http://nodal.ercot.com 1 - PowerPoint PPT Presentation

Loading...

PPT – http://nodal.ercot.com 1 PowerPoint presentation | free to download - id: 816d83-MDBkO



Loading


The Adobe Flash plugin is needed to view this content

Get the plugin now

View by Category
About This Presentation
Title:

http://nodal.ercot.com 1

Description:

Market Readiness Seminar 6 Remaining Market Trials and Cutover Activities Sept 01, 2010 http://nodal.ercot.com * – PowerPoint PPT presentation

Number of Views:181
Avg rating:3.0/5.0
Slides: 72
Provided by: erc138
Learn more at: http://www.ercot.com
Category:

less

Write a Comment
User Comments (0)
Transcript and Presenter's Notes

Title: http://nodal.ercot.com 1


1
Market Readiness Seminar 6
  • Remaining Market Trials and Cutover Activities

Sept 01, 2010
2
Antitrust Admonition
ANTITRUST ADMONITION ERCOT strictly
prohibits Market Participants and their employees
who are participating in ERCOT activities from
using their participation in ERCOT activities as
a forum for engaging in practices or
communications that violate the antitrust laws.
The ERCOT Board has approved guidelines for
members of ERCOT Committees, Subcommittees and
Working Groups to be reviewed and followed by
each Market Participant attending ERCOT meetings.
If you have not received a copy of these
Guidelines, copies are available at the Client
Relations desk. Please remember your ongoing
obligation to comply with all applicable laws,
including the antitrust laws. DISCLAIMER All
presentations and materials submitted by Market
Participants or any other Entity to ERCOT staff
for this meeting are received and posted with the
acknowledgement that the information will be
considered public in accordance with the ERCOT
Websites Content Management Operating Procedure.
3
Agenda
  • Review of Phase 5 Activities
  • 168-Hour Test Breakdown of Activities
  • 168-Hour Measurements
  • Objective / Participation Requirements
  • Entry / Exit Criteria
  • Evaluation Criteria
  • Preparation Activities
  • Completed Full System Market and Reliability
    Tests
  • Completed Outage Scheduling Verification and
    Synchronization
  • Completed CRR September Auction
  • Network Model Load
  • Data Used for 168-Hour Test
  • Nodal Production Environment
  • 168-Hour Test Execution
  • Schedule
  • Communications Plan
  • Post 168-Hour Testing Activities

4
Review of Phase 5 Activities
5
Review of Phase 5 Activities Market Trials 2010
Roadmap
6
168-Hour Test Measurements
7
168-Hour Test Breakdown of Activities Objective
/ Participation Requirements
  • Objective
  • Conduct a full rehearsal of the Nodal Day-Ahead
    Market (DAM), Reliability Unit Commitment (RUC),
    Real Time Market and Load Frequency Control (LFC)
  • Continuous seven day period of Market Systems and
    48 hours of Closed Loop LFC
  • Components required and to be exercised during
    the 168-Hour test
  • The Day Ahead functions including DAM, DRUC, HRUC
    and WRUC
  • The Real Time systems performing SCADA, Network
    Security Analysis, Transmission Constraint
    Management, SCED, and LFC
  • The Nodal support systems including Network Model
    Management, Outage Scheduler, Outage Evaluation
    tools
  • Credit Monitoring and Management (CMM)
  • Settlements and Billing
  • Posting of applicable Reports and Extracts
  • Participation Requirements
  • The value of the 168-Hour Test is dependent on
    participation by the Market.
  • The 168-Hour Test is required by all registered
    Market Participants intending to be involved in
    the Nodal Market
  • Participation data and metrics will be published
    and made readily available to the ERCOT Board,
    Independent Market Monitor and the related Market
    Participant Forums (NATF, TAC)
  • Metrics will also include comparisons of Zonal
    Resource Plans to Nodal COPs.
  • Participation should be reasonably reflective of
    post Go-Live behavior
  •  

8
168-Hour Test Breakdown of Activities Entry /
Exit Criteria
  • Entry Criteria for the 168-Hour test will be as
    follows
  • All defined Market Trials Testing up until the
    168-Hr test has been completed in accordance with
    the Market Trials Handbooks published to the
    Nodal Readiness Center
  • ERCOT declares readiness for initiating the
    168-Hour test to TAC and the Board and obtains
    director level sign off from ERCOT management.
  • Exit Criteria
  • 168 hours of continuous Nodal systems testing
    have been completed without encountering any
    major system issues that would prevent the Nodal
    Market from going live while maintaining system
    security and reliability as required by the ERCOT
    Protocols, Operating Guides, other binding
    documents, and NERC Reliability Standards.
  • ERCOT provides a test summary report to TAC and
    the Board outlining the successful testing
    processes.

9
168-Hour Test Breakdown of Activities Evaluation
Criteria
  • Evaluation Criteria was agreed on in coordination
    with the Market at the NATF and TAC forums
  • Evaluation Criteria will be reviewed holistically
    in that no one issue from this list will
    necessarily constitute a failure of the test
  • Evaluation Criteria is included in the Appendix
    of this presentation and in the 168-Hour Handbook

10
168-Hour Test Breakdown of Activities
Preparation Activities
  • Full System Market and Reliability Tests
  • The following tests have been completed prior to
    the start of the 168-Hour tests
  • 2-Hour Test Completed May 20, 2010
  • 8-Hour Test Completed June 17, 2010
  • 5-Hour Test Completed July 21, 2010
  • 24-Hour Test 1 Completed August 5, 2010
  • 24-Hour Test 2 Completed August 20, 2010
  • 40-Hour Test Completed August 28, 2010
  • Total Full System Tests completed prior to the
    168-Hour Tests 103
  • Outage Scheduling Transition Plan
  • 08/16/2010 ERCOT released the Outage Scheduler
    to be synchronized and verified by TSPs and QSEs
    for outages effective for the month of September
  • 08/30/2010 TSP and QSE deadline to complete
    synchronization and verification
  • Market Participants that have not yet completed
    this should
  • Continue work on this activity
  • If there are questions or issues, contact ERCOT
    at martkettrials_at_ercot.com
  • Congestion Revenue Rights Auction
  • 08/27/2010 ERCOT posted the Auction Results for
    the September Monthly Auction

11
168-Hour Test Breakdown of Activities
Preparation Activities
  • Network Model Load
  • 09/01/2010 Network model to be used during the
    168-Hour test loaded to the Nodal Production
    Environment
  • Going forward the network model loads will
    generally follow the Zonal schedule
  • Data from Market Trials Phase 5 to be used in the
    168-Hour test
  • To the extent necessary to support settlement and
    credit operations, ERCOT will use estimated
    and/or settled data from Operating Days in July
    and August from MT5 as well as the CRR inventory
    from the September CRR auction (see above) during
    the 168-hour test.

