Review - PowerPoint PPT Presentation

About This Presentation
Title:

Review

Description:

This is likely the last time that we will review our overall ... Move to anechoic chamber. Run LPT: in anechoic chamber, prior to test. Perform EMI/EMC testing ... – PowerPoint PPT presentation

Number of Views:15
Avg rating:3.0/5.0
Slides: 8
Provided by: Martin437
Category:
Tags: anechoic | review

less

Transcript and Presenter's Notes

Title: Review


1
LAT Environmental Test Planning and Design
Review 3-4 May 2005 Overview
Martin Nordby
2
Goals of This Review
  • Where we are now
  • This is likely the last time that we will review
    our overall test program for the LAT
    environmental testing until the Test Readiness
    Review
  • Much of what we will be presenting and reviewing
    has been gone over in one forum or another over
    the past 3-4 months, but not all in one place and
    time
  • Goals of this review
  • 1. Approve the environmental test sequenceboth
    the general sequence of tests, as well as the
    specific sequencing of the segments of each test
    that are presented as part of the individual test
    plans
  • 2. Approve the preliminary designs for the test
    MGSE and EGSE for all of the tests
  • 3. Approve the goals and plans for each of the
    testsTest Plans will be sent out for review
    soon, but this review is intended to finalize the
    structure and major segments of the tests
  • Where we are going
  • After this review, we will be holding only
    detailed reviews to cover specific topics
  • In particular
  • There will likely be individual table-top reviews
    of the Test Plans as they are sent out for
    release
  • CDRs will be held prior to sending the large
    pieces of MGSE
  • Pathfinder review will be held before we start
    the pathfinder program for data systems or
    mechanical operations
  • TRR will be held after the pathfinder program is
    complete and procedures updatedthis may be part
    of the LAT pre-ship review, focusing on plans,
    procedures, and logistics, and demonstrating that
    we are ready to receive the LAT at NRL
  • Individual TRRs for each testfocusing on the
    specifics for each test, and a more technical
    discipline review of the test program

3
Environmental Test Sequence
  • LAT-MD-00408, the LAT Instrument Performance
    Verification Plan delineates the basic content
    and order of all required LAT environmental tests
  • This responds to the requirements put forth in
    the MAR, GEVS, IRD, and other governing documents
  • LAT-MD-02717, the LAT Environmental Test
    Sequence details the order of environmental
    tests, and the major operational steps
  • This is subservient to the LAT-MD-00408, but
    includes significantly more operational detail
  • This bridges the logistics gap between the
    MD-00408 and the Test Plans, much as
    LAT-MD-006786, the LAT Integration Sequence
    provides direction for LAT integration
  • LAT-MD-00408 needs to be updated to reflect the
    final sequence agreed on by all test directors
    and subject-matter leads. Below is the updated
    sequence that will be baselined

Sine Vibe
EMI/EMC
Reconfig. LAT
Acoustic
Receive, Unpack
Mount Radiators
Perform Reference CPT (at SLAC)
C
L
L
L
L
L
L
L
4X
T-Cycle
T-Bal
Remove Radiators
Weight, CG
Ship to Spectrum
Pack LAT
C
S
C
S
L
C
C
S
Final CPT
Updated LAT Environmental Test Sequence
4
Test Sequence Walk-Through
  • Reference CPT
  • Perform Reference CPT at SLAC prior to shipping
  • Receiving and Prep
  • Unpack LAT leave on pallet base (A-59 high bay)
  • Run CPT establish instrument health prior to
    start of env testing (LAT clean tent)
  • Sine Vibe Test
  • Move to vibe test lab
  • Run LPT on vibe table expander head, prior to
    start of test
  • Perform Z-axis vibe
  • Run LPT on vibe table expander head, prior to
    Z-axis tear-down
  • Move LAT to slip table and perform X-axis vibe
  • Run LPT on slip table, prior to X-axis
    tear-down
  • Re-orient LAT on slip table and perform Y-axis
    vibe
  • Run LPT on slip table, prior to removing LAT
  • Move LAT back to A-59 high bay clean tent
  • Re-configure LAT
  • Hoist LAT onto Test Stand (A-59 high bay)
  • EMI/EMC Test
  • Move to anechoic chamber

5
Test Sequence Walk-Through (cont. 1)
  • Install Radiators
  • Integrate Radiators (A-59 high bay)
  • Run Radiator CPT after both Radiators are
    installed (LAT clean tent)
  • Run LAT LPT (LAT clean tent)
  • Acoustic Test
  • Move to acoustic test cell
  • Run LPT in acoustic test cell, prior to test
  • Perform Acoustic test
  • Run LPT in acoustic chamber, prior to removing
    LAT
  • Move LAT back to A-59 high bay
  • Re-orient LAT (A-59 high bay)
  • Mount extension beams to Test Stand
  • Rotate LAT 90 degrees using two-hook lift and
    spreader bars
  • Prep for Thermal-Vacuum Test (A-59 high bay)
  • Pick up LAT and set on T-Vac cart
  • Move LAT to T-Vac chamber and prep for test
  • Roll LAT into chamber
  • Run CPT in T-Vac chamber, prior to door closing
  • Run SVAC test in T-Vac chamber, prior to door
    closing

6
Test Sequence Walk-Through (cont. 2)
  • Thermal-Vacuum Test (T-Vac chamber)
  • Pump down
  • Bake out
  • Hot survival run Initialization, Aliveness, and
    CPT tests
  • Thermal-balance hot run LPT, SVAC, TCS Perf
    tests
  • Thermal-balance cold run LPT, SVAC, TCS Perf
    tests
  • Cold survival run Initialization, Aliveness,
    and CPT tests
  • Thermal cycle hot (2) run LPT
  • Thermal cycle cold (2) run LPT
  • Thermal cycle hot (3) run LPT
  • Thermal cycle cold (3) run LPT
  • Thermal cycle hot (4) run CPT
  • Thermal cycle cold (4) run CPT
  • Return to ambient temperature
  • Vent chamber
  • Run final LAT CPT in T-Vac chamber after
    venting and opening doors
  • Run SVAC in T-Vac chamber after venting and
    opening door
  • Break configuration and return LAT to A-59 high
    bay

7
Test Sequence Walk-Through (cont. 3)
  • Remove Radiators (A-59 high bay)
  • Mount extension beams to Test Stand
  • Rotate LAT 90 degrees back to vertical using
    two-hook lift and spreader bars
  • Remove and pack Radiators
  • Weight and C.G. Measurement (A-59 high bay)
  • Hoist LAT off Test Stand onto CG Plate
  • Measure LAT weight and center of gravity
  • Hoist LAT off CG Plate and onto pallet base
  • Move into clean tent
  • Pre-Ship Review
  • Pack LAT and Ship
  • Prep and seal Transport Container
  • Ship to Spectrum
Write a Comment
User Comments (0)
About PowerShow.com