Title: U.S. ATLAS Physics and Computing Project Status
1U.S. ATLAS Physics and Computing Project Status
- John Huth
- Harvard University
2Outline
- Project Management Plan
- Organization
- Scope
- Facilities
- Software
- Milestones
- Budget
3U.S. ATLAS Organization
4Projectization
- Access/MS Project Database
- Reporting/tracking function
- Reporting Scheme
- Formal reports quarterly
- Written reports monthly
- PCWS, PCWP, ACWP tracking (same as construction
project) - Inputs from all Level 2 managers
5PMP Overview
- Description of ATLAS
- CSG etc
- Description of U.S. Organization
- Job descriptions
- Policies
- Reporting and oversight
- Working appendices
- Budget
- WBS
- Deliverable list
- Major Milestones
6Functional Overview Cost/Schedule Control System
Baseline
Report Generator
ACCESS Database
- WBS
- WBS Dictionary
- Estimate
- - Labor
- - Material
- - Travel
- Rates
- Contingency
- Cost Books
- MOUs
- Project/NSF/Base/
- Infrastructure
- Funding Source
Reports
1
2
3
Projections Procedure
Terminal
FY Funding by Institution
4
5
6
7
Update Procedure
MS Project 98 Baseline (Resource Loaded Schedules)
Schedules
8
9
Escalation Procedure
DOE
MS Project 98 Statused (Resource Loaded Schedules)
Escalation Rates
11
BCWS/BCWP
Status Data
S/S Mgr.
10
Status Sheets
CSSR at WBS Level 3 WBS Level 5
Cost Reporting (WBS Level 5)
12
13
14
Institutions
Monthly Cost Reports
Cumulative Cost
16
15
17
18
7Cost Categories
- Advanced Information Technology Professional
- Information Technology Professional I
- Information Technology Professional II
- Information Technology Technician
- Student
- Travel
- Stores
- Space
- Power
- Low value materials
- High value materials
- Licenses
- Maintenance
- Consulting
- Technical services
- Administrative service
8Change Control
9Project Office
- Information in ACCESS DB
- Tracking functions automated
- Use of project office for procurements
- Major procurements
- 10 Mock Data Challenge (03)
- 40 Facilities ramp (end of 04)
- 100 Facilities ramp (05)
10Coordination with Intl. ATLAS
- Common WBS, schedule
- Working to same milestones
- Trying to ramp up presence at CERN
- Multiple Tutorials given on control/framework
- Software Agreements in progress
(control/framework is prototype agreement)
11Contingency
- Major issue
- Funding profiles very tight
- Uncertainties large for a fixed set of
deliverables - Factors of 2 or more in some cases
- Adopt this model
- Build to cost drop requirements as needed to
meet deliverables - Add 10 project reserve to help put deal with
crises year by year allocation - Agreement with CMS
12Major U.S. Project Components
- Regional Center at Brookhaven
- User support facility
- Software
- Core software
- Control/framework
- Data management
- Detector Specific reconstruction
- Support, training
- Physics
- Event generators, physics objects
- Computational grids
- Tier 2 facilities
13Regional Center
- Goals
- Support U.S. Physicists in analysis
- Support ATLAS Collaboration
- Hub of U.S. ATLAS Grid
- Status
- Support hires
- Center running, providing support
- Planning for ATLAS, Grid activities
- Acquisition of more Linux boxes
- Support for CPU intensive jobs
- Shielding calculations
- Trigger studies
14Muon Level 2 Trigger
Radius of curvature map for muons.
15Neutron Background Studies
Total neutron flux
KHz/cm2
16(No Transcript)
17Software
- U.S. Responsibilities
- Control/framework
- Data management
- Major detector reconstruction
- Liquid Argon Calorimeter
- Tile Calorimeter
- Muons
- Status
- Major milestones passed in creation of
control/framework - 7 FTE software professionals working
- Preparation for software agreements with ATLAS
18Grid Computing
- Petabyte scale virtual data grid
- Hierarchy of centers (Tier 0 CERN, Tier 1 BNL,
Tier 2 Universities) - Grid middleware linkages
- Resource allocation and discovery
- Security
- Automation
- Status
- U.S. ATLAS testbed planning
- Participation in GriPhyN, PPDG projects
19U.S. ATLAS Testbed
Boston University
Esnet, Mren
UC Berkeley LBNL-NERSC
NPACI, Abilene
Argonne National Laboratory
Calren Esnet, Abilene, Nton
Brookhaven National Laboratory
Esnet
Abilene
Indiana University
HPSS sites
20GriPhyN
21Challenges in Project Planning
- Projectizing
- Accounting and tracking systems (DONE)
- Revision to Project Management Plan (DONE)
- Preparations for Lehman review (NOW)
- Integration with International ATLAS
- Need more support functions at CERN (In Progress)
- LHC Computing review (in progress)
- Concerns about CERN IT division
- Coping with funding profiles (5M short integral)
- Poor match particularly in software
- Seeking relief in FY 02-04
22Major Milestones
23Milestones
24(No Transcript)
25(No Transcript)
26Request
27Software
28Facility Profile
29Guidance - Request
30Profile Effects
- Substantial delay in services at Regional Center
- Mass Storage System support delayed until FY 04.
- Impacts ability to perform 03 Mock data
challenge - Software development cant work with this profile
- Need flatter profile (FY 02-04)
- Still, integral eliminates all detector specific
tasks (mainly impacts universities)
31Fallbacks
- Overall scale back on requirements
- Software
- Degree of grid automation
- Overall requirements
- (e.g. carrying two vs. one DB product)
- Shifting personnel
- (e.g. CERN location of SW pros)
- Hardware
- Reduction of scope of RC
- Delay of purchases Moores law
- Alternative data-analysis strategies
- Comment user part of facilities is conservative
-
32Overall Budget
33Budget Breakout
34Summary
- Functional Organization
- Software effort backbone of Intl. ATLAS
- International ATLAS starting to coalesce
- Grid tasks beginning
- Funding profile must be addressed
- PMP (minus WBS, budget) available for comment
- Steps to projectization