Authority
Toll Road
Construction contractor
Operation and maintenance contract
Operator
Construction contract
Adapted World Bank 1997
18Constraints Complexity
Independent
Engineer
Concessor (State)
Engineer Agreement
Insurance providers
Concession contract
Contractor JV
Project Insurance
Construction contract
Operation contract
Subscription agreement Shareholders agreement
Loan Agreement
Equity Investor
Operation Company
Bank Lenders
Lenders Technical Adviser
Typical Structure
19Constraints (Cont.)Objectives of parties
20Predevelopment Period Risks
- Period ?Conception to financial closure
- Feasibility Studies
- - detailed and realistic
- - financially viable
- - socially acceptable
-
-
21Predevelopment Period Risks (Cont.)
- Permits
- - environmental
- - zoning
- - tolling
-
-
22Construction Period Risks
- Focus
- - complete on time
- - within budget
- - according to specifications
-
-
23Construction Period Risks (Cont.)
- Breach of Contract
- - main Contractor
- - sub-contractors
- - equipment suppliers
- Remedies
- - Performance bonus
- - Phased payment
- - Guarantess
-
-
24Construction Period Risks (Cont.)
- Delays
- - change in scope
- - weather
- - poor performance
-
-
25Construction Period Risks (Cont.)
- Cost Overruns
- Finance
- - project sponsor
- - equity participants
- Remedies
- - fixed price turnkey
- - completion guarantees
- - standby letters of credit
- - security interests
26Construction Period Risks (Cont.)
- Force Majeure
- Lack of Adequate Infrastructure
- - remoteness of site
- Remedies
- - Builders all risk insurance
- - Negotiable buyout (political risk)
27Operational Period Risks
- Political Risks
- - changes in legislation
- - inaction of government
- - materially adverse government action
- Remedies
- - Insurance
- ? MIGA
- ? private companies
- - Government as equity partner
28Operational Period Risks (Cont.)
- Legal Risks
- - access to courts
- Remedies
- - Governing law provisions
- - Arbitration provisions
- Related Party risk
- - special purpose vehicle
-
29Operational Period Risks (Cont.)
- Non-payment of debt
- - lenders
- - equity participants
- - exchange differentials
- Remedies
- - Reserve funds
- - Currency swaps
-
30Operational Period Risks (Cont.)
- Market risk
- - access to local financial markets
- Management Capability
- - operator (OM contracts)
- Force Majeure
-
31- LESSONS LEARNT
- ?Not all Roads can be Concessioned
- No Free Roads - The User Pay Principle is the
Most Equitable Means - Of Road Funding
- Utilise Internationally Recognised Best
Practices - Strengthen In House Experience - Be Hands On
- Work From an Established Platform
- Do Not Rush the Process
- Be Transparent
- Get Public Buy In
- Set Clear Outcome Parameters -Engineering
- -Environmental
- -Entrepreneurial Development
- Strict Law Enforcement
- Introduce a Highway Usage Fee (Huf)
32Conclusion
- Transparent process
- Demonstrate value for money
- Balance
- - risk
- - reward
- Risk allocated to party best able to manage and
mitigate -
33 THANK YOU
www.nra.co.za