Title: A Seminar On Validation of Heating, Ventilation and Air conditioning System
1A Seminar OnValidation of Heating, Ventilation
and Air conditioning System
Department of Quality Assurance Maliba Pharmacy
College
2Content
- Introduction
- Validation of HVAC
- HVAC Qualification
- Validation master plan
- Design Qualification(DQ)
- Installation Qualification(IQ)
- Operational Qualification(OQ)
- Performance Qualification(PQ)
- Validation parameter
- References
3Introduction
- Heating Ventilation and Air Conditioning
- system(HVAC)
- HVAC systems can have an impact on product
quality - It can provide comfortable conditions for
operators - The impact on premises and prevention of
contamination and cross-contamination to be
considered at the design stage - Temperature, relative humidity control where
appropriate - Supplement to basic GMP
4What is contamination?
- It is "the undesired introduction of
impurities (chemical/ microbial/ foreign matter)
into or on to starting material or intermediate
during sampling, production, packaging or
repackaging. - Contaminants are -
- Products or substances other than the product
being manufactured - Foreign matter
- Particulate matter
- Micro-organisms
- Endotoxins (degraded micro-organisms)
5What is cross-contamination?
- Contamination of a starting material,
intermediate product, or finished product with
another starting material or product during
production. - Cross-contamination originates from-
- Poorly designed air handling systems and dust
extraction systems - Poorly operated and maintained air handling
systems and dust extraction systems - Inadequate procedures for personnel and equipment
- Insufficiently cleaned equipment
6Cross-contamination can be minimized by
- Personnel procedures
- Adequate premises
- Use of closed production systems
- Adequate, validated cleaning procedures
- Appropriate levels of protection of product
- Correct air pressure cascade
7HVACsystem consists of-
- Air conditioner
- AHUs
- Dehumidifier / Heater
- Filters (Pre HEPA)
- Dust Extractors
- Ducting (For delivery of controlled air)
- Supply Fans
- Smoke Detector
- Dampers
- Humidity / Temperature / Pressure sensors
- Bag Filters
- Heating / Cooling Coils
8 Area 1
HVAC
Area 2
I M P U R E A I R
Impure air
Pure air
Area 3
Area 4
10 Return Air
Exhaust air
9HVAC
Exhaust Air Grille
Heater
Secondary Filter
Recirculated air
10Validation of HVAC systems
- It includes-
-
- Commissioning
- Qualification
- Maintenance
11Commissioning -
- Precursor to qualification
- Includes setting up, balancing, adjustment and
testing of entire HVAC system to ensure it meets
requirements in URS. - Acceptable tolerances for parameters
- Training of personnel
12Conti
- Records and data maintained include-
- Installation records documented evidence of
measure capacities of the system - Data design and measurement for, e.g. air flow,
system pressures - OM manuals, schematic drawings, protocols,
reports
13Qualification
- To ensure that equipment is designed as per
requirement, installed properly. - Action of proving that any equipment works
correctly and leads to the expected results.
14HVAC Qualification
- Validation Master Plan
- QUALIFICATION
- User Requirement Specification
- Design Qualification
- Installation Qualification
- Operation Qualification
- Performance Qualification
- Re- Qualification.
15Conti
- Manufacturers should qualify HVAC systems using a
risk-based approach. - The qualification of the HVAC system should be
described in a validation master plan (VMP). - The validation master plan should define the
nature and extent of testing and the test
procedures and protocols to be followed. - A change control procedure should be followed
16Conti
- Risk analysis to determine critical and
non-critical parameters, components, subsystems
and controls - Critical parameters should be included
- Non-critical systems and components are subjected
to Good Engineering Practices (GEP) - Acceptance criteria and limits defined in design
stage - Design conditions, normal operating ranges,
operating ranges, alert and action limits
17Validation master plan
- This document should contain
- Validation policy
- Organizational structure of validation activities
- Summary of facilities, systems, equipment and
processes to be validated - Documentation format to be used for protocols
and reports - Planning and scheduling
- Change control
- References to documents
18Qualification
- Typical parameters to be included in
qualification - Temperature
- Relative humidity
- Supply, return and exhaust air quantities
- Room air change rates
- Room pressures (pressure differentials)
- Room clean-up rate
- Particulate matter, microbial matter (viable and
non-viable) - HEPA filter penetration test
19Conduct of test
- Time intervals and procedure to be defined by the
manufacturer - Influenced by the type of facility and level of
protection - Requalification, and change control Tests
performed according to protocols and procedures
for the tests - Results recorded and presented in report
20Schedule of tests to demonstrate continuing
compliance
Test procedure and key aspects Maximum time interval Objective Test Parameter
Particle count test Readings and positions 6 months or 12 months depending on Class Verifies cleanliness Particle count
Measure pressure difference 12 months Absence of cross-contamination Air pressure difference
Measure supply and return air, calculate air change rate 12 months Verify air change rates Airflow volume
Velocity measurement 12 months Verify unidirectional airflow and or containment condition Airflow velocity
21Design Qualification(DQ)
- First step in the qualification of new HVAC
systems. - It documents the design of the system and will
include - 1. Functional Specification.