12
Nodal Production Environment
13
Nodal Production Environment
  • During the 168-Hour Test, applicable Nodal
    systems will be managed as if the systems were
    fully in production 7x24, exercising the same
    procedures used for Zonal production operations
  • Change Controls during and leading up to the test
    shall adhere to a similar SLA as Zonal Production
  • If an outage is required, a Market Notice will be
    issued and determination will be made if this
    will require a restart of the 168-Hour test

14
168-Hour Execution
15
168-Hour Execution Schedule
  • September 8, 2010 - 168-Hour Test begins
  • Day ahead Market will run for Operating Day
    September 9, 2010 using the DAM ACL sent from CMM
  • DRUC and WRUC will run per protocol timelines
    starting the first day of the test
  • ERCOT will begin running hourly HRUC at 1800 when
    the Adjustment Period opens.
  • All Real Time telemetry, and Market Submission
    shall continue to be submitted by the Market
  • All postings delivered in previous Market Trials
    Phases delivered per Nodal Protocol timelines
  • Initial DAM / RTM statements posted per the Nodal
    settlements calendar
  • Production level support, including those systems
    that are supported 24x7, goes into effect for the
    duration of the 168-Hour Test
  • For the duration of the test, DAM, RUC,
    Settlements and Credit processes will run per
    Nodal Protocol guidelines in an open loop format.
    Zonal will continue to commit units using the
    RPRS processes and actual, binding settlements
    will execute per Zonal Protocols.
  • September 12 September 14, 2010 Full System
    Market and Reliability Test During the 168-Hour
    Test
  • September 12, 2010 at 200 PM, all generation
    will begin transitioning to Nodal control
    estimated to be completed by 300 PM
  • The ERCOT grid will run under Nodal Control
    through September 14, amounting to a total of 48
    Hours of Full System Market and Reliability
    Testing during the 168-Hour Test
  • Day Ahead Market, RUC processes and SASM will
    continue to be executed per Nodal Protocols.
  • Zonal will continue to commit units using the
    RPRS and OOMC processes and actual, binding
    settlements will execute per Zonal Protocols.
  • September 14, 2010 all generation will transition
    back to Zonal starting at 100 PM, estimated to
    be completed by 200 PM
  • September 14, 2010 September 15, 2010
  • ERCOT will continue to run the remaining
    operating days of the 168-Hour test, executing
    DAM, RUC, settlements and credit processes

16
168-Hour Execution Communications Plan
  • ERCOT will host a daily WebEx / Conference call
  • This will occur at 10am each day of the 168-Hour
    Test
  • Details will be posted to the ERCOT calendar at
    http//www.ercot.com/committees/nodal/mt/
  • ERCOT will maintain a list of known issues to
    updated each day on these conference calls
  • This will be posted to the ERCOT Readiness Center
    on a daily basis
  • Additionally, this will also be posted to the
    ERCOT calendar instance for that day.
  • Issues Raised by the Market
  • Market Participants will continue to utilize the
    markettrials_at_ercot.com email address outside of
    the daily conference calls
  • Full System Market and Reliability Test
  • ERCOT will maintain a separate WebEx conference
    during the 48-Hour test
  • 9/12/2010 1200 PM 1200 AM
  • 9/13/2010 600 AM 1200 AM
  • 9/14/2010 600 AM 230 PM
  • Details for this WebEx will be sent out by Friday
    09/03/2010

17
Post 168HR Activities
18
Post 168-Hour Activities
  • September Congestion Revenue Rights Allocation
    and Monthly Auction for October
  • September RTM Telemetry and Market submissions
  • September Day Ahead Market
  • September Settlements and Credit
  • September Report Delivery and MIS availability
  • Full System Market and Reliability tests after
    the 168-Hour test.
  • September 28, 2010 36 hours in duration
  • October 27, 2010 24 hours in duration
  • Details on these will be communicated in a Friday
    Real Time Market Call as well as if additional
    test are scheduled

19
168HR Supporting Materials
20
Evaluation Criteria
  • Validate ERCOT and Market Participants have the
    proper resources and expertise to manage a Nodal
    system for 7 days. This will be measured by the
    successful adherence to internal ERCOT procedures
    during the 168-Hour test to be validated by the
    ERCOT Training Department during the test and
    evidenced to the market within a report. Market
    Participants Nodal Accountable Executive will
    self attest to their criterion.
  • Credit monitor credit exposures, create credit
    reports and accurately reflect each market
    participants credit position based on their
    activity during the 168-Hour test.
  • Validate data model accuracy between all systems
    including integration of the upstream NMMS system
    with downstream systems (e.g. DAM, MMS, EMS and
    CRR). This will be measured by existing ERCOT
    procedures. All issues observed regarding
    inaccurate modeling during the 168-Hour test will
    be reported on by ERCOT to the ERCOT Board,
    Independent Market Monitor, and the related
    Market Participant forums (NATF and TAC) as to
    the problem found, root cause of the error in the
    first place, and what process changes are being
    implemented to ensure that similar model accuracy
    issues do not reoccur going forward. ERCOT shall
    attest to the data model accuracy in and between
    all systems as a result of TSP and Resource
    Entity data passing the ERCOT validation rules.
  • Execute DAM, DRUC, HRUC and WRUC for 7 days
    within timelines set by Nodal Protocols. If any
    activities fall outside of expected timelines,
    procedures for handling such incident must be
    executed by ERCOT personnel in adherence with
    Nodal Protocols and internal ERCOT procedures.
  • Verify RT Operators can maintain system frequency
    to scheduled frequency, maintain ancillary
    obligations and resolve constraints during the
    period in which ERCOT will be performing Full
    System Market and Reliability tests during the
    168-Hour Test.

21
Evaluation Criteria
  • Validate ERCOT can effectively and accurately
    manage all constraints in both DAM and RT (i.e.
    not constrain on invalid contingencies or
    inaccurate line ratings) and system will utilize
    full list of competitive constraints.
  • Validate that ERCOT can execute and manage all
    SPS, RAPs, PCAPs, MPs, and TOAPs to control
    congestion in the DAM, DRUC, HRUC, and RT as
    appropriate.
  • Validate that ERCOT is accurately reflecting all
    congestion mitigation measures (SPS, RAPs) in
    DAM.
  • The rolling CPS1 one minute average score must
    equal or exceed 100 during the Full System
    Market and Reliability test period. The target
    minimum is 125.
  • Note that the CPS1 average will not take into
    account the two one-hour periods when ERCOT is
    transitioning to Nodal and then back to Zonal and
    any periods in which ERCOT must deploy RRS in
    response to system contingencies.
  • Zonal Commercially Significant Constraints (CSCs)
    and Closely Related Elements (CREs). managed
    below thermal limits.
  • Local Congestion managed below thermal limits.
  • Stability limits managed below transfer limits.
  • No NERC Disturbance Control Standard (DCS)
    failure if applicable.
  • No LFC-SCED system issues that result in
    termination of the test.

