New Zealand Transport Agency and NZIHT 9th Annual Conference - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

New Zealand Transport Agency and NZIHT 9th Annual Conference

Description:

Force Majeure. Lack of Adequate Infrastructure - remoteness of site. Remedies ... Force Majeure. 31. LESSONS LEARNT. Not all Roads can be Concessioned ... – PowerPoint PPT presentation

Number of Views:81
Avg rating:3.0/5.0
Slides: 34
Provided by: heinn
Category:

less

Transcript and Presenter's Notes

Title: New Zealand Transport Agency and NZIHT 9th Annual Conference


1
New Zealand Transport Agency and NZIHT 9th
Annual Conference Improving the Road Network
Right Price, Done the Right Way, at the Right
Time Road Infrastructure Financing For Safe,
Reliable and Affordable Transport 12 14 October
2008 NAPIER NEW ZEALAND Nazir Alli
379701
2
Needs To Be Addressed
  • ? Decaying infrastructure services
  • ? Poor service delivery
  • ? Meeting basic needs
  • ? New infrastructure services
  • ? Inability to obtain finance for capital
    investments

3
Financing
  • Government
  • Traditionally
  • Social goods
  • Nominal cost recovery

4
Private Sector (?)
  • Fear
  • Natural monopoly
  • Payback period
  • Political risks

5
Options
  • Service Contracts - limited benefits
  • Management Contracts
  • Concessioning - the first step to private
    participation
  • BOT, BOO etc - direct private involvement
  • Divestment - another route to full-fledged
    private participation

6
Allocation of Responsibilities
7
(No Transcript)
8
Selecting Option
  • Government objectives
  • What needs addressing?
  • What will government do?
  • Countrys attractiveness to private investor

9
Why PPPs?
  • ? Financing requirements outstrip resources
    available from tax-based revenues
  • ? Government negotiates investments through
    diverse sources through private sector
  • ? Cost effective and appropriately adapted
  • ? Improvements and preservation beyond MTEF
    horizon

10
Considerations
  • ? Compare the results of PPP process with public
    sector ownership
  • - BUT use an appropriate private sector cost
    of funds in governments instance
  • - look to market comparables
  • ? If private sector assumes real risks, it is
    impractical to hold private sector to government
    cost of funds

11
Considerations (Cont.)
  • ? Extra Cost of private financing is what
    government is paying to off-load project risk
  • ? Procurement analysis must ask the question
  • - Is government being charged the right price
    to off-load these risks?

12
Relative Cost of Funds
  • ? What do the public and private cost of
    financing reflect?
  • ? Government bond financing
  • - rates reflect the risk that government will
    not be able to tax citizens to extent needed to
    cover outlays i.e. its power to tax

13
Relative Cost of Funds (Cont.)
  • ? Private sector financing
  • - rates reflect the capital markets judgment
    as to the riskiness of investing in the debt
    and equity securities of the project i.e.
    projects or companies
  • ? Risk of project exist
  • no matter who owns it!

14
Challenge
  • ? Determine optimum mixture of public and private
    resources
  • - optimum method of providing a public good at
    acceptable levels of quality and price
  • ? Determine if public sector can deliver service
    (manage risk) at lower cost than private sector

15
Risk Regime
  • ? Traffic
  • ? Financial
  • ? Political
  • ? Pre-development
  • ? Construction
  • ? Operation
  • ? Commercial
  • ? Legal
  • ? Societal concerns

16
SOCIETAL CONCERNS
  • - Income transfers
  • - Environmental problems
  • - Attitude towards taxation
  • both by government and
  • citizens
  • - Role of government

17
Typical Project Structure
Sponsors
Loan Security
Equity investment
Financiers
Government (the grantor)
Project Company (SPV) (Concessionaire)
Concession
Roads Authority
Toll Road
Construction contractor
Operation and maintenance contract
Operator
Construction contract
Adapted World Bank 1997
18
Constraints Complexity
Independent
Engineer
Concessor (State)
Engineer Agreement
Insurance providers
Concession contract
Contractor JV
Project Insurance
Construction contract
Operation contract
Subscription agreement Shareholders agreement
Loan Agreement
Equity Investor
Operation Company
Bank Lenders
Lenders Technical Adviser
Typical Structure
19
Constraints (Cont.)Objectives of parties
20
Predevelopment Period Risks
  • Period ?Conception to financial closure
  • Feasibility Studies
  • - detailed and realistic
  • - financially viable
  • - socially acceptable

21
Predevelopment Period Risks (Cont.)
  • Permits
  • - environmental
  • - zoning
  • - tolling

22
Construction Period Risks
  • Focus
  • - complete on time
  • - within budget
  • - according to specifications

23
Construction Period Risks (Cont.)
  • Breach of Contract
  • - main Contractor
  • - sub-contractors
  • - equipment suppliers
  • Remedies
  • - Performance bonus
  • - Phased payment
  • - Guarantess

24
Construction Period Risks (Cont.)
  • Delays
  • - change in scope
  • - weather
  • - poor performance

25
Construction Period Risks (Cont.)
  • Cost Overruns
  • Finance
  • - project sponsor
  • - equity participants
  • Remedies
  • - fixed price turnkey
  • - completion guarantees
  • - standby letters of credit
  • - security interests

26
Construction Period Risks (Cont.)
  • Force Majeure
  • Lack of Adequate Infrastructure
  • - remoteness of site
  • Remedies
  • - Builders all risk insurance
  • - Negotiable buyout (political risk)

27
Operational Period Risks
  • Political Risks
  • - changes in legislation
  • - inaction of government
  • - materially adverse government action
  • Remedies
  • - Insurance
  • ? MIGA
  • ? private companies
  • - Government as equity partner

28
Operational Period Risks (Cont.)
  • Legal Risks
  • - access to courts
  • Remedies
  • - Governing law provisions
  • - Arbitration provisions
  • Related Party risk
  • - special purpose vehicle

29
Operational Period Risks (Cont.)
  • Non-payment of debt
  • - lenders
  • - equity participants
  • - exchange differentials
  • Remedies
  • - Reserve funds
  • - Currency swaps

30
Operational Period Risks (Cont.)
  • Market risk
  • - access to local financial markets
  • Management Capability
  • - operator (OM contracts)
  • Force Majeure

31
  • LESSONS LEARNT
  • ?Not all Roads can be Concessioned
  • No Free Roads - The User Pay Principle is the
    Most Equitable Means
  • Of Road Funding
  • Utilise Internationally Recognised Best
    Practices
  • Strengthen In House Experience - Be Hands On
  • Work From an Established Platform
  • Do Not Rush the Process
  • Be Transparent
  • Get Public Buy In
  • Set Clear Outcome Parameters -Engineering
  • -Environmental
  • -Entrepreneurial Development
  • Strict Law Enforcement
  • Introduce a Highway Usage Fee (Huf)

32
Conclusion
  • Transparent process
  • Demonstrate value for money
  • Balance
  • - risk
  • - reward
  • Risk allocated to party best able to manage and
    mitigate

33

THANK YOU

www.nra.co.za
Write a Comment
User Comments (0)
About PowerShow.com