Title: CITY OF BALITMORE DEPARTMENT OF PUBLIC WORKS BACK RIVER WWTP
1CITY OF BALITMOREDEPARTMENT OF PUBLIC WORKSBACK
RIVER WWTP
- ENERGY INITIATIVES AND
- INNOVATIVE PRACTICES
-
Sheila Dixon, Mayor David E. Scott,
Director Nicholas H. Frankos, Plant Manager
2Presentation Outline
- Plant Overview
- Water Reuse
- Potable Water Conservation
- Electrical Distribution Upgrades
- Performance Based Energy Contract
- BGE Load Response Program
- On-Site Bleach Generation
- Future Energy Considerations
3Back River WWTP
- Built in 1907 on 466-acre tract located in
eastern Baltimore County - Design flow 180 MGD
- Average flow 140 MGD
- 140 sq. mile service area/1.3 million customers
- Two outfalls-Back River and Sparrows Point
- Annual O M budget - 50 million
- 300 employees
- Removal Efficiencies FY-08
- BOD 99, SS 99, TP 94, TN 68
4PLANT AERIAL VIEW
5BACK RIVER FACILITIES
6Water Reuse Overview
- Sparrows Point approached City to use Back River
effluent for process water at steel plant. - In 1941 Back River and Sparrows Point Steel Plant
entered into a Water Reuse Agreement. - SP currently takes approximately 40 MGD of Back
Rivers final effluent. - SP reimburses the City for electrical, chlorine
and water costs 950,000 per year. - Current steel plant owner is Severstal
7BS Sparrows Point PlantBackground
- Built in 1887 on 3500 acre tract of land with
frontage on the Patapsco River - Location selected so ships could off-load raw
materials and transport finished product - Produced steel plates, strip steel, sheet steel,
and tin plate - Plant has downsized since its heyday in the
1950s when it employed over 30,000 people
8Water Reuse Agreement - History
- Bethlehem Steel needed larger supply of water
than available from ordinary sources - Original Agreement executed in 1941
- Bethlehem Steel constructed 4.5 mile 60 pipeline
to convey water - Max rate of 50 MGD
- 1947 amended to 100 MGD max
9Water Reuse Agreement - History
- 1951 amended to 100 MGD min 200 max
- - built additional 96 pipeline
- - built treatment facilities at Back River to
further treat effluent - Mid-1980s abandoned treatment facilities.
- Flow gradually has been reduced over time to the
current level of 40 45 MGD - Agreement can be cancelled by either party with a
two year notification.
10LIFT PUMPS
11High Head Lake
12Effluent Water Uses at BS
- Currently takes 40 MGD of Back River final
effluent for process water - Used in various steel production processes
- Cooling and cleaning of hot gas streams
- After use the water is treated at their
Humphreys Creek Facility prior to discharge into
the Chesapeake Bay
13(No Transcript)
14(No Transcript)
15(No Transcript)
162008 Annual Water Reuse Costs Paid to City by
Sparrows Point
Bleach 724,155 Power
190,945 Water 24,500 949,600/
Year Based on 44 MGD 2600/day
17Waste Pickle Liquor Agreement
- 1979 initial agreement Bethlehem Steels waste
product used for P removal at Back River - 40,000 gal/day
- City constructed loading, storage and dosing
facilities at Back River - Trucking costs were split
- 1982 amended City pays 2/3 trucking and
Bethlehem Steel 1/3
18Waste Pickle Liquor Agreement
- 1986 amended City pays 100 trucking
- December 2000 changed from ferrous sulfate to
ferrous chloride - Ferrous chloride a preferred product due to
decreased acidy and higher iron content - Reduced quantity to less than 10,000 gallons/day
- Current average usage is 8,000 gallons/day
19(No Transcript)
20(No Transcript)
21POTABLE WATER CONSEVATION
- Plant has converted pump seal water systems and
polymer mixing systems from potable water to
plant flushing water - Saves over 100,000 gpd of potable water
- Potable water still used as backup source
- Saves over 36.5 million gallons of potable water
per year - Annual savings of over 50,000
22Seal Water System
23Poly-Blend System
24ELECTRICAL DISTRIBUTION UPGRADES
- SC- 9555 Electrical Distribution Upgrade
- 4,000,000 capital cost
- Installed four new 34.5 kV capacitor banks to
maintain power factor between 0.9 and 0.98 - Upgraded the 13.2 and 2.4 kV feeders to 34.5kV
- Standardize entire plant distribution system to
34.5kV - SC- 835 Blower House 2 Controls System
Improvement - 1,800,000 capital cost
- Replaced across the line starters with soft
starts - Replaced blower and guide vane controls
- These projects improved energy efficiency and
increased system reliability
25ENERGY PERFORMANCE CONTRACTING
- Mechanism to implement necessary infrastructure
improvements that reduce energy consumption and
operating costs. - Financed through operating budget utility
savings. - No impact to capital funding program.
- Performance and savings guaranteed.