22
Cut-Over Milestones
2/10/2017
23
Nodal Cutover and Market Transition Key
Cut-Over Milestones
Key Cut-Over Milestones Key Cut-Over Milestones
Network Model Nodal Protocol Section 3.10 goes into effect (Sept. 1) TAC Approval July 1 (July 20) Board Approval July 20 Market Notice July 30
Congestion Revenue Rights Nodal Protocol Section 7 goes into effect (Oct. 13) TAC Approval August 5 Board Approval August 17 Market Notice September 13
Outage Scheduler Nodal Protocol Section 3.1 goes into effect (Nov. 1) TAC Approval August 5 Board Approval August 17 Market Notice October 1
Full Nodal Operations Nodal Protocol Sections 3, 4, 5 and 6 go into effect as well as all other unimplemented Protocol Sections (Nov. 23) TAC Approval October 7th Board Approval October 19th Market Notice October 23rd
24
Key Cutover Activities Thru December 2010
2/10/2017
25
Cut-Over Timeline Thru December 2010
26
Cut-Over Monthly Outlook August
  • Key Cut-Over Activities for August 2010
  • (08/01) Model Begin network modeling
    timelines-Complete
  • (08/13) OS Outage Scheduler Zonal to Nodal
    Import process run
  • (08/13) CRR Last day to register for CRR
    December monthly auction
  • (08/16) OS ERCOT releases Outage Scheduler to
    Market
  • (08/16-09/17) OS Market Participants
    synchronize / verify outages in the Nodal Outage
    Scheduler to the Zonal Outage Scheduler for
    Outages effective during and after December 2010
  • Network Model
  • Outage Scheduler
  • Congestion Revenue Rights

Functional Area
Functional Area
  • Task Plan
  • Data Prep
  • Decommission/Retirement Template
  • Contingency/Back-out Template
  • Entities Involved
  • ERCOT
  • TSP
  • REs
  • CRRAH
  • QSE
  • Impacts
  • TSPs/REs submit Transmission and Resource data
    for December model (05_Nodal_Load_transition_1_0.d
    oc posted on 06/01 NATF Materials)
  • Resource outages will NOT be imported during
    Zonal to Nodal import into Outage Scheduler
  • CRRAH must register by deadline to be eligible to
    participate in the December Auction (Protocol
    16.8.2)
  • TSPs/QSEs can begin entering outages in Outage
    Scheduler via Web Service or UI
  • TSPs/QSEs are responsible for verifying outages
    imported to Nodal Systems and correcting any
    missed outages or incorrect outages by 09/17/2010

27
Cut-Over Monthly Outlook September
Functional Area
  • Key Cut-Over Activities for September 2010
  • (09/01) Model Network Model Go-Live
  • (09/01) Model Deadline to submit Model changes
    for Month of December
  • (09/02) Model Begin interim update process
  • (09/01) CRR ERCOT publishes CRR Activity
    Calendar to MIS
  • (09/08) CRR Deadline for PCRR NOIE Contract
    Eligibility
  • (09/17-12/01) OS Outages are synched. Market
    Participants maintain outages in both the Zonal
    and Nodal Outage Scheduler for outages effective
    December and beyond.
  • Network Model
  • Outage Scheduler
  • Congestion Revenue Rights
  • Entities Involved
  • ERCOT
  • TSP
  • REs
  • CRRAH
  • QSE
  • Impacts
  • TSPs / REs that submit Model changes to ERCOT by
    09/01 will be applied prior to Go-Live
  • From 09/02 forward until Go-Live any Model
    changes submitted to ERCOT for application prior
    to Go-Live will leverage the interim update
    process.  
  • MPs can retrieve the CRR Activity Calendar from
    MIS public with a valid Digital Certificate

28
Cut-Over Monthly Outlook October
  • Key Cut-Over Activities for October 2010
  • (10/01) CRR CRR system data clean up for
    Go-Live
  • (10/01) Credit ERCOT assesses each CPs credit
    worthiness for the Dec CRR Auction
  • (10/02) OS First pull of December Outages for
    CRR Network Model (for PCRR Allocation)
  • (10/02) Model Network Model built for CRR
    Allocation and Auction
  • (10/03-10/11) MIS UI and EWS Get Report function
    not available (ERCOT back end reconfiguration)
  • (10/13) OS  Changes to December Outages
    considered for CRR Auction Model
  • (10/13) Model  Changes to Model considered for
    CRR December Auction
  • Functional Area
  • Network Model
  • Outage Scheduler
  • Congestion Revenue Rights
  • Credit
  • MIS
  • Impacts
  • MIS UI and EWS Get Report unavailable from
    10/03-10/11 for production reconfiguration
  • MPs able to start retrieving Go-Live postings on
    MIS. Refer to EMIL for dates per posting.

29
Cut-Over Monthly Outlook October
  • Key Cut-Over Activities for October 2010
  • (10/14-10/19) CRR ERCOT begins accepting PCRR
    Nominations for December Monthly Auction
    (updated)
  • (10/15-11/15) Model Network Operations Model
    posted to TSP Citrix location and TSPs begin
    validation process
  • (10/26) CRR ERCOT shall allocate PCRRs to NOIEs
    for the 2010 December Monthly Auction and publish
    to MIS
  • (10/26) CRR ERCOT shall post CRR Network Model
    for the 2010 December Monthly Auction to MIS
  • (10/28-11/08) Credit ERCOT posts ACLs daily for
    CRR December monthly auction to CRR
  • (10/29) CRR ERCOT to post December 2010 Monthly
    Auction Notice to MIS
  • Functional Area
  • Network Model
  • Outage Scheduler
  • Congestion Revenue Rights
  • Credit
  • MIS
  • Impacts
  • CRRAH able to retrieve ACLs from CRR system each
    business day.
  • MPs can post additional collateral until
    11/08/2010 for Dec 2010 CRR Auction
  • Dec 2010 CRR Model available on MIS
  • Dec 2010 Monthly Auction Notice available on MIS

30
Cut-Over Monthly Outlook October MIS UI and
EWS Get Report Reconfiguration Details
  • MIS UI and EWS Get Report Reconfiguration
    Details (10/03/2010 10/11/2010)
  • Market Participants will not have access to the
    MIS UI and EWS Get Reports functionality.
  • Market Participants will need to use the direct
    links (listed on next slide) or Citrix to access
    system applications.
  • All other EWS will be left on and from 10/1 up
    until the First Run Date as defined in EMIL of
    the CDR report, the EWS will return no reports
    found during that time.
  • MIS UI and EWS Get Report Go-Live (10/12/2010)
  • Postings will be made available based on the
    EMIL posting date going forward.
  • Postings live prior to 10/12/2010 will continue
    to be made available at this time.
  • Market Participants will only have access to
    go-live posting data. Data from Market Trials
    activities is no longer available for download.

