Using Earned Value Analysis by Alan Bye - PowerPoint PPT Presentation

1 / 49
About This Presentation
Title:

Using Earned Value Analysis by Alan Bye

Description:

Using Earned Value Analysis by Alan Bye Activities do not always last for a reporting period (week, month etc) Some activities do not deliver anything, e.g ... – PowerPoint PPT presentation

Number of Views:191
Avg rating:3.0/5.0
Slides: 50
Provided by: AlanL179
Category:

less

Transcript and Presenter's Notes

Title: Using Earned Value Analysis by Alan Bye


1
Using Earned Value Analysisby Alan Bye
2
Earned Value
Why Do I Need It ? What Is It ? How Do I Do
It?
3
Todays Situation
  • Need for accurate and consistent status
    information
  • Numerous complex (and interrelated) projects
  • Projects with many WBS activities
  • Virtual offices
  • Diverse technology platforms

4
Theres Room For Improvement
  • 70 of projects are
  • Over budget
  • Behind schedule
  • 52 of all projects finish at 189 of their
    initial budget
  • And some, after huge investments of time and
    money, are simply never complete
  • SourceThe Standish Group

5
Earned Value Analysis (EVA)
  • Earned Value Analysis is
  • an industry standard way to
  • measure a projects progress where direct
    measures cannot be used
  • Predict future performance, and
  • provide schedule and budget variances along the
    way
  • By integrating three measurements, it provides
    consistent, numerical indicators with which you
    can evaluate and compare projects.

6
EVA the three elements
  • It compares the PLANNED amount of work with what
    has actually been COMPLETED, to determine if Cost
    , Schedule, and Work accomplished are progressing
    as planned.
  • Work is Earned or credited as it is completed.

7
Earned Value is needed because...
  • Provides an Early Warning signal for prompt
    corrective action.
  • Bad news does not age well.
  • Still time to recover
  • Timely request for additional funds

8
Earned Value Management EVolution
  • 1959 US DoD began looking at Milestone
    Charts and Rate of Expenditure
  • Curves.
  • 1963-64 Earned Value concept begins with the
    Minuteman Titan III
  • rocket programmes.
  • 1966 USAF - Cost/Schedule Planning
    Control Specification (C/SPCS).
  • 1967 US DoD - Cost/Schedule Control
    Systems Criteria (CSCS2).
  • 1972 US DoD - Issued the Joint
    Implementation Guide (JIG).
  • (revisions were to follow
    1976, 1980, 1987 and 1996).
  • 1972 NASA
  • 1975 US Dept of Environment (DoE)
  • 1982 US National Security Agency
  • 1989 Australian DoD
  • 1990 Canadian DoD
  • 1992 National Oceanic Atmospheric
    Administration (NOAA)
  • 1994 Federal Bureau of Investigation
    (FBI), Inland Revenue Service (IRS)
  • 1996 JIG replaced by Earned Value
    Management Implementation Guide (EVMIG)
  • (revised 1997)
  • Present World wide implementations.USA,
    Europe, Canada, Australia, Japan

9
Traditional Plan vs. Actual view
  • Is there a performance problem? Is it a good or
    bad position?

10
Terminology
  • BCWS - Budgeted Cost of Work Scheduled
  • ACWP - Actual Cost of Work Performed
  • BCWP - Budgeted Cost of Work Performed

11
Earned Value Definitions
  • BCWS Budgeted Cost of Work Scheduled
  • The planned earned value to be performed by the
    milestone date.

12
Earned Value Definitions (cont.)
  • ACWP Actual Cost of Work Performed
  • Actual Cost to date.

13
Earned Value Definitions (cont.)
  • BCWP Budgeted Cost of Work Performed
  • The actual earned value i.e. the value of the
    work performed based on its planned value

14
How to construct the baseline (BCWS) (planned
earned value)
  • Establish the activities (milestones)
  • Calculate a budget for each activity (milestone).
    What is the cost of completing the activity?
  • Ideally one activity (milestone) per reporting
    period
  • In a table, record the cumulative budget for each
    milestone and draw the graph

15
How to construct the baseline (BCWS)
16
How to score the Earned Value (BCWP) (actual
earned value)
  • When an activity (milestone) is achieved, the
    Earned Value (EV) is scored equal to its planned
    value
  • It has nothing to do with how much you get paid
  • The EV is scored in the period in which it was
    completed

17
How to score the EV (BCWP)
18
How to record Actual Cost (ACWP)
  • Actual cost of doing the work
  • This may be recorded for each activity
    (milestone). This is the ideal situation, but
    you may only have information relating to actual
    cost for the entire project. This is also
    acceptable
  • You may be accumulating an actual cost in a
    period prior to the activity is delivered.

