Title: ESTIMATION
1ESTIMATION
- Estimation is the scientific way of working out
the approximate cost of an engineering project
before execution of the work. - It is totally different from calculation of the
exact cost after completion of the project. - Estimation requires a thorough Knowledge of the
construction procedures and cost of materials
labour in addition to the skill , experience,
foresight and good judgment.
2ESTIMATE
- An estimate of the cost of a construction job is
the probable cost of that job as computed from
plans and specifications. -
- For a good estimate the, actual cost of the
proposed work after completion should not differ
by more then 5 to 10 from its approximate cost
estimate, provided there are no unusual,
unforeseen circumstances.
3NEED FOR ESTIMATE
- 1. It help to work out the approximate cost of
the project in order to decide its feasibility
with respect to the cost and to ensure the
financial resources, it the proposal is approved. - 2. Requirements of controlled materials, such as
cement and steel can be estimated for making
applications to the controlling authorities. - 3. It is used for framing the tenders for the
works and to check contractors work during and
after the its execution for the purpose of making
payments to the contractor. - 4. From quantities of different items of work
calculated in detailed estimation, resources are
allocated to different activities of the project
and ultimately their durations and whole planning
and scheduling of the project is carried out.
4SITE CONDITIONS AFFECTING THE OVERALL COST
- 1 Each type of work requires a different method
of construction. Construction may be of an
ordinary house or office and it may also be of a
Dam, Tunnel, Multistory building, Airport,
Bridge, or a Road, already in operation. Each of
these works requires totally different
construction techniques, type of machinery, and
formwork. - 2 Quality of labour and labour output varies in
different localities. - 3 Weather conditions greatly affect the output
and, hence, the overall cost.
5SITE CONDITIONS AFFECTING THE OVERALL COST (-ctd-)
- 4. Ground conditions vary and change the method
of construction. For example, excavation may be
dry, wet, hard, soft, shallow or deep requiring
different efforts. - 5. The work may be in open ground such as fields
or it may be in congested areas such as near or
on the public roads, necessitating extensive
watching, lightening, and controlling efforts,
etc.
6SITE CONDITIONS AFFECTING THE OVERALL COST (-ctd-)
- 6. The source of availability of a sufficient
supply of materials of good quality is also a
factor. - 7. The availability of construction machinery
also affects the method of construction. - 8. Access to the site must be reasonable. If the
access is poor, temporary roads may be
constructed.
7ESSENTIAL QUALITIES OF A GOOD ESTIMATOR
- In preparing an estimate, the Estimator must have
good knowledge regarding the important rules of
quantity surveying. - He must thoroughly understand the drawings of the
structure, for which he is going to prepare an
estimate. - He must also be clearly informed about the
specifications showing nature and classes of
works and the materials to be used because the
rates at which various types of works can be
executed depend upon its specifications.
8ESSENTIAL QUALITIES OF A GOOD ESTIMATOR (-ctd-)
- A good estimator of construction costs should
possess the following capabilities, also- - 1 A knowledge of the details of construction
work. - 2 Experience in construction work.
- 3 Having information regarding the materials
required, machinery needed, overhead problems,
and costs of all kinds. - 4 Good judgment with regard to different
localities, different jobs and different workmen. - 5 Selection of a good method for preparing an
estimate. - 6 Ability to be careful, thorough, hard working
and accurate. - 7 Ability to collect, classify and evaluate
data relating to estimation. - 8 Ability to visualize all the steps during the
process of construction.
9ESSENTIAL QUALITIES OF A GOOD ESTIMATOR (-ctd-)
- Before preparing the estimate, the estimator
should visit the site and make a study of
conditions, there. For example, if the
construction of a large building is planned, the
estimator or his representative should visit the
site and - Note the location of the proposed building.
- Get all data available regarding the soil.
- Make a sketch of the site showing all important
details. - Obtain information concerning light, power, and
water. - Secure information concerning banking
facilities. - Note conditions of streets leading to railway
yards and to material dealers, and - Investigate general efficiency of local workman.
10TYPES OF ESTIMATES
- There are two main types of estimates-
- 1 Rough cost estimate.
- 2 Detailed estimate.
- Depending upon the purpose of estimate, some
types of detailed estimate are as follows- - Contractor's estimate
- Engineer's estimate
- Progress estimate
11I Rough cost estimate
- Estimation of cost before construction from plans
or architectural drawings of the project scheme,
when even detailed or structural design has not
been carried out, is called Rough cost estimate. - These estimates are used for obtaining
Administrative Approval from the concerning
Authorities. - Sometimes, on the basis of rough cost estimates,
a proposal may be dropped altogether.
12Rough cost estimate (-ctd-)
- Unit cost is worked out for projects similar to
the project under consideration carried out
recently in nearly the same site conditions. - Unit cost means cost of execution of a unit
quantity of the work. -
13Rough cost estimate (-ctd-)
- To find rough cost of any project, this worked
average unit cost is multiplied with total
quantity of the present work in the same units. - For example, in case of a building, plinth area
(sq. ft.) of the proposed building is worked out,
which is then multiplied by the cost per unit
area (Rs. /ft2) of similar building actually
constructed in the near past in nearly the same
site conditions, to find out the rough cost
estimate of the building. - This cost is sometimes adjusted by the average
percentage rise in the cost of materials and
wages.
14Rough cost estimate
- The rough cost estimate may be prepared on the
following basis for different types of projects - 1. Cost per square foot of covered area
(plinth area) is the most commonly adopted
criterion for preparing rough cost estimate for
most of the residential buildings. - 2. For public buildings, cost. Per person
(cost per capita) is used. For example, - Students hostel-cost per student
- HospitalsCost per bed
- HotelCost per Guest
15Rough cost estimate (-ctd-)
- Cost per cubic foot is particularly suitable for
commercial offices, shopping centers, and factory
buildings, etc. - For water tank/reservoir, cost may be worked out
on the basis of capacity in gallons of water
stored. - For roads and railways, cost may be found out
per mile/kilometer of length. - For streets, cost may be per hundred feet/meters
of length. - 7. In case of bridges, cost per foot/meter of
clear span may be calculated.
16EXAMPLE 01
- Calculate the total rough cost estimate and cost
per Flat for a multi-storey (4-storeyed) block
consisting of 40 residential flats. Other details
are given in the table
17Sr. No PORTION AREA (sq. ft) UNIT COST (Rs./sq.ft.) UNIT COST (Rs./sq.ft.) UNIT COST (Rs./sq.ft.) UNIT COST (Rs./sq.ft.)