31
Cut-Over Monthly Outlook October MIS UI and
EWS Get Report Reconfiguration Details
  • URLs to be used during cutover activities
  • Network Model via Citrix
  • https//gateway.ercot.com/vpn/index.html
  • Market Manager User Interface
  • https//mis.ercot.com/mmsui/mmsui/displayTradesLan
    ding.action
  • Outage Scheduler Application
  • https//mis.ercot.com/osrui/osrui/Summary.action
  • CRR Application (MUI)
  • https//mis.ercot.com/crr/mui/ListAllUserMessage.d
    o - direct link for CRRAHs
  • https//mis.ercot.com/crr/mui/editSMPCreditLimit.d
    o - direct link for CPs
  • Web Services Endpoint URL
  • https//misapi.ercot.com/2007-08/Nodal/eEDS/EWS

32
Cut-Over Monthly Outlook November
  • Key Cut-Over Activities for November 2010
  • (11/8/2010 1200pm) Credit Collateral Posting
    Deadline (Dec Auction)
  • (11/8/2010 500pm) CRR Credit Lock for Dec CRR
    Auction
  • (11/9/2010 11/11/2010) CRR December CRR
    Auction Bid Open/Close
  • (11/12/2010) CRR December CRR Auction Executes
  • (11/15/2010) CRR December CRR Auction Results
    published
  • (11/16/2010) Settlements December CRR Auction
    Invoice published
  • (11/16/2010) Disputes Dispute submitted to
    ERCOT for CRR Invoice
  • (11/19/2010) Credit Payment Due for December
    CRR Auction Invoices
  • (11/22/2010) Settlements Payments to CRRAH
    (Dec Auction)
  • (11/23/2010) Credit ERCOT to Release ACL (TPE
    and ACL Reports Available on MIS)
  • (11/23/2010) Market Submission Opens (Remaining
    Protocol Go-Live)
  • (11/24/2010) Model Network Model Load
  • (11/29/2010) Credit ERCOT to Publish ACL for
    the initial Day-Ahead Market execution by ERCOT
  • Functional Area
  • Settlements
  • Credit
  • Congestion Revenue Rights
  • Disputes
  • Market Management
  • Impacts
  • Available Credit Limit is locked for CRRAHs
  • CRRAHs can submit disputes against CRR Auction
    Invoice via the API or MIS
  • CRRAHs can receive postings on MIS
  • QSEs can begin DAM Bid submission (15 submission
    items)
  • Market checkpoint calls begin to facilitate
    issues and readiness
  • LFC testing in November will not include
    Settlements
  • Daily Market Conference Bridge starts 11/23

33
Cut-Over Monthly Outlook Go-Live Sequence of
Events
  • 11/30/2010 Go-Live Sequencing

Time Action Comments
up to 1000 Bids and Offer submission  QSE submit bids and offers
1000 Close DAM  
1000 Execute Dam Clearing Process  
1330 Approve DAM results Day Ahead results will be posted to MIS
1400 LFC Cutover Generation control moves to Nodal systems
1330-1430 Submit Post DAM COP and offers  QSE submit Post Dam COPs and Offers
1430 Close for RUC  
1430 Begin Execution of DRUC  
1600 Approve DRUC Results  
1600 Post DRUC Results  
1800 HRUC executions Hourly HRUC runs hourly thru 235959 of Operating Day
34
Cut-Over Monthly Outlook December
  • Key Cut-Over Activities for December 2010
  • (12/01/10) Nodal Program Nodal Go-Live
    (Operating Day 1)
  • (12/3/2010) Settlements Nodal Day Ahead Market
    Statement Invoice Available
  • (12/3/2010) Disputes Disputes submitted to
    ERCOT for DAM Invoice
  • (12/8/2010) Credit Nodal Payment Due for
    OD12/01/2010
  • (12/9/2010) Credit Nodal Payout for
    OD12/01/2010
  • (12/15/2010) Model Network Model Load
  • (12/13/2010) Settlements Nodal Real-Time
    Statement Available
  • (12/16/2010) Settlements Nodal Real-Time
    Invoice Available
  • (12/27/2010) Credit Nodal Payment Due for
    Real-Time Invoice 12/16/10
  • (12/28/2010) Credit Nodal Payout for Real-Time
    Invoice 12/16/10
  • Functional Area
  • Network Model
  • Settlements
  • Congestion Revenue Rights
  • Credit
  • Market Management System
  • Impacts
  • Daily Market Calls continue for issue
    facilitation
  • MPs receive 1st Nodal Invoice for DAM and RTM via
    MIS
  • MPs can submit Disputes via MIS or API

35
Nodal Cutover and Market Transition Reversion
Plan
  • Reversion Plan Approach
  • 12/01/2010 12/02/2010 Zonal and Nodal systems
    continue to process in parallel. This allows for
    48hrs of stabilization (2 Operating Days) with
    parallel processing similar to the level of
    effort being performed with the LFC Testing
  • 12/03/2010 12/31/2010 Zonal systems Retire
    where processing is disabled, but remain in place
    in the event they are needed to be reinstated
    quickly.
  • 01/01/2011 Zonal System Decommissioning begins

36
Nodal Cutover Nodal System Readiness Criteria
  • Nodal System Readiness Update

37
Nodal Cutover Communications Zonal Protocol
21.12.3
  • 21.12.3 Notice to Market Participants of
    Effective Date for Nodal Protocol Provisions and
    Retirement of Zonal Protocol Provision
  • No part of the nodal market design may start
    operation until all the Market Readiness Criteria
    for that part of the nodal market design have
    been met. Certification that all Market
    Readiness Criteria have been met must be made at
    least by each of the following the Technical
    Advisory Committee (TAC), ERCOT and the ERCOT
    Board. Upon such certification, ERCOT shall
    issue two Notices alerting Market Participants to
    the effective date of Nodal Protocol sections and
    the retirement of Zonal Protocol sections, as
    applicable. ERCOT shall issue the first Notice
    no less than thirty (30) days prior to the
    effective date or retirement date, as applicable,
    and the second Notice no less than ten (10) days
    prior to the effective date or retirement date,
    as applicable. The Notice shall include
  • (1) The Nodal Protocol Sections to become
    effective and
  • (2) The Zonal Protocol Sections to be retired, if
    any