19
How to record Actual Cost (ACWP)
20
Graphical representation of project progress
Budget At Completion (BAC)

Planned Costs (BCWS)
Actual Costs (ACWP)
Earned Value (BCWP)
Time
Today
21
  • Exercise
  • Describe the status of each project using EV
    terminology
  • 10 minutes

22
As at today, the value of the work is less than
planned, therefore we are behind schedule. The
actual cost of work is greater than plan and also
greater than the BCWP. Therefore we have been
doing the work considerably more costly than
planned.
23
As at today, the value of the work is greater
than planned value, therefore we are ahead of
schedule. The actual cost of work is greater
than plan but less than the BCWP. Therefore
despite having spent more money than plan, on the
work we have completed, we are doing it cheaper
than the plan.
As at today, the value of the work is greater
than planned value, therefore we are ahead of
schedule. The actual cost of work is greater
than plan and also greater than the the BCWP.
Therefore as well as spending more money than
planned, we are overspent on the work that we
have completed.
24
As at today, the value of the work is less than
planned value, therefore we are behind schedule.
The actual cost of work is less than plan but is
greater than the BCWP. Therefore despite having
spent less than the plan, on the work that we
have done we are overspending
As at today, the value of the work is less than
planned value, therefore we are behind schedule.
The actual cost of work is less than plan and
also less than the BCWP. Therefore as well as
being under the planned expenditure, we are also
doing the work cheaper than the plan
25
Some Derived Metrics
  • SV Schedule Variance (BCWP - BCWS)
  • A comparison of the amount of work performed to
    what was planned to be performed.
  • A negative variance means the project is behind
    schedule
  • CV Cost Variance (BCWP - ACWP)
  • A comparison of the budgeted cost of work
    performed with actual cost.
  • A negative variance means the project is over
    budget.

26
Some More Derived Metrics
  • SPI Schedule Performance Index SPI BCWP /
    BCWS
  • SPI lt 1 means project is behind schedule
  • CPI Cost Performance Index CPI BCWP/ACWP
  • CPI lt 1 means project is over budget

27
  • Cost indices and variances
  • Cost Performance Index (CPI) BCWP
  • ACWP
  • Cost Variance (CV) BCWP - ACWP
  • Cost Variance (CV) CV x 100
  • BCWP
  • Schedule indices and variances
  • Schedule Variance (SV) BCWP - BCWS
  • Schedule Performance Index (SPI) BCWP
  • BCWS
  • Schedule Variance (SV) SV x 100

28
Graphical representation of project progress
Budget At Completion (BAC)

Planned Costs (BCWS)
Schedule slippage (time)
Cost Variance ()
Actual Costs (ACWP)
Schedule Variance ()
Earned Value (BCWP)
Time
Today
29
Making Projections
Once a project is 10 complete, the overrun at
completion will not be less than the current
overrun. Once a project is 20 complete, the CPI
does not vary from its current value by more than
10. The CPI and SPI are statistically accurate
indicators of final cost results. Source
Defense Acquisition University
30
Estimate At Completion (EAC)
  • Formula 1 BAC
  • CPI
  • Considered to give a minimum EAC
  • Formula 2 BAC
  • CPI x SPI
  • Provides an EAC that accounts for a schedule
    change
  • Formula 3 ACWP BAC BCWP
  • CPI
    x SPI
  • Provides an EAC that accounts for a schedule
    change, but also takes
  • into account the value of the work done



31
Graphical representation of project progress
Estimate At Completion (EAC)
Variance at Completion
Budget At Completion (BAC)

Planned Costs (BCWS)
Schedule slippage (time)
Forecast schedule slippage
Cost Variance ()
Actual Costs (ACWP)
Schedule Variance ()
Earned Value (BCWP)
Time
Today
32
Basic Analysis
33
  • Exercise
  • 1. Read the worked example
  • Do the Earned Value exercise
  • 1 hour

