Openreach makes every effort to ensure the information in this report is accurate at the time of com - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Openreach makes every effort to ensure the information in this report is accurate at the time of com

Description:

Jumper Recovery Order not available, however demand is expected to be low ... Approximately 10k assets were Flexi Ceased with jumpers left in ... – PowerPoint PPT presentation

Number of Views:240
Avg rating:3.0/5.0
Slides: 14
Provided by: rossdi
Category:

less

Transcript and Presenter's Notes

Title: Openreach makes every effort to ensure the information in this report is accurate at the time of com


1
Flexi Cease - Update Service Forum 9th
September 2008 Trevor Benjamin Openreach LLU
Product Development
Openreach makes every effort to ensure the
information in this report is accurate at the
time of compilation, however, Openreach does not
represent that it is complete and Communications
Providers should check with Openreach for the
latest available information. Openreach reserves
the right to modify delivery criteria and
delivery dates.
2
Agenda
  • Proxy CP Testing
  • Launch Decision
  • Launch Timescales
  • Premature Flexi Cease / Charging
  • Tie Pair Utilisation Report

3
Proxy CP Testing
  • SMPF
  • BD756629 Warning Message 1884,5,6 holding back
    11 Test Cases
  • BD790081 JRO holding back 3 Test Cases
  • MPF
  • Pending on Bridge case BD745839 clean retest

4
Proxy CP Testing Summary
  • SMPF
  • Good overall progress with successful end to end
    tests completed
  • Flexi Cease SMPF KCI2 Warning Message 1884,5,6
    no being sent, fix in MR906
  • Jumper Recovery Order not progressed end to end,
    cause and fix being progressed.
  • MPF
  • Flexi Cease MPF order not progressed end to end
  • Jumper Recovery Order not progressed end to end

5
Launch Decision
  • SMPF
  • The majority of CP functionality exists and is
    tested ok. Two testing issues remain-
  • KCI warning messages codes fixed in mr906 (18th
    September) and no charging until 22nd September
  • Jumper Recovery Order not available, however
    demand is expected to be low initially until LIJ
    system size grows, also the functionality is
    achieved via a provide order which will trigger
    removal of LIJ.
  • Launched on 8th September and resolve remaining
    issues.
  • Commence charging 22nd September as previously
    notified.

6
Launch Decision
  • MPF
  • This functionality has not been satisfactorily
    tested. With several problems identified-
  • Flexi Cease order not progresses end to end
  • Jumper Recovery Order not available end to end
  • Do Not Launch on 8th September.
  • Resolve remaining issues as soon as possible and
    launch.

7
Flexi Cease SMPF
Not available on SMPF at launch
Available from 18th September but no charges
until 22nd
8
Launch Timeline (revised)
2008
Nov
Mar
April
May
June
July
Aug
Sep
Oct
R1000
R800
R900
S/MPF
Deploy SMPF 8th September
Test
Develop
SMPF
Deploy SMP JRO TBC
Jumper Recover Order
Test
Deploy MPF TBC
MPF
Develop
Test
Today
9
SMPF Premature Flexi Cease / Charging
  • Two problems have cause the early introduction of
    Flexi Cease principals and associated charges for
    SMPF
  • Synchronised Cease cease of NB service triggers
    BB Cease
  • Planned to be switched on post Flexi Cease
  • Deployed prior to Flexi Cease but was
    unfortunately switched on in error
  • Resulted in 500 circuits, spread across most CPs,
    tagged as LIJs
  • Switched on 3rd July and off on 16th August 2008
  • Will cause charges to be raised against CP when
    ties are reused
  • Flexi Cease FLOW exclusion table
  • Inclusion in FLOW table switches Flexi Cease off
    Proxy CP excluded to enable testing
  • One CP had details entered incorrectly, resulted
    in Flexi Cease being switched on.
  • Switched on 26th April and corrected on 22nd
    August
  • Approximately 10k assets were Flexi Ceased with
    jumpers left in
  • Will cause charges to be raised against CP when
    ties are reused
  • For both of these the introduction of R900 has
    now started the billing for the removal of Left
    In Jumpers. Openreach did not expect to encounter
    LIJs prior to launch.

10
SMPF Premature Flexi Cease / Charging
  • For both of these problems Openreach will take a
    snapshot of LIJ inventory at 8.00am on 8th
    September and share the individual lists with
    each CP.
  • On each monthly billing run Openreach will check
    the charges for LIJ removal and will credit CPs
    for charges for LIJs that are raised from this
    inventory.
  • Openreach will also update the inventory monthly
    to reflect additional activity that could have
    changed the tie pair status
  • After 6 months Openreach will review the
    position.

11
Tip Pair Utilisation Report
  • The Tie Pair Utilisation Report allows CPs to
    interrogate their inventory and run reports on
    their Tie Pairs.
  • Allowing identification of a given tie pair
    status as either in use, spare or faulty.
    Also with the introduction of Flex Cease LIJ
    (left in Jumper).
  • For MPF circuits this TPUR since Release 900 now
    excluded all MPF assets with an active open
    order. These re-appear on order closure.

12
Questions?
13
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com