- 2. Technical / Performance specification for
equipment. - 3. Detailed Air Flow Schematics.
- 4. Detailed layout drawing of the system.
- Compliance with GMPs and other regulatory
requirements.
22Conti
- Ensures that design -
- 1. Meets the user requirements.
- 2. Details facility airflow and pressure cascade
philosophy. - 3. Takes into account process and personnel flow
(cross- contamination issues) - 4. Details materials of construction.
- 5. Details safety requirements.
- 6. Full details of the intended construction
prior to implementation. - 7. Details all equipment that must be ordered.
23Installation Qualification(IQ)
- IQ Should include-
- Instrumentation checked against current
engineering drawings and specifications - Properly served by the required utilities
- Verification of materials of construction
- Installation of equipment and with piping
- Calibration of measuring instruments
- Operation manuals and spare parts lists to assure
the proper and continuous operation of the system - Components are installed at specified location
24Conti.
- IQ Document should contain-
- Instrument name, model, I.D. No., Personnel
responsible for activities and Date. - A fully verified installation that complies with
the documented design. (all deviations will have
been recorded and assessed.) - All equipment documentation and maintenance
- requirements would be documented.
- Completed calibration of measuring instruments.
25Conti.
- Calibration verification
- To provide a list of critical instrumentation
and control panel and to document that they have
been identified and calibrated in accordance with
the approved procedure - SOP verification
- To verify that required SOPs exist in either
draft or final form and must be current and
approved for use. - Utilities Connection Verification
- Utilities supported to HVAC need to be
verified to assure that they are installed
properly. -
26Conti.
- Change Parts and Replacement Parts Verification
- Maintenance Procedures Verification
- Critical Systems Change Request Procedure
verification - Lubricants Verification
27Operation Qualification
- The purpose of OQ is to establish, through
documented testing, that all critical components
are capable of operating within established
limits and tolerances. - The purpose of OQ is to verify and document that
an HVAC system provides acceptable operational
control under at-rest conditions. - Scope of OQ is to test the individual components
of the system such as AHU, blowers and others.
28Conti
- Operation Qualification Checks -
- Ability to provide air of sufficient quality and
quantity to ensure achievement of specified clean
room conditions. - Ability to maintain temperature, relative
humidity and pressure set points. - Ability to maintain any critical parameters
stated in the DQ consistently.
29Conti.
- Includes the tests that have been developed from
knowledge of processes, systems and equipment. - Tests to include a condition or a set of
conditions encompassing upper and lower operating
limits, sometimes referred to as worst case
conditions.
30OQ also includes-
- Testing Equipment Calibration Verification
- Instrumentation Calibration verification
- SOP Verification
- Operation Qualification tests
-
31Conti
- OQ protocols to be written and approved prior to
completion. It includes following - All relevant SOPs should be in place
- Temperature measurement report
- Humidity measurement report
- Differential pressure measurement report
- Air flow direction measurement report
- Room particle count measurement report
- All maintenance/ cleaning instructions available
- All O M staff to be trained to use and maintain
the system. - Sign off. (Compliance Certificate by Engineering
Dept QA)
32Performance Qualification
- The purpose of PQ is to verify and document that
an HVAC system provides acceptable control under
Full Operational conditions. - PQ should follow successful completion of IQ and
OQ. - PQ verifies that the critical parameters, as
defined in the DQ are being achieved.
33Conti
- PQ Should include -
- Test to include a condition or set of conditions
encompassing upper and lower operating limits. - Tests should be conducted under in use,
condition either or simulated as close as
possible to the actual process
34Conti
- PQ is used to demonstrate consistent achievement
of critical parameters over time. ( under
manufacturing conditions) - PQ and OQ tests are sometimes performed in
conjunction with one another. - Any changes to the HVAC system should be
revalidated before proceeding to the PQ phase.
35Validation Parameters
- Air flow measurement
- Room air changes per hour.