38
Nodal Program Communications
Readiness Signoff Schedule Readiness Signoff Schedule Readiness Signoff Schedule
Network Operations Modeling 06/30 07/01 07/20 07/30 09/01 ERCOT Management Readiness Signoff TAC Approval Board of Directors Approval 30 Day Market Notice sent Nodal Protocol Section 3.10 goes into effect
Congestion Revenue Rights 08/04 08/05 08/17 09/13 10/13 ERCOT Management Readiness Signoff TAC Approval Board of Directors Approval 30 Day Market Notice sent Nodal Protocol Section 7 goes into effect
Outage Scheduling 08/04 08/05 08/17 10/01 11/01 ERCOT Management Readiness Signoff TAC Approval Board of Directors Approval 30 Day Market Notice sent Nodal Protocol Section 7 goes into effect
Full Nodal Operations 10/01 10/07 10/19 10/23 11/23 ERCOT Management Readiness Signoff TAC Approval Board of Directors Approval 30 Day Market Notice sent Nodal Protocol Sections 3,4,5,6 go into effect as well as all other unimplemented Protocol Sections
39
Readiness Methodology
  • ERCOT will measure readiness by the following
    categories
  • System Readiness an evaluation of a particular
    system needed to support identified market
    activities
  • Process Readiness an evaluation of the
    Processes and Procedures necessary to support
    identified market activities
  • People Readiness an evaluation of ERCOT and
    Market Participant capabilities to support
    identified market activities
  • ERCOT plans to review the Market Readiness
    Criteria at NATF and subsequently request a vote
    from TAC per Section 21.12.3, Notice to Market
    Participants of Effective Date for Nodal Protocol
    Provisions and Retirement of Zonal Protocol
    Provision

40
Readiness Methodology
  • System Readiness evaluation of the Nodal system
    to support the market design
  • Core system functionality delivered
  • Protocol required system functionality available
    for market testing
  • System Integration delivered
  • System to system integration delivered to support
    Market Timeline and Business Processes
  • Known defects resolution plan
  • All Must fix prior to go-live defects have a
    resolution plan in place
  • Active Readiness Metrics
  • Current status of Readiness Metrics

41
Readiness Methodology
  • Process Readiness evaluation of the Processes
    and Procedures necessary to support the market
    design
  • Procedures complete
  • ERT project procedures to support business
    processes complete
  • System cutover transition plan established
  • ERCOT and Market Participant business activities
    required for transitioning into Go-Live have been
    established and communicated.
  • Market rules transition communicated
  • Nodal and Zonal Protocol effective / retirement
    dates identified and communicated for Market
    Participant review

42
Readiness Methodology
  • People Readiness evaluation of ERCOT employee
    readiness and Market Participant knowledge to
    support the market design
  • ERCOT staff supporting Market Trials
  • ERCOT Business teams supporting system execution,
    problem resolution, and Market questions
  • ERCOT staff trained on System and Processes
  • ERCOT Business teams training status based on
    identified ERT training metrics
  • Market Participant Training delivered
  • ERT external training classes and web based
    training provided by the Nodal training project

43
NMMS Overview
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • Stability issue resolved as of July 1 (ERCOT
    continues to monitor production)
  • Navigation performance issues improved Aug 1st
    (43 reduction in response time measured)
  • Validation performance improvement patch was
    added on Friday, August 27th (expected a 20-40
    reduction in validation time). Improvement on
    validation times were tested as follows
  • Average 45.18
  • Median 66.41
  • Max 97.46

Open Defects
Deferred Defects
0
Sev 1
!
11
Deferred
!
0
Sev 2
!
0
Sev 3-5
44
Network Operations Modeling Go Live
System Readiness Planned Completion Status
SEM Go-Live 8/31/09 Complete
TSP Model Validation (Metric MP14C) 4/30/10 Complete
Model Change Request Tools Support Market Updates Ongoing Green
Regular Model Loads into Market Trials Systems Ongoing Green
8 Hour LFC Test Executed w/ Network Model from NMMS 6/17/10 Complete
Process Readiness Process Readiness Process Readiness
Network Operations Change Request Timeline Transition Plan established 6/03/10 Complete
Network Modeling Procedures Ready 8/01/10 Complete
Market Rules Protocol Transition Plan for September 7/23/10 Complete
Status updated post ERCOT, TAC, BOD approval in
RED
45
Network Operations Modeling Go Live
People Readiness Planned Completion Status
ERCOT Staff Support of Market Trials 9/30/2010 Green
ERCOT Staff Trained on System and Processes 6/22/10 Complete
Market Participant Training Delivered 7/29/09 Complete
Readiness Review and Approval Readiness Review and Approval Readiness Review and Approval
NATF Review 6/23/10 7/08/10 Complete
ERCOT Management Approval 6/30/10 Complete
TAC Approval 7/20/10 Complete
BOD Approval 7/20/10 Complete
30 Day Market Notice 7/30/10 Complete
10 Day Market Notice 8/20/10 Complete
Status updated post ERCOT, TAC, BOD approval in
RED
46
OS Overview
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • No defects reported in the Outage Scheduler
  • Outage Scheduler transition tasks were completed
    on 8/13 and the system was ready for dual entry
    and validation on 8/16
  • Market Notice for dual entry and validation was
    sent on August 16th
  • All Outage scheduler issues within the TSP Issues
    list have either been addressed or are resolved