Sr. No PORTION AREA (sq. ft) Building Works Sanitory Works Electric Services Sui Gas Services
1 Main Flat Area (i) Ground Floor (ii) Ist Floor (iii) 2nd Floor (iv) 3rd Floor 20030 20030 20030 20030 1800 1500 1650 1800 130 130 130 130 100 100 100 100 60 60 60 60
2 Park Area at G. Floor 75,800 800 -------- 40 -------
3 Circulation Area in all 4 floors 1936 1050 -------- 70 -------
4 Covered Shopping Area at G. Floor 920 950 -------- 70 -------
5 Attached Servant Quarters 2112 1150 55 70 40
18Add the following costs as Lump Sum
- 1- Road and Walkways 15,00,000/-
- 2- Land Scapping 12,00,000/-
- 3- External Sewerage 7,00,000/-
- 4- External Water Supply, Overhead and
Underground Water Tanks with pumping machinery
for each set of Flats 19,00,000/- - 5- External Electricity 3,00,000/-
- 6- Boundary Wall 6,00,000/-
- 7- Miscellaneous unforeseen items
- 8,00,000/-
- 8- Add 6 development charges.
- 9- Add 3 consultancy charges
19EXAMPLE 2
- Prepare a Rough-cost Estimate of a residential
building project with a total plinth area of all
building of 1500 sq.m. given that - Plinth Area Rate Rs 950.00 / sq. ft.
- Extra for special architectural treatment
1.5 of the buiding cost. - Extra for water supply and sanitary installations
5 of the building cost. - Extra for internal installations 14 of the
buiding cost - Extra for Electric Sui gas services 16 of
buiding cost - Contigencies 3 overall
- Supervision charges 8 overall
- Design charges 2 overall
20EXAMPLE 3
- Prepare a Rough-cost Estimate based on unit
costs of per unit plinth area basis of a four
storeyed office building having a carpet area of
2000 sq.m. for obtaining the administrative
approval of the Government. It may be assumed
that 30 of the built up area will be taken by
the corridors, verandas, lavatories, staircase,
etc. and 10 of built up area will be occupied
by walls. The following data is given - Plinth Area Rate Rs 1100.00 / sq. ft.
- Extra for special architectural treatment
0.5 of the building cost. - Extra for water supply and sanitary installations
6 of the building cost.
21- Extra for internal installations 14 of the
building cost - Extra for electric services 12.5 of
building cost - Extra for sui gas services 6 of building
cost - Extra due to deep foundations at site 1.0 of
building cost - Contingencies 2.5 overall
- Supervision charges 8 overall
- Design charges 2.5 overall
- Hint Let Building Area X
- Building Area Carpet Area Wall Area
Corridores, Stair-case, Lavatories, Lobby, etc - X 2000 (0.01 X) (0.03 X)
in sq. m.
22Example 4
- Prepare a Rough-cost Estimate for obtaining the
administrative approval of the Government for a
hospital project to serve both indoor and outdoor
patients in an important rural area. The hospital
will consist of the following - Main administrative office with dispensing
operations, etc. - Two general wards, each of 20 general beds.
- Superintendent Doctors Residence.
- Two Assistant Doctors Residences.
- Eight single Nurses Quarters.
- Four Compounders Quarters.
- Twelve lower staffs Quarters.
23- Provision for electrical, sui gas, water supply,
sewerage installations, and for external roads,
water supply, sanitary, electrification, storm
water drains, fencing, arboriculture, etc. shall
have to be made. - Assuming suitable plinth area of the building,
plinth area rate, and other rates including
design, supervision, contingencies, landscaping,
arboriculture, and development charges, work out
the total estimated cost of the hospital based on
unit costs of per unit plinth area basis.
24DETAILED ESTIMATE
- Detailed estimates are prepared by carefully and
separately calculating in detail the costs of
various items of the work that constitute the
whole project from the detailed working drawings
after the design has been finalized. -
- The mistakes, if any, in the rough cost estimate
are eliminated in the detailed estimate. - Detailed estimates are submitted to the competent
authorities for obtaining technical sanction.
25DETAILED ESTIMATE
- The whole project is sub-divided into different
items of work or activities. The quantity for
each item is then calculated separately from the
drawings as accurately as possible. The procedure
is known as "taking out of quantities". - The quantities for each item may be estimated and
shown in the pattern which is called "Bill of
quantities." - The unit, in which each item of the wok is to be
calculated, should be according to the prevailing
practice as followed in various departments of
the country.
26BILL OF QUANTITIES
Sr. No Description of item No Measurements Measurements Measurements Quantity Total Quantity Remarks
Sr. No Description of item No Length Breadth Height Quantity Total Quantity Remarks
27PRICED BILL OF QUANTITIES
Sr. No. Description of Item Unit Quantity Rate Cost Remarks
28DETAILED ESTIMATE
- Each item of the work is then multiplied by its
estimated current rate calculated by a fixed
procedure to find out cost of the item. - At the end, a total of all items of the work are
made to get the total estimated cost. - The rates are usually as per Schedule of Rates
for the locality plus a premium to allow for rise
in labor and material rates over and above the
schedule of rates. - A percentage, usually 5 is also provided on the
total estimated cost for the work to allow for
the possible contingencies due to unforeseen
items or expenditure or other causes, besides 2
establishment charges.
29DETAILED ESTIMATE
- Besides drawings and details of measurements and
calculation of quantities (Bill of Quantities),
the following documents are also usually
submitted with the detailed estimate for
obtaining Technical Sanction - A report explaining History, necessity, scope and
main features of the project, its design, and
estimate, etc. - 2. Specifications lying down the nature and
class of work and material to be used in various
parts of the work. - 3. The abstract of cost (priced Bill of
Quantities) showing the total quantities under
each sub-head, rate per unit of measurement, and
cost. - 4. Calculation sheets showing calculations for
important parts of the structure. In fact, in
estimating the art and skill lies only in the
computation of details without any omissions, of
all parts of the building or work.
30CLASSIFICATION DEPENDING UPON
PURPOSE OF DETAILED ESTIMATE
- 1- CONTRACTOR ESTIMATEIt is made by the
contractor for determining the price or prices to
be bid. It is usually a carefully prepared
detailed estimate. - 2- ENGINEERS ESTIMATE
- This type of estimate is made by the Engineer
(Consultant) usually for the purposes of
financing the work and for checking bids and
running bills submitted by contractors.
313- PROGRESS ESTIMATES
- These are made by the Engineer at regular
intervals for the completed parts of the project
during the progress of the work for determining
the amounts of partial payments to be made to the
contractor. - On large contracts, such estimates are commonly
made each month and, hence, are frequently called
monthly estimates.
32UNFORESEEN ITEMS IN DETAILED ESTIMATE
- While preparing a detailed estimate, one had to
be very careful to see that all items of the work
are incorporated. - It is likely that a few Items, though unimportant
in nature, might have been overlooked and which
may result in raising the estimate of the
project. - There may be also certain unforeseen
circumstances affecting the project. - Hence, a certain allowance usually 5 to 10 of
the total cost, is made in the estimation which
will take care of all these items that are
unforeseen or are overlooked and are known as
"Contingencies".