- Filter Integrity Testing (HEPA Leak test)
- Pressure Differentials
- Particulate count measurement
- Recovery test
- Temperature and Relative Humidity
- Air Flow Pattern
- Microbial Count
36Conti
- A. PHYSICAL TESTS
- A1. NON-VIABLE PARTICLE COUNTS
- Equipment
- Optical Particle Counter (Discrete Particle
Counter) - Air sample is drawn into the instrument passed
through light scattering device. The signal that
this generates is electronically processed to
display particle counts at different size ranges. - Sample Volume
- 1 cubic ft
- Sample Time
- 1 Min
37Conti
- Frequency
-
- GMP compliance- Quarterly
- Sch M - 6 Monthly
- Acceptance criteria
- 1. Critical environments The particle
concentration under the dynamic condition should
not more than 100 particle of 0.5µm and larger
per cubic meter (for class 100 area)
38Conti
- A2. PRESSURE DIFFERENTIALS
- Introduction
- Correct degree of overpressure can be maintained
relative to the adjacent areas of lower
classification to ensure that air moves from
clean areas to less clean areas. - Equipment
- Electronic manometer (portable and easy to use),
- Incline manometer
39Conti
- Sample location
- Between adjacent areas connected either by a door
or grille. - Frequency of sampling
- Continuously by gauges / manometer recorded
daily.
40Conti
- Acceptance Criteria
- gt 10 Pa between classified area adjacent area
of lower classification - gt 15 Pa between classified area unclassified
area - Action
- HEPA filter blockage
- Increase fan speed
- Increase air flow to specific area by altering
dampers
41Conti
- A3. AIRFLOW VELOCITY
- Equipment - Anemometer
- Reading should be taken 10cm from the surface of
filter. - Record velocity reading from all the four corners
and the Centre of the filter surface. - Repeat twice at each location
- For Grade A laminar flow workstations, the air
flow rates shall be 0.3 meter per second 20
(for vertical flows) and 0.45 20 (for
Horizontal flows) - No value may deviate from the mean by more than
20
42Conti
- Air velocity exceeding the stated value may cause
excessive air movement affect work zone
protection. - Air velocity below the limit may be insufficient
to maintain critical work zone protection. - Deviation indicates the blockade of filter
- Solution Alteration of fan speed or HEPA
filter replacement
43Conti
- A4. HEPA filter integrity test (DOP test)
- Purpose
- To confirm that no damage to filter, seals and
no leakage of particles. - Equipment
- 1. Aerosol generator
- 2. Photometer
- Scan at 1 inch from filter surface.
- Make separate passes at peripheries.
44Conti
- Acceptance criteria
- An unacceptable leak is defined as a penetration
of 0.03 or more of particle, 0.3µm and
larger than the reference calibration curve for
99.97 efficient filter -
45Conti
- A5. Temperature and Relative Humidity
- Use a sling psycrometer to measure the dry bulb
and wet bulb temperature of the air. - Check the wick of the sling psycrometer, it
should be always in wet conditions in order to
record correct wet bulb temperature. - Sling the psycrometer in air for about a minutes
time and record the dry bulb and wet bulb
temperature. - Check the wet bulb depression i.e. difference
between dry bulb and wet bulb temperature.
46Conti
- Acceptance criteria
- Temperature NMT 27 degree centigrade
- Humidity NMT 55
- Frequency Daily
47Conti
- A6.Air change rate
- Measurement of the air supply volume and
determination of the air change rate (ACR) is a
measure of the frequency of air turnover in the
clean room. - This gives some idea as to how quickly
contamination may be removed from the clean room
provided there is acceptable mixing of air in the
room. - The ACR can be determined by measuring the mean
air velocity at the supply HEPAs or grilles and
calculating the air change rate based on the mean
air supply volume.
48Conti
- Equipment Anemometer
- Sample locations
- At least four positions are tested
across the filter or grille face to obtain
the mean supply air velocity. - Frequency of sampling
- Sch M - 6 Monthly
- GMP compliance Quarterly
49Conti
- A7. MICROBIOLOGICAL TESTS
- Solid growth media (e.g. settle and contact
plates) Soybean Casein Digest Agar medium can be
used for both Bacteria Fungi tested. - The recommended size of solid media is 90 mm in
diameter (for settle plates) - 55 mm for contact plates.
50Conti
- Sampling condition
- Sampling in the at rest condition may be
continued at an agreed frequency to monitor
baseline contamination levels - The operational conditions and the activities
being performed at the time of testing should be
recorded - Incubation condition
- Incubation of samples, inverted, at 20 25o C
for at least 5 days is suitable for the growth of
mould and fungi. - Incubation of samples, inverted, at 30 - 350C for
at least 2 days is suitable for the growth of
bacteria.
51Conti
- Acceptance criteria for Airborne Bioburden test
- Critical Environment no more than 1
CFU/m3, or 0.03 CFU/ft3(USP
monograph) - Acceptance criteria for Surface Bioburden test
- Critical Environment no more than 1
CFU/12.9cm2, or 2 in2 (FDA Aseptic
Processing Guidelines) -
52References
- Supplementary guidelines on good manufacturing
practices for HVAC systems for
non-sterile pharmaceutical dosage forms. (WHO
Technical Report- Series, No. 937), Annex
2.(2006) - Validation of pharmaceutical process, sterile
product - 2ndEdition, edited by Fredrick J. Carleton,
James P. Agalloco, page no.240-256.
53Thank you