Transcript and Presenter's Notes

Title: PetroGas FZE


1
PetroGas FZE
Concrete Weight Coating PlantAladja
2
Applying Of Concrete Coating Using Gunnite Method
By Means Of CRC Machine
3
- Range of Pipes Diameters for Applying Concrete
Coating
TECHNICAL CAPABILITIES OF THE PLANT
10 40
- Concrete Coating Reinforcement
Galvanized Wire Mesh from 1 to 4 Layers
- Thickness of Concrete Cover
Up to 210 mm
- Obtainable Concrete Density For Concrete
Weight Coating
Up to 3100 kg/m³
- CWC Plant Capacity
0,47 m³/min
- Batching Plant Capacity
0,6 m³/min
4
Technical Base of the Company PetroGas FZE
Provides Steady Supply of Materials
5
Aladja Weight Coating Plant Material and
Technical Base Allows Any Complexity Operations
Execution
6
Ability to Perform Operations 24/7
7
Particularly Developed Winter Period Procedure
Allows High Quality Concrete Production In
Temperatures Lower Than 5 ? Degrees. Plant
Fully Operational 12 Month Per Year
8
Storage Yard Area 900 000 m²
9
CWC Plant Is Located In 700 meters Away From
Aladja Port, Which Decreases The Time and Cost
in Pipes Materials Transferring
10
Quality Control Is Performed At All Stages Of
Production And Guaranteed By TPI.
11
Laboratory And All Certified Tools Required For
Destructive Testing (DT) And Non-Destructive
Testing (NDT) Controls Are Available On Site
12
Concrete Coating Application Operations Are
Performed in Accordance With Approved Procedures
Developed On The Basis Of The Following Standards
- DNW-OS-F101 Offshore standard- ASTM C33
Standard Specification for Concrete
Aggregates- ASTM C94 Standard Specification
for Ready-Mixed Concrete- ASTM A82 Standard
Specification for Steel Wire, Plain, for Concrete
Reinforcement- ASTM C642 Standard Test Method
for Specific Gravity, Absorption and Voids in
Hardened Concrete- ASTM A810 Standard
Specification for Zinc-Coated (Galvanized) Steel
Pipe Winding Mesh- API-RP 5LW Recommended
Practice for Transportation of Line Pipe on
Barges or Marine Vessels- API RP
5L1 Recommended Practice for Transportation of
Line Pipe- BS 1881-108 Method for Making Test
Cubes from Fresh Concrete- BS 1881-114 Method
for Determination of Density of Hardened Concrete
Cubes- BS 1881-120 Method for Determination of
Density of Hardened Concrete Cores- NACE RP
02-74-1974 High Voltage Electrical Inspection of
Pipeline Coating to Installation.
13
Technological Process of Concrete Coating
Applying
14
  1. Feeding Pipe To The Racks For
    Anti-Corrosion Coating Control Repair If Any

15
2. Installation Of Pipes On Transfer Cart And
Application Of Concrete Coating
16
3. Pipes Weighing Simultaneous Negative
Buoyancy Calculation
17
4. Transportation To Storage Area
18
5. Damaged Concrete Coating Repair By Means Of
Manual Gunnite Machine
19
6. Installation Of Anode Protection
20
THREE LEVEL QUALITY ASSURANCE
21
1 Pipe and Raw Materials Receipt
- Receipt Inspection of Raw Materials
a) Condition, Packing Markings
b) Testing of Concrete Materials
- Cement Portland Cement
a) Test Certificate
b) Batch Date of Manufacture
c) Physical Condition of Cement, i.e. Lumps
Contamination
- Iron Ore Delivery Testing
a) Test Certificate
b) Packing List Country of Origin
c) Check for moisture content
- Water
a) Certificates Issued by Local Water Authority
Tested 3rd Party
b) Cleanliness
- Wire Reinforcement
a) Test Certificates
b) Conditions of Rolls
c) Dimensional checks
d) Markings
e) Packaging Storing
- 3-LPE Coated Pipe Stacking (Temporary Storage)
a) Stacking of 3-LPE Coated Pipe
b) Check if Number of Tiers is Per the Approved
Calculation
c) Check That separators are Intact no Pipe
Surfaces are Adhering to Each Other
22
2 CWC Coating Qualification (PQT)
- Concrete Mix Design
- Concrete Weight Design
- 3-LPE Coated Pipe Reception
- Temperature (Ambient, Water, Sand, Iron Ore)
- Aggregate Gradation (Iron Ore)
- Aggregate Gradation (Sand)
- Pipe Weight Scale Calibration
- Holiday Detector Voltage Check
- Visual Inspection Holiday Detection
- 3-LPE Coating Repairs (If Any)
- Concrete Mix Temperature
- Concrete Moisture Content
- Reinforcement Required (Wire Mesh Control)
- Reinforcement Placement, Overlap, Reinforcement
Concrete Cover
- Concrete Girth Measurements
- Concrete Cut-Back Control
- Visual Inspection of Applied Concrete
- Weight of Freshly Concrete Coated Pipe
- Calculation of Negative Buoyancy
- Electrical Isolation Between Reinforcement/Pipe
- Concrete Repairs (If Any)
- Compressive Strength (Cubes)
- Compressive Strength (Cores)
- Density
- Water Absorption
23
3 Concrete Coating Production
- 3-LPE Coated Pipe Stacking (Temporary Storage)
- CWC Plant, 3-LPE Coated Pipe Reception
- Holiday Detector, Voltage Check
- Visual Inspection Holiday Detector
- Pipe Weight Scale Calibration
- 3-LPE Coating Repairs (If Any)
- Ambient Temperature
- Concrete Mix Temperature, Concrete Mix Content
- Concrete Application
- Reinforcement Required (Wire Mesh Control)
- Reinforcement Overlap
- Reinforcement Placement
- Reinforcement Concrete Cover
- Concrete Cut-Back Control
- Reclaimed Concrete
- Visual Inspection of Applied Concrete
- Concrete Girth Measurements
- Weighing of Freshly Concrete Coated Pipe
- Calculation of Negative Buoyancy
- Pipe Markings
- Anodes Slotting
- Concrete Repairs (Cracks)
- Surface Damage
- Electrical Isolation Between Reinforcement and
Pipe
- Colour Coding Concrete Coated Pipe
24
4 Laboratory Productions Tests
- Concrete Moisture Content
- Aggregate Gradation (Iron Ore)
- Aggregate Gradation (Sand)
- Compressive Strength (Cubes)
- Compressive Strength (Cores)
- Density
5 Handling Stacking of Coated Pipe
- Handling of Coated Pipe
- Stack Heights
- Load-Out
6 Records Documentation
- Documentation Record (All Reports on a Daily
Basis)
- Final Documentation (Data Books)
25
Completed Projects
Epic of new 30" Trunk Line and Infield Lines
Pipeline 30 29 km. Concrete Thickness 80, 105
152,4 mm
Pipeline 20 5 km. Concrete Thickness 65 75 mm
Pipeline 18 5 km. Concrete Thickness 40 mm
GARAGOL DENIZ DEVELOPMENT PROJECT
Pipeline 14" 74 km. Concrete Thickness 40 mm,
45 mm, 95 mm
26
Plant Qualified Engineers and Operating Personnel
Are Minded To Implement Projects Of Any Complexity
Concrete Weight Coating Plant Aladja
PetroGas FZE, 2010