33METHODS OF DETAILED ESTIMATE
- The dimensions, length, breadth and height or
depth are to be taken out from the working
drawings (plan, elevation and section). - Junctions of walls, corners and the meeting
points of walls require special attention. - For symmetrical footings, which is the usual
case, earthwork in excavation in foundations,
foundation concrete, brickwork in foundation and
plinth, and brickwork in superstructure may be
estimated by either of the two methods - (1) SEPARATE OR INDIVIDUAL WALL METHOD
- (2) CENTER LINE METHOD
34SEPARATE OR INDIVIDUAL WALLS METHOD
- The walls running in one direction are termed as
"long walls and the walls running in the
transverse direction, as "Short waLls", without
keeping in mind which wall is lesser in length
and which wall is greater in length. - Lengths of long walls are measured or found
"Out-to out" and those of short walls as
"In-to-in". - Different quantities are calculated by
multiplying the length by the breadth and the
height of the wall. - The same rule applies to the excavation in
foundation, to concrete bed in foundation,
D.P.C., masonry in foundation and super structure
etc.
35SEPARATE OR INDIVIDUAL WALLS METHOD
- For symmetrical footing on either side, the
center line remains same for super structure,
foundation and plinth. So, the simple method is
to find out the centre-to-centre lengths of long
walls and short walls from the plan. - Long wall length out-to-out
- Center to center length half breadth on one
Side half breadth on other side. - Center to center length one breadth
- Short wall length in-to-in Center to Center
length - one breadth.
36SEPARATE OR INDIVIDUAL WALLS METHOD
- This method can also be worked out in a quicker
way., as follows - For long walls
- First of all, find the length of the foundation
trench of the long wall out-to-out in the same
manner as explained above. - The length of the foundation concrete is the
same. - For the length of the first footing or first step
of the brick wall, subtract two offsets
(2x6"12") in foundation concrete from the length
of the trench or concrete. - For the second footing subtract from the length
of the 1st footing two offsets (2x2.25" 4.5"),
for 3rd footing subtract from the length of the
2nd footing 2 offsets (4.5") and in this way
deal with the long walls up to the
super-structure. - For short walls
- Follow he same method but instead of subtracting
add two offsets to get the corresponding lengths
in-to-in.
37(No Transcript)
38CENTRE LINE METHOD
- In this method, total length of centre lines of
walls, long and short, has to be found out. - Find the total length of centre lines of walls of
same type, having same type of foundations and
footings and then find the quantities by
multiplying the total centre length by the
respective breadth and the height. - In this method, the length will remain the same
for excavation in foundations, for concrete in
foundations, for all footings, and for
superstructure (with slight difference when there
are cross walls or number of junctions). - This method is quicker but requires special
attention and considerations at the junctions,
meeting points of partition or cross walls.
39CENTRE LINE METHOD
- For rectangular, circular polygonal (hexagonal,
octagonal etc) buildings having no inter or cross
walls, this method is quite simple. - For buildings having cross or partition walls,
for every junction, half breadth of the
respective item or footing is to be deducted from
the total centre length. - Thus in the case of a building with one partition
wall or cross wall having two junctions, deduct
one breadth of the respective item of work from
the total centre length.
40(No Transcript)
41CENTRE LINE METHOD
- For buildings having different types of walls,
each set of walls shall have to be dealt
separately. - Find the total centre length of all walls of one
type and proceed in the same manner as described
above. Similarly find the total centre length of
walls of second type and deal this separately,
and so on. - Suppose the outer walls (main walls) are of A
type and inner cross walls are of B type. -
- Then all A type walls shall be taken jointly
first, and then all B type walls shall be taken
together separately. -
- In such cases, no deduction of any kind need be
made for A type walls, but when B type walls are
taken, for each junction deduction of half
breadth of A type walls (main Walls) shall have
to be made from the total centre length of B type
walls.
42CENTRE LINE METHOD
- At corners of the building where two walls are
meeting, no subtraction or addition is required. - In the figure, the double cross-hatched areas
marked P,Q,R, S come twice, while blank areas,
A,B,C, D do not come at all, but these portions
being equal in magnitude, we get the correct
quantity.
43(No Transcript)
44DESCRIPTION AND UNITS OF MEASUREMENT FOR COMMON
ITEMS
451 SITE CLEARANCE WORKS
- This item is described in detail but the price of
this item is usually indicated as lump sum (LS). - The cost of this item is provided in the estimate
by judgment, according to the description of the
item and is indicated as Lump sum (L.S).
462 EXCAVATION FOR FOUNDATION TRENCHES
- Earthwork in excavation for foundation trenches
is calculated by taking the dimensions of each
trench as length X breadth X depth. -
- It is measured in cubic ft, cubic yard or cubic
meter, according to the prevailing practice. -
- The payment for this item is generally done as
Rs. per hundred cubic ft. -
47FILLING IN TRENCHES
- Filling in trenches after the construction of
foundation masonry is ordinary neglected. If the
trench filling is, also taken in account, it may
be calculated by deducing the volume of masonry
in trenches from that of the volume of
excavation.
483 FOUNDATION CONCRETE (P.C.C.)
- The type of concrete must be clearly mentioned.
The mix proportions and the type of cement, sand
and coarse aggregate must be specified. - This item is measured in cubic ft and the unit
for measurement is, generally Rs. per 100 cubic
ft. - When the soil is soft or weak, one layer of dry
bricks or stone soling is applied below the
foundation concrete. The soling layer is computed
in sq.ft (length X breadth), specifying the
thickness in description of item.
494 BRICKWORK IN FOUNDATION UP TO PLINTH
- Care must be taken, while taking dimensions from
the drawings in the bill of quantities because
the walls in this part of the structure are in
the form of steps with changing dimensions. - This item is calculated in cft and the unit for
payment is Rs. per 100 cft. - In the description of work, the quality of bricks
and mortar ratio must be specified. For example, - "Brickwork in foundation and plinth using first
class bricks laid in (14) or (16) cement-sand
(c/s) mortar
505 BRICKWORK IN SUPER STRUCTURE
- Important considerations are
- a Measurements of walls shall be taken in the
same order and in the same manner as for
brickwork in foundations and plinth. - b In the first measurements, all openings
such as doors, windows, veranda openings etc.
shall be neglected. However, deductions shall be
made for all openings in the walls, at the end of
the item.
51BRICKWORK IN SUPER STRUCTURE (ctd)
- c In the description of the work, the
quality of bricks and mortar ratio have to be
specified. - d Masonry for arches shall be paid separately,
at a different rate. - e The height of super structure is very
important. Generally the quantities are worked
out for each storey separately and rates would
be different for different storeis because of
additional labor work, scaffolding and
shuttering. - f The item is worked out in cft and the
standard unit for payment is Rs. Per 100 cft.
526 DAMP PROOF COURSE (D.P.C.)
- Horizontal D.P.C. shall extend the full width of
the super structure walls, however, it shall not
be provided across doorways and veranda openings.
