Title: BSM Product Assurance Plan Team Briefing
1BSM Product Assurance PlanTeam BriefingPA
plan roll-out
2Overview
- The BSM is a high reliability precision cryogenic
mechanism - PA plan goal is to provide
- traceability and assurance to the customer
- specific assurance that the product is fit for
purpose in the space environment. - the Acceptance Data Package (ADP)
- Reduced cost!
3Quality Assurance at the UK ATC
- UK ATC mission
- be the UK's National Centre for the design and
production of state of the art astronomical
technology". - Quality management (ATC PM procedures)
- ... is the process of ensuring that the quality
expected by the customer is achieved....All work
packages must be traceable back to the customer
requirements to ensure that they are met. - General ATC practice,
- project engineers responsible for the quality of
their work - supervisory aspects covered by the relevant Head
of Specialism. - The Chief Engineer is responsible for approving
the overall quality of the products delivered to
customers. - For the SPIRE BSM
- a Product Assurance Manager is designated
- to ensure that the unique quality aspects of
space flight projects are fully met.
4BSM PA - People
5BSM PA Plan Contents
- ATC QUALITY ASSURANCE
- PROCUREMENT CONTROL
- MANUFACTURING AND ASSEMBLY CONTROL
- NON-CONFORMANCE PROCESS
- PRODUCT ASSURANCE MANAGEMENT
- GENERAL
- DESIGN QUALITY ASSURANCE
- CONFIGURATION MANAGEMENT AND CONTROL
- MATERIAL AND PROCESS SELECTION AND CONTROL
- ELECTRONIC PARTS SELECTION AND CONTROL
- CLEANLINESS AND CONTAMINATION CONTROL
- SOFTWARE PRODUCT ASSURANCE
- RELIABILITY ASSURANCE
- INTEGRATION AND TEST CONTROL
- ACCEPTANCE AND DELIVERY
6Applicability of PA to the BSM models
A Applicable P Partially Applicable N
Non-Applicable
7Key to PA applicability table
- 1. Space rated parts are not required, but
performance should be equivalent (e.g. Mil-Spec) - 2. Applied via LAM
- 3. Applicable for components coming into direct
contact with flight standard hardware (e.g.
interfacing connectors from GSE cables). - 4. Applicable to elements directly interfacing
with the flight hardware, when an impact on the
flight hardware is possible. - 5. Applicable to all activities related to design
verification
8PA plan roll-out
- What
- 2 axis Prototype
- data,
- build,
- fault logging
- Development Model
- Design
- Manufacture
- Assembly
- Test
- When
- starts now
- Why
- it will take us 3 months to get it right
- we need to fine tune the PA plan
- we may want to re-use some DM bits on the STM or
CQM
- How
- PA reviewed monthly
- Produce all logs etc
- apply as we go.
9Design Documentation
10DESIGN QUALITY ASSURANCE
- PA during design
- Verifying the presence of all necessary inputs,
- Safety and reliability studies,
- The formalization of the functional analysis,
- Verifying interactivity between
mechanical-electrical and software design, - Verifying the presence and compliance of "latest
design" files and documents. - Controlled documents
- Design Description
- Specification
- ICDs
- PA Plan, Development Plan
- Mechanical Electrical Design Drawings/Models
- Analysis Reports
11Documentation control
- Q-Pulse
- New ATC doc management system
- used on VISTA, SPIRE, others
- ATC SPIRE documents are migrating to it now.
- Will also use it for NCRs
- Intralink
- for models and drawings
- Livelink
- for SPIRE project office consortium files
- Bug-track
- Fault logging during lab work
12(No Transcript)
13(No Transcript)
14(No Transcript)
15MATERIAL AND PROCESS SELECTION AND CONTROL
- Material and process controls implemented
- Space approved materials selected
- Proven cryogenic heritage
- Declared Lists
- Materials
- Parts
- Processes
- .all finalized by the IBDR Nov/Dec.01
16ELECTRONIC PARTS SELECTION AND CONTROL
- Warm Electronics
- Responsibility divided between ATC LAM,
- ATCs bits - Cold Electronics
- Motors,
- Zeiss/PACS
- Sensors
- Infineon (ISOPhot)
- up-screen PAD
- Launch Latch
- LAM/SMEC
- Harness
- approved wiring
- RAL supply?