26ENERGY PERFORMANCE CONTRACTING PROCESS
- Preliminary Feasibility Study
- Share information and identify potential savings
- Phase 1 Agreement
- Lists ECMs and potential savings
- Develops costs for Phase 1 Proposal
- Phase 1 Proposal
- Completes detailed energy audit, project scope,
savings and final proposal - Phase 2 Agreement
- Complete design followed by construction
- After construction, measurement and verification
data collected and reconciled annually
27PROJECT RESULTS
- Project Cost 14.1 Million
- 1.8 Million in Annual Energy and Operational
savings in first year - Sustainable and reliable solution
- Funded through savings in operating budget
- Increased equipment redundancy and reliability
- Demonstrates BRWWTPs commitment to energy
conservation
28ENERGY CONSERVATION MEASURES (ECM)
- ECM 1 - Digester Gas Utilization
- ECM 2 - Digester Recirculation Pump
Improvements - ECM 3 - HVAC Improvements
- ECM 4 - Direct Digital Ventilation Controls
- ECM 5 - Lighting Improvements
- ECM 6 - Water Conservation
29ECM 1 DIGESTER GAS UTILIZATION
- Digester Gas Conditioning
- Two new gas conditioning skids for cleaning,
- drying and siloxane removal
- Engine Generators
- Three 1 MW Waukesha Enginators designed for
landfill and digester gas - Recovery Steam Generators (HRSGs)
- Capture waste heat from engine exhaust to produce
low pressure steam
30ECM 1 DIGESTER GAS UTILIZATION
- Plant biogas needs will be met first and all
excess biogas will be used by generators. - Generators sized to handle annual average of 1.1
million cubic feet of gas per day. - Electricity generated must be used on-site and
cant be fed back to grid (Interconnect
Agreement) - Cogen Facility will be operated and maintained
by JCI under a Maintenance Agreement
31ECM 1 DIGESTER GAS UTILIZATION
- Financial and Operational Benefits
- Clean gas will be available throughout site.
- Improved reliability of HVAC and process boilers
due to clean gas. - Convert wasted flared biogas to electricity.
- Heat recovery/steam generation results in more
digester gas available to engines. - Sustainable and reliable solution.
- Produces 20 of Plants electrical requirements
32(No Transcript)
33(No Transcript)
34ECM 2 DIGESTER RECIRCULATION PUMP
- ESD Recirculation Pump Improvement
- Replace one vortex pump in each digester
- Replace with a Hidrostal pump
- Energy consumption reduced by 55 HP
35ECM 3 HVAC IMPROVEMENTS
- 320 ton York absorption chiller boiler unit
- 125 gallon domestic water heater
- Split system heat pump with programmable
thermostat - 2 cast iron sectional hot water boilers
- Benefits
- More efficient use of digester gas
- Increased equipment service life
- Reduced maintenance and improved redundancy
36ECM 4 DIRECT DIGITAL CONTROL/VENTILATION
OPTIMIZATION
- Direct Digital Control
- Metasys energy management system (EMS)
- Lab exhaust fan monitoring and control
- Ventilation Optimization
- Establish schedule and ventilation rates for fan
systems - Optimize return and outside air ratios
- Electric Unit Heaters
- New non-adjustable fixed range thermostats
37ECM 5 LIGHTING IMPROVEMENTS
- Energy efficient electronic ballast
- Occupancy sensors for low use areas.
- Re-lamping/ re-ballast existing fixtures with 28W
T8 lamps and magnetic ballasts. - Replace metal halide high pressure sodium
fixtures with energy efficient high output T5
fixtures. - LED exit signs.
38ECM 6 WATER CONSERVATION
- Installation of the following water conservation
devices - Replace 3.5 gpf toilets with 1.6 gpf low flush
toilets and flush valves - Replace 4 gpm shower heads with 2.5 gpm reduced
flow shower heads - 0.5 gpm aerators on restroom sinks
- Water less urinals in Administration Bld.
39SUMMARY OF ANNUAL SAVINGS (Year 1)
- ECM 1 Digester Gas Utilization 1,630,000
- ECM 2 ESD Recirculation Pump 15,145
- ECM 3 HVAC Improvements 32,250
- ECM 4 Digital HVAC Control
46,500 - ECM 5 Lighting Improvements
81,350 - ECM 6 Water Conservation 1,050
- TOTAL 1,806,000
40BGEs RIDER 24 LOADRESPONSE PROGRAM
- Customers that can reduce electric loads during
peak demands receive credits on bill for
enrolling - Credits based on amount of load reduction
- 1,000 kw load reduction worth 70,000/yr
- Customers can participate by either shutting down
equipment or running generators - Maximum load response is 10 times per year for up
to 6 hours. (Monday-Friday) - Average number of activations over past 6 years
was1.6 requests per year
41WWFD ENROLLMENT
- Location Capacity (kw) Annual Credit ()
- Back River 2,000 144,682
- Patapsco 1,366 98,329
- Eastern Ave PS 433 31,869
- Jones Falls PS 250 18,400
- Dundalk PS 115 8,454
- TOTAL SAVINGS 301,734
42ONSITE BLEACH GENERATION
- Construction of bleach/chlorine gas generation
facility of maximum 15,000 /day equivalent
chlorine. - Hybrid system which produces chlorine gas for
immediate use, 12 bleach and excess caustic
soda. - Estimated project cost 18.5 million
- Excess caustic use in scrubbers and future ENR
- Project payback less than 6 years
- Estimated production cost for chlorine 0.40
vs. bulk delivery cost of 0.97.
43FUTURE ENERGY CONSIDERATIONS
- Solar Power
- Hydrogen Gas Utilization from OSBG
- Digestion Process Enhancements
- Possible 4th Enginator
- Biodiesel production from scum and grease
44QUESTIONS?
45(No Transcript)