It is also provided in roof and floors. -
- Vertical D.P.C. is provided in external walls,
especially, in the walls of basements. - The quantity of D.P.C. is estimated in square
ft.(on area basis) and standard unit for payment
is Rs. per 100 sft.
537 ROOFING RCC WORKS
- Area of the Roof slab is calculated by taking
inside dimensions of the room plus a bearing of
the roof slab on the walls, on all sides. - For R.C.C. Roof slabs and beams, the total
quantities of concrete and steel are estimated,
separately. - The quantity of plain concrete is estimated in
cft and the standard unit for payment of concrete
is Rs. per 100 cft. -
- Volume of Reinforcing Steel is not deducted ,
while estimating the volume of plain concrete
for payment. - c R.C.C. lintels over wall openings such as
doors and windows are also included in R.C.C.
work.
54ROOFING RCC WORKS (ctd)
- Roof consisting of beams, battens, and tiles or
wooden planks is estimated for each part,
separately. -
- Steel beam is estimated by weight, whereas,
wooden beam is measured in cft. Battens are
estimated by numbers indicating there size and
lengths. Tiles are also estimated by size and
numbers. - Roof finishing may consist of bitumen coating
and/or Polythene sheets (water proofing) , earth
filling (heat proofing) and brick tiles, etc. -
- Dimensions are taken from inner face to inner
face of parapet walls. -
- This item is estimated in sft and a composite
rate for payment is taken as Rs. per 100 sft of
the roof area.
558 REINFORCEMENT STEEL / GENERAL STEEL WORK
- Steel is provided separately from R.C.C. per ton,
per Kg, or per cwt (standard weight also called
Quintal or century weight equal to 112 Ibs
50Kg). - Quantity of steel can either be worked out by
rules of thumb practice or by intensive
calculations taking the length and diameter of
steel bars from the working drawings showing
reinforcement details and bar-bending schedules.
In taking length of bars, due margin of hooks,
bends and overlapping is given
56REINFORCEMENT STEEL / GENERAL STEEL WORK (-ctd-)
- As a Rule Of Thumb Practice,
- for ordinary beams and slabs for residences,
assume 6.75 Ibs of steel per cft of R.C.C. work.
However, for R.C.C. columns, it varies from 8 to
10 Ibs per cft., because normally, we use 2 of
steel in columns. - Percentage of steel means, area of steel divided
by total area of the column multiplied by 100 and
1 of steel in columns corresponds to a quantity
of 4.5 Ibs/cft.
579 FLOORS
- Cement concrete floors. Mosaic floors, and brick
floors are most commonly used. - Payments are made separately for different
layers, like, topping, lean concrete, sand
filling, earth filling, etc. - Earth filling, sand filling and lean concrete
are paid by volume, whereas, topping is paid on
area basis, mentioning thickness in the
description. - Standard unit for payment of topping is, usually,
Rs. per 100 sft. - The skirting is estimated in running ft.
5810 PLASTERING
- The type of plaster, proportioning of materials
and minimum thickness of plaster have to be
specified. - The quantity is calculated for total wall surface
without deduction for openings such as doors
windows, ventilators, etc. However, if the wall
is being plastered on both the faces, the
deductions for opening areas are made from one
side only. - Standard unit for payment is Rs. per 100 sft.
- Height is also specified for plastering because,
for greater heights, labor cost increases. The
rate varies according to the number of the storey
5911 WOODWORK/CARPENTRY
- The type of material used and the quantity of
finish required should be clearly indicated in
the description of the item. - The rate for any type of woodwork includes
cutting of timber to required sizes, joinery
work, fittings and fastenings, three coats of oil
paints or varnish, bolts, locks, handles, etc. - The measurements are taken for the overall area
of doors, windows, etc. If volume of timber
required for these items is to be finding out,
the computed area is multiplied with the nominal
thickness and an allowance of 25 is made for
wastage of timber.
60WOODWORK/CARPENTRY (-ctd-)
- Rectangular wooden beams, vertical columns,
trusses, etc., are measured in cft. - Wooden stairs are measured in number of steps and
description of the item includes the riser,
tread, and width of the steps. - Wooden shelves are measured in running ft (RFT).
6112 PLUMBING WORK/SANITARY FITTINGS
- For water supply and drainage works in a
building, the pipe lines and sewer lines are
measured in RFT, while other items are measured
in numbers. - These items include wash hand basins (W.H.B.),
kitchen basins (which may be of glazed ceramic,
mosaic, or stainless steel), water closets (W.C.,
which may be of European type, or local type),
flushing tanks (also known as flushing
cisterns), shower rose, and all type of water
tapes.
62PLUMBING WORK/SANITARY FITTINGS (-ctd-)
- Within sewer lines, man holes or inspection
chambers are to be provided at every corner and
also at a distance, not exceeding every 50 ft
inside the house and every 100 ft outside the
house. - The size of man hole may be 2.5ft X 2,5ft for low
depths and 3ft X 3ft, 4ft X 4ft or 5ft X 5ft for
deep depths. - Drainage pipe lines outside the covered area but
inside the boundary wall are, usually, of R.C.C.
with minimum diameter 4 in, however, these are
available in different sizes. - Inside the building, drainage pipe is, usually,
of C.I. with minimum diameter 3 in. - Water supply pipes are, usually, G.I. pipes.,
estimated in RFT in different dias. - Other accessories, like sockets, elbows, tees,
reducers, unions, etc., are estimated in numbers.
6313 ELECTRIC FITTINGS
- All the accessories used in electric fittings are
described in detail and payment is done in
numbers or RFT. - All wires and pipes are taken in RFT while other
items are taken in Nos.