- In-house solder repair - trained personnel
17Part Approval Document (PAD Sheet)
18RELIABILITY ASSURANCE
- Reliability Block Diagram
- Single Point Failures
- FMEA/FMECA
- Cumulative Operating Time (Log!)
- Environmental Assurance
- Environmental Testing
- Critical Items Identification and Control (Log!)
- may include flex pivots
- may include sensor bonded assemblies
19Procurement Manufacture
20PROCUREMENT CONTROL
- Traceable Purchase Orders (PPARC FMs)
- Supplier Selection
- Incoming Inspection Report
- verification of the packaging conditions
- visual inspection,
- conformance to ordering data,
- certificate of conformance,
- supplier's inspections and control results,
- remaining lifetime (for products with limited
lifetimes). - Quarantine Bonded Store
- until released (inspection OK)
21MANUFACTURING AND ASSEMBLY CONTROL
- Manufacturing Request
- Route Card
- Serial Number identification (S/N book)
- Inspection Reports
- Operator Inspection
- Independent Inspection as required
- External attendance at MIP/KIPs if required
- Bonded Store
- Assembly Control Logs
22Manufacturing Documents
Request
Inspection Record
Material Certificates,
Process Records,
23NON-CONFORMANCE PROCESS
- Identify a Non-Conformance
- Quarantine component
- Raise NCR
- NCR review
- Responsible engineer, PA manager others
- Classification (major/minor)
- Disposition
- Report
- Close Out
24NCR management - enter details of CA.
25Non Conformance Report
- Raise using Q-Pulse
- Review
- investigate and close out each NCR,
- recommendation for disposition and corrective
action - NCR register reviewed at BSM project meetings,
- NCR review panel
- the responsible engineer identified on the
Workshop Effort Request, - the BSM PA manager
- the member of staff raising the NCR.
- Additional staff as required. UK-SPO and/or ESA
for major NCRs. - Disposition as
- 'Use as is', with/without requirement for waiver
- 'Re-work or Repair', with attached repair
instructions. - 'Scrap'
- Corrective action
- documented and circulated to the relevant HoS.
26Assembly Test
27CLEANLINESS AND CONTAMINATION CONTROL
- Clean Room assembly
- Class 1000 cleanroom
- Class 100 air-bench
- Bakeout
- 80degC
- Transfer from clean room to test dewar
- Limit exposure time
- clean up CCD lab!!
- Bag/purge/cover
- Test Dewar
- cleanliness enforced (semi-clean area)
- Storage
- Dry Nitrogen purge of storage containers
28Cleanliness Certificate
29INTEGRATION AND TEST CONTROL
- Assembly, Integration and Test
- Test Procedures
- Test Witnessing
- Test Reports
- Fault Logging (bug-track)
- Historical Record (Logbook)
- Handling, Storage, Packaging, Marking and
Labeling, Transportation
30Assembly Log
31Mate/ De-mate Log
32Acceptance data pack
- Shipping Documents
- Procedures for Transport Handling Installation
- Certificate of Conformance/Delivery Review board
MOM AI Lists - Qualification Status/Test Matrix
- Top Level Drawings incl... Family Tree
- Interface Drawings
- Functional Diagrams (Block Diagram)
- Electrical Circuit Diagrams
- As built configuration lists
- Serialized Components List
- List of Waivers
- Copies of Waivers
- Operation Manual
- Historical Record
- Logbook/Diary of Events
- Operating Time/Cycle Record
- Connector Mating Record
- Test Record
- Calibration Data record
- Temporary Installation Record
- Open Work / Deferred Work / Open Tests
- List of Non-Conformance reports (NCR's)
- Copies of Non-Conformance reports (NCR's)
- Test Reports
- Mass records / Power Budgets
- Cleanliness Statement
- Compliance Matrix
- Photographs
33PA Plan Summary
- PA Plan Goal Fitness for purpose
- Purpose
- Reliable cryogenic high precision mechanism
- Space qualified
- Integrated to a 10M instrument
- Method
- Rigorous Design
- Configuration Control
- Traceable Materials, Parts, Documents
- Fully documented clean room assembly
- Non-conformances design changes, raised
tracked - Qualification Programme backs the design
- ADP demonstrated fitness for purpose