Open Defects
Deferred Defects
0
Sev 1
!
119
Deferred
!
0
Sev 2
0
!
Sev 3-5
47
Outage Scheduling Go Live
System Readiness Planned Completion Status
Outage Scheduler released to Market Trials 2/01/10 Complete
Outages Scheduler Integrated with DAM, RUC 4/15/10 Complete
Outage Scheduler Qualification Connectivity Qualification (MP20) 4/01/10 Green
Process Readiness Process Readiness Process Readiness
Verify Outage Evaluation System Functionality (EMO3 1) 6/23/10 Complete
Outage Coordination Procedures 7/16/10 Complete
Nodal Protocol Transition Plan Updated for Outage Scheduling 7/29/10 Complete
Outage Scheduling Transition Plan Established 7/08/10 Complete
48
Outage Scheduling Go Live
People Readiness Planned Completion Status
ERCOT Staff Support of Market Trials Ongoing Green
ERCOT Staff Trained on System and Processes 09/03/10 Green
Market Participant Training Delivered 7/15/10 NMMS/OS work-shop added
Overall Readiness Overall Readiness Overall Readiness
NATF Review 7/08/10, 07/29/10 Complete
ERCOT Management Signoff 8/04/10 Complete
TAC Approval 8/05/10 Complete
BOD Approval 8/17/10 Complete
30 Day Market Notice 10/01/10
10 Day Market Notice 10/21/10
49
CRR Overview
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • Working with Siemens on automated processor fix.
    Expectation is to receive fix before Go-Live
  • Incorrect Loadzone Designation from Topology
    Processor Output file
  • Resource Nodes missing from Settlement Point
    output file produced by Topology Processor
  • Topology Processor cannot consume outages
    information for CRR modeling
  • CRR MUI requires a system reboot for Bid Limit
    to take effect (internal to ERCOT) workaround is
    nuisance -targeting 09/13/2010 resolution

Open Defects
Deferred Defects
0
Sev 1
!
4
Deferred
!
0
Sev 2
!
4
Sev 3-5
50
CRR Allocation and Auction Readiness Update
System Readiness Planned Completion Status
CRR System released to Market Trials 2/01/10 Complete
CRR Integrated in Market Trials 5/01/10 Complete
CRR Account Holder Connectivity Qualification MP 15 (B) 9/17/10 Red
Operation of CRR Auctions and Allocations (CRR3) 8/17/2010 Complete
Verify CRR Auction Invoices (CO8) 8/17/2010 Complete
Process Readiness Process Readiness Process Readiness
CRR Procedures 6/25/10 Complete
Nodal Protocol Transition Plan Updated for CRR 7/29/10 Complete
TCR to CRR Transition Plan (CRR4) 9/29/09 Complete
Red due to MPs registering but not working to
get qualified. (inflated denominator)
51
CRR Allocation and Auction Go Live
People Readiness Planned Completion Status
ERCOT Staff Support of Market Trials Ongoing In Progress
ERCOT Staff Trained on System and Processes 06/25/10 Complete
Market Participant Training Delivered 07/15/09 Complete
Overall Readiness Overall Readiness Overall Readiness
ERCOT Management Signoff 08/04/10 Complete
NATF Review 07/08/10, 07/29/10 08/03/10 Complete
TAC Approval 08/05/10 Complete
BOD Approval 08/17/10 Complete
30 Day Market Notice 09/13/10
10 Day Market Notice 10/03/10
52
MMS Day Ahead, Adjustment Period, RT Market
Overview
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • MMS currently has 58 Open defects in Test
    targeted to be fixed by September 3.
  • 21 DAM
  • 2 AS Mgr
  • 1 CIM, 1 SASM, 1 CCT, 1 Validation Rules
  • 9 Background Processing
  • 3 SCED
  • 6 RUC
  • 13 Market Infrastructure including 6 GUI
  • MMS currently has 24 Open defects in development
    targeted to be fixed by October 1.
  • 6 DAM, 4 RUC, 4 SCED, 3 MI, 7 GUI
  • MMS remaining 13 (7 performance, 3 MOI, 3 MI)
    defects are being reviewed by business for final
    disposition.

Open Defects
Deferred Defects
0
Sev 1
!
44
Deferred
!
43
Sev 2
!
52
Sev 3-5
53
MMS Day Ahead, Adjustment Period, RT Market
Readiness Update
System Readiness Planned Completion Status
MMS System release to Market Trials 2/01/10 Complete
Market Submission Connectivity Qualification (MP3) Ongoing Green
Real-Time Market Daily Participation (MP15A) Ongoing Green
Generate LMPs for 6 months (MO5) Ongoing Green
Verify SCED Price Validation (MO4) Ongoing Green
DAM Participation (MP16) Ongoing Amber
Generate Day-Ahead LMPs (MO9) Ongoing Green
Verify DAM Price Validation (MO8) Ongoing Green
DRUC Execution (MO10) Ongoing Green
Verify Supplemental Ancillary Services Market (MO3) Ongoing Green
Process Readiness Process Readiness Process Readiness
Day Ahead, Adjustment Period and RTM Procedures 8/31/10 Complete
MMS Day Ahead Real Time Price Validation Procedures 8/31/10 Complete
Nodal Protocol Transition Plan Updated for DAM, RUC, SASM, SCED
People Readiness People Readiness People Readiness
ERCOT Staff Support of Market Trials 09/30/2010 In Process
ERCOT Staff Trained on System and Processes 8/27/10 Complete
Market Participant Training Delivered Ongoing In Process
54
EMS Real-Time Operations
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • EMS currently has 20 Open defects in development
    targeted to be fixed by October 1.
  • 1 EMS Interface, 1 CIM Importer, 1 PSSE export
  • 6 STNET/SMTNET/OE
  • 1 VSAT
  • 3 RLC
  • 1 SE
  • 2 TCM
  • 3 LFC/Generation

Open Defects
Deferred Defects
0
Sev 1
!
321
Deferred
!
12
Sev 2
!
8
Sev 3-5
55
EMS Real-Time Operations Readiness Update
System Readiness Planned Completion Status
EMS System Release to Market Trials 2/1/10 Complete
Verify ACE Performance (EMO5) 4/21/2008 Complete
Individual LFC Testing (EMO6) 5/31/2010 Green
Telemetry / ICCP System Failover (N2) Ongoing Green
Telemetry Compliance (MP6) 6/2/2010 Complete
Validate Telemetry / SE ISM / Data Accuracy (E3) Planned Planned
State Estimator Standards Performance (EMO9) Ongoing Green
RTCA Zonal to Nodal Modeling Differences (EMO9) Ongoing Amber
RTCA CSC Zonal to Nodal Comparison (EMO9) Ongoing Green
Verify Voltage Support Functionality (EM02) 9/8/2010 Planned
Anomalous/Auto-Disabled Telemeted Points (EMO10) Ongoing Green
Verify Load Forecast Accuracy (EMO7) Planned Planned
Process Readiness Process Readiness Process Readiness
RT Operations Business Procedures 8/31/10 Complete
Nodal Protocol Transition Plan Updated for RT Operations 7/29/10 Complete
People Readiness People Readiness People Readiness
ERCOT Staff Support of Market Trials 9/30/10 In Process
ERCOT Staff Trained on System and Processes 9/3/10 In Process
Market Participant Training Delivered Ongoing In Process
56
COMS Settlement Billing, Metering, and Data
Aggregation - Overview
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • There are only 5 Open defects related to Core
    Systems at this time that are scheduled to be
    resolved by 09/03/2010.
  • -Adjustment to queries in Appworx Scheduling Job
  • -IDR Staging Performance Enhancement
  • -Adjustment to DAM Start Logic
  • -Adjustment to Data Aggregation to prevent file
    aborts from missing data
  • -Adjustment for AIEC calculation logic when
    RTPERFIP missing
  • There are 11 Commercial System Integration (CSI)
    defects related to transfer of data