64SOME COMMON RELATIONS USED IN BUILDING ESTIMATES
65- 1- MORTARS
- Cement-Sand Mortars
- 120 cft dry yields 100 cft wet
- (b) Lime-Sand Mortars
- 113 cft dry yields 100 cft wet
- (C) Cement-Lime-Sand Mortars
- 112 cft dry yields 100 cft wet
- (d) Dry mortar required for 100 sft of ½ thick
cement plaster 6 cft
662- CEMENT CONCRETE 154 cft dry yields
100 cft wet 3- BRICKWORK (a) 100 cft Brick
masonary Bricks ------------1350 Dry
Mortar ------- 30 cft Wet Mortar ------- 25
cft (b) 100 sft surface area using bricks on
bed Bricks --------------360 Mortar
------------- 9 cft (b) 100 sft surface area
using bricks on edge Bricks
--------------540 Mortar ------------- 13
cft
674- POINTING PER 1000 SFT AREA
Ingredient 11 12 13
Cement 8 cft 5 cft 3.8 cft
Sand 8 cft 10 cft 11.4 cft
5- EARTHWORK Output of labor assuming one man
working 8 hours per day with lift up to 5 ft or
less
TYPE OF SOIL EXCAVATION PER DAY
Medium Soil 75 100 cft
Hard / Stiff Soil 50 75 cft
Rocky Soil 25 30 cft
686- BITUMEN
Bitumen for 100 sft of DPC (first coat) 15 Kg
Bitumen for 100 sft of DPC (second coat) 10 Kg
7- CEMENT 1 Bag ------------- 50 Kg
(Weight), 1.25 cft (Volume) 8- SPECIFIC
WEIGHTS RCC --------------- 150 lbs /
cft PCC --------------- 145 lbs /
cft Aggregate ------- 166 lbs / cft
699- TIMBER
Timber for 100 sft of Panelled Doors and Windows 13 cft
Timber for 100 sft of Glazed windows and Ventilators 8 cft
10- WHITE WASH
Lime for 100 sft of white wash (one coat) 1.00 Kg
70ESTIMATION OF A SIMPLE BUILDING
71PLAN
72 FOUNDATIONS
73SPECIFICATIONS
- Clear height of rooms 12
- Clear height of Verandah 10-0
- Plinth level 1-6
- Thickness of roof slab 4
- Thickness of RCC shade 3
- Depth of RCC Beams in Verandah 1-6 below
verandah slab - Parapet wall 1-0 (Clear height above roof
tiles) - Ventilators (4 No.) 2-6 x 1-6
- RCC lintel 6 in depth
- Damp proof coarse 1 ½thick PCC (124) 2
coats of hot bitumen polythene sheet - Full foundation up to plinth level along verandah
periphery is provided - Internal finishes Three coats of white
wash/distemper paint - External finishes Three coats of Weather shield
paint
74Center to Center Lengths
- L1 (10-0) (12-0) (0-4 ½) (0-4 ½)
(0-4 ½) 23-1 ½ - S1 S2 (12-0) (0-4 ½) (0-4 ½)
12-9 - S3 (8-0) (0-4 ½) - (0-4 ½) 8-0
75BILL OF QUANTITIES1- CIVIL WORKS
S. No Description of item No Measurement Measurement Measurement Quantity Total Quantity Remarks
S. No Description of item No Length Breadth Depth Quantity Total Quantity Remarks
1 Earthwork for excavation in foundation trenches
L1 3 25-7 ½ // 2-6 3-6 224.22 cft 672.66 cft L 23-1 ½2-6 25-7 ½
S1 2 10-3 2-6 3-6 89.69 cft 179 .38 cft L 12-9-(2-6) 10-3
S2 1 10-3 2-1 ½ 3-6 76.23 cft 76.23 cft L 12-9-(2-6) 10-3
S3 2 5-6 2-6 3-6 48.13 cft 96.25 cft L 8-0-(2-6) 5-6
Total 1024.52 cft
762 Earth work in filing under floors
Room No.1 1 12-0 12-0 0-6 ½ 78.00 cft 78.00 cft D 1-6-(0-11 ½) 6 1/2
Room No.2 1 10-0 12-0 0-6 ½ 65.00 cft 65.00 cft
Veranda 1 22-4 ½ 7-3 0-6 ½ 87.87 cft 87.87 cft L 10-0(0-4½)(12-0) 22-4 ½ B 8-0-(0-9) 7-3
Total 230.87 cft
3 P.C.C (148) in foundation using crushed or broken stones Length Breadth same as for Foundation trenches (Item No. 1)
L1 3 25-7 ½ 2-6 0-6 32.00 cft 96.00 cft
S1 2 10-3 2-6 0-6 12.81 cft 25.63 cft
S2 1 10-3 2-1 ½ 0-6 10.89 cft 10.89 cft
S3 2 5-6 2-6 0-6 6.87 cft 13.75 cft
Total 146.27 cft
774 Burnt brick work in foundation and plinth using first class bricks in (16) cements sand mortar.
(a) L1
1st step 3 24-7 ½ 1-6 0-6 18.47 cft 55.40 cft L 23-1½(1-6) 24-7½
2nd step 3 24-3 1-1 ½ 0-6 13.64 cft 40.92 cft L 23-1½(1-1½) 24-3
3rd step up to plinth level 3 23-10 ½ 0-9 3-4 ½ 60.43 cft 181.30 cft L 23-1½(0-9) 23-10½ D 2-0 (1-6) (0-1 ½) 3-4 ½
Total 277.62 cft
(b) S1
1st step 2 11-3 1-6 0-6 8.44 cft 16.88 cft L 12-9-(1-6) 11-3
2nd step 2 11-7 ½ 1-1 ½ 0-6 6.54 cft 13.08 cft L 12-9-( 1-1½) 11-7½
3rd step up to plinth level 2 12-0 0-9 3-4 ½ 30.37 cft 60.75 cft L 12-9-( 0-9) 12-0
Total 90.71 cft
78(c) S2
1st step 1 11-3 1-1 ½ 0-6 6.33 cft 6.33 cft L 12-9-(1-6 ) 11-3
2nd step 1 11-7 ½ 0-9 0-6 4.36 cft 4.36 cft L 12-9-( 1-1½) 11-7½
3rd step up to plinth level 1 12-0 0-4 ½ 3-4 ½ 15.19 cft 15.19 cft L 12-9-( 0-9) 12-0
Total 25.88 cft
(d)S3
1st step 2 6-6 1-6 0-6 4.87 cft 9.75 cft L 8-0-(16) 6-6
2nd step 2 6-10 ½ 1-1 ½ 0-6 3.86 cft 7.73 cft L 8-0-(1-1½) 6-10½
3rd step up to plinth level 2 7-3 0-9 3-4 ½ 18.35 cft 36.70 cft L 8-0-(0-9) 7-3
Total 54.18 cft
(e) steps in front of verandah
1st step 1 23-10 ½ 2-0 0-6 23.88 cft 23.88 cft L 23-1½(0-4½) (0-4½) 23-10½
2nd step 1 23-10 ½ 1-0 0-6 11.94 cft 11.94 cft
Total 35.82 cft
G.Total 484.21 cft
795 1-1/2 thick P.C.C (124) in DPC including two coats of hot bitumen 2 layers of Polythene sheet Length Breadth same as for plinth wall
L1 2 23-10 ½ 0-9 - 17.9 sft 35.81 sft
S1 2 12-0 0-9 - 9.00 sft 18.00 sft
S2 1 12-0 0-4 ½ - 4.5 sft 4.50 sft
Verandah columns 3 0-9 0-9 - 0.56 sft 1.69 sft
Total 60.00 sft
Deduction of Door sills 1 4-0 0-9 - 3.00 sft 3.00 sft
1 4-0 0-4 ½ - 1.50 sft 1.50sft
Total 4.50 sft
Net Total 55.50 sft
806 Brick work in super structure using first class bricks in (14) cement sand mortar Length Breadth same as for plinth wall
L1 2 23-10 ½ 0-9 13-10 ½ 248.45 cft 496.90 cft H 12-0 (Room height) 0-4 ( Slab) 0-4 (Earth filling) 0-1(Mud plaster) 0-1½ (Tiles) 1-0 (P. wall) 13-10½
S1 2 12-0 0-9 13-10 ½ 124.87 cft 249.75 cft
S2 1 12-0 0-4½ 12-0 54.00 cft 54.00 cft No Parapet Walls
Verandah columns 3 0-9 0-9 8-6 4.78 cft 14.34 cft H10-0- (1-6)8-6
Verandah parapet walls
(i) L1 1 23-10 ½ 0-9 1-6 ½ 27.60 cft 27.60 cft H 0-4 (Earth filling) 0-1 (Mud plaster) 0-1½ (Tiles) 1-0 (P. walls) 1-6½
(ii) S3 2 7-3 0-9 1-6 ½ 8.38 cft 16.76 cft
Total 859.35 cft
81Deduction
Doors 1 4-0 0-9 7-0 21.00 cft 21.00 cft
1 4-0 0-4 ½ 7-0 10.5 cft 10.50 cft
Windows 3 4-0 0-9 4-0 12.00 cft 36.0 cft
Ventilators 4 2-6 0-9 1--6 2.81 cft 11.25 cft
Shelves 2 4-0 0-6 5-0 10.00 cft 20.00 cft
RCC lintels over
(i)doors 1 5-0 0-9 0-6 1.87 cft 1.87 cft
1 5-0 0-4 ½ 0-6 0.93 cft 0.93 cft
(ii)Windows 3 5-0 0-9 0-6 1.87 cft 5.62 cft
(iii)Ventilators 4 3-6 0-9 0-6 1.31 cft 5.25 cft
(iv)Shelves 2 5-0 0-9 0-6 1.87 cft 3.75 cft
Total 116.18 cft
Net Total 743.17 cft
827 Reinforced cement concrete (124) as in roof slab, lintels, columns, beams etc., (reinforcement will be measured separately) There is 4½ bearing of both slabs on all walls
Roof slab of rooms 1 23-1 ½ 12-9 0-4 98.28 cft 98.28 cft L 10-0 12-0 0-4½ 0-9 (2 bearings) 23-1½
B 12-0 0-4½(bearing) 0-4½(bearing) 12-9
Roof slab of Verandah 1 23-10 ½ 8-4 ½ 0-4 66.65 cft 66.65 cft B 8-0 0-4½ (bearing) 8-4½
Verandah beam
Long beam 1 23-1 0½ 0-9 1-6 26.86 cft 26.86 cft
Short beam 2 7-7 ½ 0-9 1-6 8.59 cft 17.18 cft L8-0-(0-9) (0-4½) 7-7½
83Lintels
Doors 1 5-0 0-9 0-6 1.87 cft 1.87 cft
1 5-0 0-4½ 0-6 0.93 cft 0.93 cft
Windows 3 5-0 0-9 0-6 1.87 cft 5.62 cft
Ventilators 4 3-6 0-9 0-6 1.31 cft 5.25 cft
Shelves 2 5-0 0-9 0-6 1.87 cft 3.75 cft
Shades 2 5-0 1-6 0-3 1.87 cft 3.75 cft
Total 226.39 cft
848 Mild steel round bars as reinforcement including cutting, bending, binding and placing reinforcement in position 6.75 lbs/cft steel of 226.39 cft concrete 1528.13 lbs
Total 1529.00 lbs
9 Roof insulation comprising of 2 coats of hot bitumen, 4 thick earth filling, 1 thick mud plaster and 1-1/2 thick brick tiles jointed and pointed in cement sand mortar (13)
Rooms (1 2) 1 22-4 ½ 12-0 - 268.50 sft 268.5 sft L 10-0 (12-0) (0-4½) 22- 4-½
Verandah 1 22-4 ½ 7-3 - 162.22 cft 162.22 cft B 8- 0- (0-9) 7-3
Total 430.72 sft
8510 Sand under floors
Room No.1 1 10-0 12-0 0-6 60.00 cft 60.00 cft
Room No.2 1 12-0 12-0 0-6 72.00 cft 72.00 cft
Verandah 1 22-4½ 7-3 0-6 81.11 cft 81.11 cft
Total 213.11 cft
11 Cement concrete (148) as under layer of floors
Room No.1 1 10-0 12-0 0-4 40.00 cft 40.00 cft
Room No.2 1 12-0 12-0 0-4 48.00 cft 48.00 cft
Verandah 1 22-4 ½ 7-3 0-4 54.07 cft 54.07 cft
Total 142.07 cft
8612 1-1/2 thick cement concrete (124) as top layer of floor, finished smooth
Room No.1 1 10-0 12-0 - 120.00 sft 120.00 sft
Room No.2 1 12-0 12-0 - 144.00 sft 144.00 sft
Verandah 1 23-10 ½ 8-0 - 191.00 sft 191.00 sft L 10-0 (12-0) (0-4 ½ ) (0-9) (0-9) 23-10 ½
Door sill 1 1 4-0 0-9 - 3.00 sft 3.00 sft
Door sill 1 1 4-0 0-4 ½ - 1.50sft 1.50sft
Total 459.5 sft
Deduction
Columns 3 0-9 0-9 - 0.56 sft 1.68sft
Net Total 457.80 sft
8713 ½ thick (13) cement sand plaster to walls finished smooth
Inner side
Room No.1 (Long wall) 2 12-0 - 12-0 144.00 sft 288.00 sft
Room No.1(Short wall) 2 10-0 - 12-0 120.00 sft 240.00 sft
Room No.1 (Ceiling) 1 10-0 - 12-0 120.00 sft 120.00 sft
Room No.2 (Long wall) 2 12-0 - 12-0 144.00 sft 288.00 sft
Room No.2(Short wall) 2 12-0 - 12-0 144.00 sft 288.00 sft
Room No.2 (Ceiling) 1 12-0 - 12-0 144.00 sft 144.00 sft
Verandah wall 1 23-10 ½ - 10-0 238.75 sft 238.75 sft L (10-0) (12-0) (0-4½ ) (0-9) (0-9) 23-10 ½
Verandah ceiling 1 22-4 ½ - 7 3 162.26 sft 162.26 sft L (10-0)(12-0) (0-4 ½ ) 22-½
Columns 3 3-0 - 8-6 25.50 sft 76.5 sft L (0-9) (0-9) (0-9) (0-9) 3-0
Long beam (internal side) 1 22-4 ½ - 1-6 33.55 sft 33.55 sft
Long beam (soffit) 2 10-9 ¾ - 0-9 8.10 sft 16.21 sft L(22-4 ½)-(0-9)/2 10-9¾
Short beam (internal sides) 2 7-3 - 1-6 10.87 sft 21.74 sft L(8-0)-(0-9) 7-3
Short beam (soffit) 2 7-3 - 0-9 5.43 sft 10.87 sft
88Door jambs 2 0-9 - 7-0 5.25 sft 10.50 sft
2 0-4½ - 7-0 2.63 sft 5.25 sft
1 0-9 - 4-0 3.0 sft 1.50 sft
1 0-4½ - 4-0 1.50 sft 3.00 sft
Window jambs 6 0-9 - 4-0 3.00 sft 18.00 sft
6 0-9 - 4-0 3.00 sft 18.00 sft
Ventilator jambs 8 0-9 - 2-6 1.88 sft 15.00 sft
8 0-9 - 1-6 1.19 sft 9.00 sft
Shelves 4 0-6 - 5-0 2.5 sft 10.00 sft