Open Defects
Deferred Defects
0
Sev 1
!
45
Deferred
!
6
Sev 2
!
9
Sev 3-5
57
SB Settlements and Billing, Metering, and Data
Aggregation Readiness Update
System Readiness Planned Completion Status
SB System release to Market Trials 5/01/10 Complete
Verify RTM Settlement Statements (CO5) Ongoing Green
Verify RTM Settlement Invoices (CO6) Ongoing Green
Verify DAM Settlement Statements (CO3) Ongoing Green
Verify DAM Settlement Invoices (CO7) Ongoing Green
Verify CRR Auction Invoices (CO8) Ongoing Green
Settle Market for 7 days and provide appropriate extracts (CO1) 8/25/2010 Complete
Verify Dispute Process (CO2) 9/22/2010 Planned
Zonal/Nodal Coordinated Settlement Operations (CO4) 8/25/2010 Complete
Process Readiness Process Readiness Process Readiness
Settlements and Billing Procedures 8/24/10 Complete
Nodal Protocol Transition Plan Updated for Settlements and Billing 7/29/10 Complete
People Readiness People Readiness People Readiness
ERCOT Staff Support of Market Trials 9/30/10 In Process
ERCOT Staff Trained on System and Processes 7/30/10 In Process
Market Participant Training Delivered Ongoing In Process
58
COMS Credit Overview
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • Open issues related to an intermittent
    performance issue and reporting and
    notifications. All items are internal ERCOT
    fixes targeting a 09/03/2010 resolution date.
  • NPRR 241 - CMMFCE Detail reports runs long
  • Exposure calculation engine hung process on
  • EAL Detail Report - In the OIA Section the
    corresponding Invoice data display
  • E-factors- Email notification about e-factors
    values to the counter-parties is not working
    correctly
  • Entity Name field is missing from the Enter CP
    Estimates screen
  • AIL Report- if the RTM Estimated data is missing
    for an Operating Date the report is not
    displaying data correctly

Open Defects
Deferred Defects
0
Sev 1
!
45
Deferred
!
5
Sev 2
!
Sev 3-5
1
59
CMM Credit Management and Monitoring Go Live
draft
System Readiness Planned Completion Status
Credit Management Integrated in Market Trials 5/3/10 Complete
Verify Credit Calculations (CO10) 9/8/2010 Planned
Process Readiness Process Readiness Process Readiness
Credit Management Procedures 8/24/10 Complete
Nodal Protocol Transition Plan Updated for Credit Management 7/29/10 In Process
People Readiness People Readiness People Readiness
ERCOT Staff Support of Market Trials 9/30/10 In Process
ERCOT Staff Trained on System and Processes 8/13/10 Complete
Market Participant Training Delivered Ongoing In Process
60
MIS - Market Information System Overview
Recommendation of Certification
ERCOT
NATF
TAC
BOD
  • Status / Other Issues
  • MIS defects of highest priority are around
    Extract Subscriber and LMP Contour Map and are
    targeting a resolution date by 10/11/2010. Fixes
    for most of these are already developed and will
    be tested during the MIS reconfiguration
    downtime. Examples are
  • Extract Subscriber - No choice to select the
    extract format
  • Extract Subscriber - Unable to unsubscribe the
    subscribed extract.
  • Extract Subscriber Help icon is not being
    displayed in Extract Subscriber application
  • LMP Contour Map Dashboard does not allow for
    alternate dates