4 0-6 - 4-0 2.0 sft 8.00 sft
Outer side
Rear wall (From 6 below G.L. to Parapet walls) 1 23-10 ½ - 15-10½ 379.00 sft 379.00 sft H (0-6) (1-6) (12-0) (0-4) (0-4) (0-1) (0-1½) (1-0) 15-10½
Left Right side wall 2 13-6 - 15-10½ 214.32 sft 428.64 sft L (12-0) (0-9) (0-9) 13-6
Front side (above verandah roof) 1 23-10 ½ - 3-0 71.63 sft 71.63 sft H (12-0) 0-10½) (1-0) - (10-10 ½ ) 3-0
Left Right side plinth of verandah 2 8-0 - 2-0 16.00 sft 32.00 sft H (1 6) (0 6) 2 0
89Parapet wall
Inner side of rooms 2 22-4 ½ - 1-0 22.37 sft 44.70 sft L (10-0)(12-0)(0-4 ½ ) 22-4 ½
2 12-0 - 1-0 12.00 sft 24.00 sft
Inner side of Verandah 1 22-4 ½ - 1-0 22.37 sft 22.37 sft
2 7-3 - 1-0 7.25 sft 14.50 sft
Outer side of Verandah 1 23-10 ½ - 3- 4 ½ 67.66sft 67.66 sft H (1-6)(0-4)(0-6 ½) (1-0 ) 3-4 1/2//
2 8-0 - 2-10 22.67 sft 45.33 sft
Top of parapet wall (Rooms) 2 23-10 ½ - 0-9 17.9 sft 35.80 sft
2 12-0 - 0-9 9.00 sft 18.00 sft
Top of parapet wall (Verandah) 1 23-10 ½ - 0-9 17.90 sft 17.90 sft
2 7-3 - 0-9 5.43 sft 10.87 sft
90Steps
Tread 2 23-10 ½ - 1-0 23.87 sft 47.74 sft
Riser 3 23-10 ½ - 0-6 11.93 sft 35.80 sft
Sides 2 2 00 0-6 1.00 sft 2.00 sft
2 1 00 0-6 0.5 sft 1.00 sft
Total 3316.07 sft
Deduction
Doors 2 4-0 - 7-0 28.00 sft 56.00 sft
Windows 3 4-0 - 4-0 16.00 sft 48.00 sft
Ventilators 4 2-6 - 1-6 3.75 sft 15.00 sft
Total 119.00 sft
Net Total 3197.07 sft
9114 Wood work as in
(i) 1 ½ thick wooden doors with chowkat,. 2 4-0 - 7-0 28.00 sft 56.00 sft
Total 56.00 sft
(ii) Glazed and gauzed windows and ventilators. 3 4-0 - 4-0 16.00 sft 48.00 sft
4 2-6 - 1-6 3.75 sft 15.00 sft
Total 63.00 sft
G.Total 119.00 sft
15 Three coats of painting to doors , windows and ventilators - - - - - .(2 x Qty of item No.14) 238.0 sft
Total 238.00 sft
9216 Three coats of distempering/ white washing to walls (Internal Side)
Room No.1 (Long wall) 2 12-0 - 12-0 144.00 sft 288.00 sft
Room No.1 (Short wall) 2 10-0 - 12-0 120.00 sft 240.00 sft
Room No.1 (Ceiling) 1 10-0 - 12-0 120.00 sft 120.00 sft
Room No.2 (Long wall) 2 12-0 - 12-0 144.00 sft 288.00 sft
Room No.2 (Short wall) 2 12-0 - 12-0 144.00 sft 288.00 sft
Room No.2 (Ceiling) 1 12-0 - 12-0 144.00 sft 144.00 sft
Verandah wall 1 23-10 ½ - 10-0 238.75 sft 238.75 sft
Verandah Ceiling 1 22-4 ½ - 7 3 162.26 sft 162.26 sft
Columns 3 3-0 - 8-6 25.50 sft 76.50 sft
Long beam (sides) 1 22-4 ½ - 1-6 33.55 sft 33.55 sft
Long beam (soffit) 2 10-9 ¾ - 0-9 8.10 sft 16.21 sft L (22-4 ½)-(0-9)/2 10-9¾
Short beam (sides) 2 7-3 - 1-6 10.87 sft 21.74 sft
Short beam (soffit) 2 7-3 - 0-9 5.43 sft 10.87 sft
93Door jambs 2 0-9 - 7-0 5.25 sft 10.50 sft
2 0-4½ - 7-0 2.63 sft 5.25 sft
1 0-9 - 4-0 3.0 sft 1.50 sft
1 0-4½ - 4-0 1.50 sft 3.00 sft
Window jambs 6 0-9 - 4-0 3.00 sft 18.00 sft
6 0-9 - 4-0 3.00 sft 18.00 sft
Ventilator jambs 8 0-9 - 2-6 1.88 sft 15.00 sft
8 0-9 - 1-6 1.19 sft 9.00 sft
Shelves 4 0-6 - 5-0 2.5 sft 10.00 sft
4 0-6 - 4-0 2.0 sft 10.00 sft
Total 2017.16 sft
Deduction
Doors 4 4-0 - 7-0 28.00 sft 112.00 sft
Windows 4 4-0 - 4-0 16.00 sft 64.00 sft
Ventilators 6 2-6 - 1-6 3.75 sft 22.50 sft
Total 142.5 sft
Net Total 1874.66 sft
9417 Three coats of Weather shield paint to walls. (External side)
Rear wall 1 23-10 ½ - 15-4½ 367.07 sft 367.07 sft H (15-10 ½)-(0-6) 15-4 1/2
Left Right side wall 2 13-6 - 15-4½ 207.5 sft 415.13 sft
Front side (above verandah roof) 1 23-10½ - 3-0 71.63 sft 71.63 sft
Left Right side wall of verandah 2 8-0 - 2-0 16.00 sft 32.00 sft
Parapet wall
Inner side of rooms 2 22-4 ½ - 1-0 22.37 sft 44.70 sft
2 12-0 - 1-0 12.00 sft 24.00 sft
Inner side of Verandah 1 22-4 ½ - 1-0 22.37 sft 22.37 sft
2 7-3 - 1-0 7.25 sft 14.50 sft
Outer side of Verandah 1 23-10½ - 2-10½ 67.66 sft 67.66 sft
2 8-0 - 2-10½ 22.67 sft 45.32 sft
Top of parapet wall (Rooms) 2 23-10 ½ - 0-9 17.9 sft 35.80 sft
2 12-0 - 0-9 9.00 sft 18.00 sft
Top of parapet wall (Rooms) 1 23-10 ½ - 0-9 17.90 sft 17.90 sft
2 7-3 - 0-9 5.43 sft 10.87 sft
Total 1186.95 sft
95Deduction
Windows 2 4-0 - 4-0 16.00 sft 32.00 sft
Ventilators 2 2-6 - 1-6 3.75 sft 7.50 sft
Total 39.50 sft
Net Total 1147.45 sft
96ABSTRACT OF QUANTITIES
971- CALCULATIONS
1. Excavation in Medium soil
Quantity from BOQ item No. 1 Output of one labourer working 8 hrs 04 labourers are required for 3 ½ days to excavate 1050 cft earth. 1024.52 cft 75 cft
982. PCC (148)
Quantity of BOQ item No.3 (Foundations) 146.27 cft
Quantity of BOQ item No.11 (Floors) 142.07 cft
Total 288.34 cft
Note Dry material for 100 cft of cement concrete 154 cft
Materials
(i) Cement154x1x288.34/(100x13) 34.15cft
(ii) Sand154x4x288.34/(100x13) 136.62 cft
(iii) Coarse aggregate 154x8x288.34/(100x13) 273.25 cft
993. Ist Class Burnt brick work in foundation in cement sand mortar (16)
Quantity of BOQ item No.4 484.21 cft
Note Bricks for 100 cft of brick work 1350 Nos.
Dry mortar for 100 cft of brik work 30 cft
Material
(i) Bricks1350x484.21/100 6537 Nos.
(ii) Cement30x1x484.21/(7x100) 20.75 cft
(iii) Sand30x6x484.21/(7x100) 124.51cft
1004. 1 ½ thick PCC (124) in DPC including two coats of hot bitumen 2 sheets of Polythene.
Quantity of BOQ item No.555.50x0.125 6.93 cft
Note (i) Dry material for 100 cft of cement concrete 154 cft
(ii) Bitumen for 100 sft of DPC (first coat) 15 Kg
(iii) Bitumen for 100 sft of DPC (second coat) 10 Kg
Material
(i) Cement154x1x6.93/(100x7) 1.52 cft
(ii) Sand154x2x6.93/(100x7) 3.04 cft
(iii) Coarse aggregate154x4x6.93/(100x7) 6.09 cft
(iv) Bitumen 25x55.50/100 13.87 Kg
(v) Polythene Sheet (2 x 55.5) 111.0 sft
1015. Ist Class Burnt brick work in Super structure in cement sand mortar (14)
Quantity of BOQ item No.6 743.17 cft
Note (i) Bricks for 100 cft of brick work 1350 Nos.
(ii) Dry mortar for 100 cft of brik work 30 cft
Material
(i) Bricks1350x743.17/100 10033 Nos.
(ii) Cement30x1x743.17/(5x100) 44.59 cft
(iii) Sand30x4x747.13/(5x100) 178.36 cft
1026. Reinforced cement concrete (124)
Quantity of BOQ item No.7 226.39 cft
Note Dry material for 100 cft of cement concrete 154 cft
Materials
(i) Cement154x1x226.39/(100x7) 49.80 cft
(ii) Sand154x2x226.39/(100x7) 99.61 cft
(iii) Coarse aggregate 154x4x226.39/(100x7) 199.22 cft
(Note (iv) Mild steel round bars 1 Kg 0.454 lbs) 1529 lbs 693.55 Kg
1037. Roof insulation
Quantity of BOQ item No.9 430.72 sft
Note (i) Brick tiles for 100 sft roof insulation 360 Nos.
(ii) Dry mortar for 100 sft 9.00 cft
(iii) Bitumen for 100 sft of DPC (first coat) 15 Kg
(iv) Bitumen for 100 sft of DPC (second coat) 10 Kg
Material
(i) 1 ½ thick brick tiles 1551 Nos.
(ii) Cement9x1x430.72/(4x100) 9.69 cft
(iii) Sand9x4x430.72/(4x100) 29.07 cft
(iv) Bitumen 430.72/100 107.68 Kg
(v) Mud /Earth filling430.72x0.42 180.90 cft
(Vi) Polythene sheet (2 x 430.72) 862 sft
1048. Sand under floors
Quantity of BOQ item No.10 213.11 cft
Material
Sand 213.11 cft
9. 1 ½ thick cement concrete (124) in floors
Quantity of BOQ item No.12457.80x0.125 57.23 cft
Note (i) 1 ½ 0.125 ft (ii) Dry material for 100 cft of cement concrete 154 cft
Materials
(i) Cement154x1x57.23/(100x7) 12.59 cft
(ii) Sand154x2x57.23/(100x7) 25.18 cft
(iii) Coarse aggregate 154x4x57.23/(100x7) 50.36 cft
10510. 1/2 thick cement plaster in cement sand mortar (13)
Quantity of BOQ item No.13 3197.07 sft
Note Dry mortar for 100 sft of ½ thick cement plaster 6 cft
Material
(i) Cement6x1x 3197.07/(4x100) 47.96 cft
(ii) Sand6x3x 3197.07/(4x100) 143.87 cft
11. Wood work in door, windows ventilators
Quantity of BOQ item No.14 (i) Doors 56.00 sft
Quantity of BOQ item No.14 (ii) Windows 63.00 sft
Note (i) Timber for 100 sft of Panelled Doors 13 cft
(ii) Timber for 100 sft of Glazed windows and Ventilators 8 cft
Material
(i) Timber for doors 13x56/100 7.28 cft
(ii) Timber for windows and Ventilators 8x63/100 5.04 cft
Total 13.32 cft
10612. White wash / Distemper
Quantity of BOQ item No.16 1872.9 sft
Note Lime for 100 sft of white wash (one coat) 1.00 Kg
Material
Lime for three coats1x3x1872.9/100 56.24 Kg
13. Weather Shield
Quantity of BOQ item No.17 1143.45 sft
14. Earth filling under floors
Quantity of BOQ item No.2 230.87 cft
Material
Earth for filling 230.87 cft
1072- SUMMARY
S.No. Description of material Quantity
1. Cement (From 2,3,4,5,6,7,9,10) 220.68 cft or 177 Bags
2. Sand (From 2,3,4,5,6,7,9,10) 740.26 cft
3. Coarse aggregate (From 2,4,6,9) 528.92 cft
4. Mild steel round bars (item No 6) 693.55 Kg
5 Burnt bricks 1st class (From 3,5) 16570 Nos.
6 1/2 thick Brick tiles (item No 7) 1551 Nos.
7 Bitumen (From 4,7) 121.55 Kg
8 Polythene sheet (From 4,7) 973 sft
9. Timber (item No 11) 13.32 cft
10. Lime (item No 12) 56.24 Kg
11. Mud/Earth filling (From 7,13) 411.77 cft