Open Defects
Deferred Defects
0
Sev 1
!
7
Deferred
!
9
Sev 2
!
3
Sev 3-5
61
MIS Market Information System Go Live draft
System Readiness Planned Completion Status
MIS System release to Market Trials 2/1/10 Complete
MIS Compliance Test (E12) 9/8/2010 Planned
Process Readiness Process Readiness Process Readiness
MIS Procedures 8/25/10 Complete
Nodal Protocol Transition Plan Updated for MIS 7/29/10 Complete
People Readiness People Readiness People Readiness
ERCOT Staff Support of Market Trials 9/30/10 In Process
ERCOT Staff Trained on System and Processes 8/20/10 Complete
Market Participant Training Delivered Ongoing In Process
62
Nodal Overall Readiness Go Live draft
Market Participant Readiness Items Planned Completion Status
QSE with Resource Connectivity to EDS Environment (MP2) 9/4/2008 Complete
ICCP Point to Point Telemetry Test (MP5) 9/4/2008 Complete
QSE Ability to Submit Transactions via MIS (MP8) 9/4/2008 Complete
QSE Ability to Submit Web Services Transactions (MP9) 9/4/2008 Complete
Resource Registration (MP11) 8/25/2010 Complete
Wind Generation Resources ICCP Metrological Telemetry (MP21) Ongoing Amber
Telemetry Quality (MP to ICCP Server) (MP23) Ongoing Green
Mapping of Resource and Loads in Private Area Networks (MP18) 8/25/2010 Complete
Telemetry Compliance (MP6 - TSP) 6/2/2010 Green
Market Participant Nodal Readiness Declaration (R0) 10/1/2010 Planned
Independent Market Monitor Independent Market Monitor Independent Market Monitor
Market Monitor Systems Capability (IMM1) 10/1/2010 Planned
Validate ISM Access Accuracy of Postings Required by the IMM (E7) 10/1/2010 Planned
ERCOT working to pull IMM target dates in to
meet readiness prior to TAC and Board
63
Nodal Overall Readiness Go Live draft
ERCOT Readiness Planned Completion Status
ERCOT Internal Training (E1) Ongoing Green
Develop Nodal Procedures (E9) Ongoing Green
Develop Nodal Operating Guides (E6) 9/8/2010 Planned
Validate ISM, CDR, and Lodestar Source Reporting Access Accuracy for internal ERCOT use (E10) 10/1/2010 Planned
Verify ERCOT Performance Monitoring Test Plan (E2) 10/1/2010 Planned
Nodal SAS 70 Preparedness (E5) 10/1/2010 Planned
ERCOT Staffed for Texas Nodal Operations (E8) 8/25/2010 Complete
Verify QSE Performance Monitoring Test Plan (E14) 10/1/2010 Planned
Verify TSP Performance Monitoring Test Plan (E15) 10/1/2010 Planned
Operating Personnel and Facilities Readiness (EMO13) 8/11/2010 Complete
ERCOT Operating Personnel and Facilities Readiness (MO7) 8/11/2010 Complete
Conduct EEA Test (EMO8) 9/8/2010 Planned
168-Hour Test Completion (R3) 9/22/2010 Planned
ERCOT Nodal Readiness Declaration (R1) 10/1/2010 Planned
Develop Texas Nodal Market Launch Plan (R2) 9/22/2010 Planned
64
Nodal Overall Readiness Go Live draft
Contingency Plans Planned Completion Status
Contingency Plan for Weekly, Daily and Hourly RUC Failure (C1) 10/01/2010 Planned
Contingency Plan for DAM / LMP Failure (C2) 10/01/2010 Planned
Contingency Plan for ICCP Data Failure (C3) 10/01/2010 Planned
Contingency Plan for SCED Failure (C4) 10/01/2010 Planned
Contingency Plans for Key Settlement and Financial Transfer Processes (C5) 10/01/2010 Planned
Develop Plan for SE Failure (C6) 10/01/2010 Planned
Contingency Plan for a Backup Facility (C7) 10/01/2010 Planned
Contingency Plan for Portal/API Failure (C8) 10/01/2010 Planned
Contingency Plan for Site Unavailability (C9) 10/01/2010 Planned
Verify Single Point of Failure Recovery EMS/MMS/NMMS/CRR/COMS (C10) 10/01/2010 Planned
65
Cut-Over Communication Plan
2/10/2017
66
Nodal Cutover and Market Transition
Communication Plan
  • Friday Market Calls
  • Starting 09/03/2010 at 9AM-12noon these calls
    will be combined, without breaks, into a single
    Market Trials and Cut-over Activities call
  • Market Participants should plan on attending the
    full duration of this call as it will provide the
    primary means of communication between ERCOT and
    the Market.
  • Information and materials covered in this call
    will continue to be posted to the ERCOT calendar
    website every Friday at the following URL
    http//www.ercot.com/committees/nodal/mt/
  • Monday Kick-Off Calls
  • As needed to review the cutover activities for
    the week
  • Market Notices and Market Participant Contact
    Lists
  • ERCOT will continue to leverage Market Notices to
    communicate pertinent information that is
    required to be consumed by the Market as a whole.
  • Market Participants employees can subscribe to
    the Market Notices on the ERCOT Lists website at
    the following URL http//lists.ercot.com/scripts/
    wa-ercot.exe?HOME.
  • Market Participants may verify their contact
    information on file with ERCOT through their
    assigned Whole Client Services Representative.

67
Nodal Cutover and Market Transition
Communication Plan (Cont.)
  • Market Participants Contacting ERCOT
  • Market Trials email inbox markettrials_at_ercot.com.
    This inbox will continue to be maintained
    throughout Nodal Cutover. This will serve as a
    catch-all forum for questions if there is any
    doubt as to where a question should be submitted.
  • Friday Market Calls In line with the previously
    mentioned schedule, these Market Calls not only
    serve as the primary means for ERCOT to
    communicate to the Market, but also for MPs to
    field general questions concerning the Nodal
    Cutover plan.
  • ICCP email inbox ERCOTICCPSupport_at_ercot.com for
    specific MP questions regarding their Nodal ICCP
    / Telemetry, this email address should be
    leveraged for the fastest response.
  • ERCOT Wholesale Client Services Account Manager
    Whenever possible MPs should leverage the Market
    Trials email inbox, however, MPs Wholesale
    Client Services Account Manager will also be
    equipped to either answer your questions or route
    you to the correct support personnel.
  • Nodal Advisory Task Force (NATF) NATF will
    serve as a forum for initially reviewing changes
    in activities during the ERCOT Nodal Cutover,
    NPRRs and any concerns from the Market that would
    impact the overall Cutover plan. To that end,
    NATF will be meeting more frequently to ensure
    expedient coverage of these types of issues.
    Details regarding meeting agendas and materials
    from past meetings will continue to be maintained
    at the following URL http//www.ercot.com/committ
    ees/board/tac/natf/

68
Nodal Cutover and Market Transition
Communication Plan (Cont.)
  • Go-Live Communication Strategy
  • Purpose and Objectives
  • Maintain reliable grid operations during the
    Go-Live period
  • Maintain constant interaction to respond quickly
    and effectively to issues that arise during the
    go-live period
  • Respond and report any observed anomalies in
    market performance or behavior
  • Go-Live Period Communication
  • Market Calls
  • Daily and at times hourly conference calls
    between ERCOT and Market Participants will start
    on 11/23/2010. ERCOT will set up the logistics
    of the calls and communicate via a Market Notice
    and the Cutover Handbook
  • Stabilization Period Communication
  • Market Calls
  • Daily Market Calls thru 12/07/2010 then adjust to
    weekly/biweekly based on need
  • Daily Issue / Inquiry
  • Wholesale Client Service Reps
  • Retail Client Service Reps
  • ERCOT Helpdesk

69
Nodal Cutover and Market Transition Upcoming
Events
Event Agenda Date Location
Nodal Market Call Combined Market Trials and Cutover call between ERCOT and Market Participants begins 09/03/2010 9am-12pm Conf. Call/Web Ex
Nodal Cutover Update Post Go-Live Activities for January, February, March, and Reversion Plan End September Conf. Call/Web Ex
70
Next 60-days of Nodal Classes/Workshops
Course Start Date Location
Congestion Revenue Rights August 31 ERCOT Met Center (Austin)
Generation 201 September 1 Hilton Austin Airport (Austin)
Economics of LMP September 13 ERCOT Met Center (Austin)
ERCOT 101 for Wind Generation September 13 Optim Energy (Dallas)
ERCOT Nodal 101 September 14 StarTex Power (Houston)
Generation 101 September 15 Hilton Austin Airport (Austin)
Basic Training Program September 20 LCRA (Austin)
Load Serving Entity 201 September 27 ERCOT Met Center (Austin)
Congestion Revenue Rights September 29 Suez Energy (Houston)
ERCOT Nodal 101 October 5 RBS Sempra (Stamford, CT)
Basic Training Program October 18 Suez Energy (Houston)
Enrollment at http//nodal.ercot.com/training/cou
rses/index.html
71
Questions