34
Now the real world!
  • Activities do not always last for a reporting
    period (week, month etc)
  • Some activities do not deliver anything, e.g.
    management support, but it still a cost to the
    project

35
Activities do not always last for a reporting
period What can be done?
  • Use an Earned Value Method of 50/50
  • When constructing the BCWS (the plan), you put
    50 of the activity (as a BCWS value) in the
    period the activity is planned to start and the
    remaining 50 in the period when the activity is
    planned to finish.
  • The BCWP (Earned Value) is earnt in the same
    proportions, i.e. 50 when the activity starts
    and 50 when the activity finishes

36
EV Methods Internal resource
37
EV Methods Material/vendor
38
Some activities do not deliver anything - What
can be done?
  • Use an Earned Value Method called Level of Effort
  • When constructing the BCWS (the plan), spread the
    activity value evenly throughout the duration
  • The BCWP (Earned Value) is earnt in the same
    proportion to the plan regardless of whether any
    time has been spent on the activity or not
  • BCWP BCWS therefore SPI 1.0 and SV 0 It
    shows that we are always on schedule for this
    type of activity

39
EVMS / EVM / EV / EVA
  • Earned Value Management System
  • The executive Cost and Schedule system employed
  • Can be a single system or many that are working
    together
  • Earned Value Management
  • Active management of a programme using EV
    processes EVA
  • Earned Value Methods
  • Metric selected to provide best possible
    reflection of Schedule performance
  • Typically 0-100, 20-80, 50-50, 40-60,
    Estimates, Milestones, Apportioned,
  • Level of Effort
  • Earned Value
  • Budgeted Cost of Work PerformedBCWP
  • Executed tasks within a baseline having been
    completed in line with exit criteria
  • Earned Value Analysis
  • Variance Analysis of - Current month, Cumulative
    to Date, and VAC
  • EAC Analysis in terms of TCPI(EAC) / Independent
    EACs if warranted

40
Key EVMS Components
  • Authorisation
  • Planning Budgeting
  • Baseline Change Control
  • Analysis
  • Reporting

41
Authorisation
  • Control Account Authorisation CAA
  • Total Allocated Budget (TAB) flow-down to
    reporting WBS
  • Details initial Baseline distribution of Budget
  • Provides a narrative (and/or) points to
    additional documentation detailing deliverables
  • Indicates open duration of Control Account
  • Details specific schedule adherence
  • Signed off by both Programme Manager and
    Control Account Manager
  • Usually a one-time eventfuture budget
    transactions being dealt with by PCRs

42
Planning and Budgeting
  • Total Planning or Rolling Wave Planning
  • Vertical Horizontal Integration with
    Milestones, especially if a Critical Path is
    required
  • Resource allocation and management
  • Management Reserve (in-scope arisings)
  • Undistributed Budget (WBS earmarked budget)
  • Earned Value Method (EVM) selection
  • TAB (DB UB MR)
  • Where (DBUBMR) gtTAB Over Target Baseline !

43
Baseline Control
  • Baseline Change Control is performed using
    Programme Change Requests (PCRs)
  • Baseline distribution Contract Budget Base (CBB
    Log)
  • Change Control (Rubber Baseline mitigation)
    performed by the usage of PCRs
  • PCRs authorise both BAC/EAC and pure EAC
    changes
  • An understanding of MR v EAC is required !
  • PCRs are signed-off by Programme Managers

44
Analysis
  • Performance Current Month, CTD, and Variance at
    Completion
  • History SV, SPI, CV, CPI
  • Current Management Reserve level predicted
    Burn-Down
  • Programme flexibility MR versus VAC delta
  • Staffing..Equivalent Heads versus Forecast
  • Milestones.future forecasted dates versus
    requirements (Exec, MWP, Programmatic)
  • Variance Analysis Reports (VARs) and Corrective
    Actions
  • Future TCPI(EAC) and Trending

History
45
Variance Analysis Report (VAR)
  • Thresholds
  • Fixed at Baseline
  • Current month SV CV
  • Cumulative SV CV
  • VAC
  • CAM reports
  • Cause of variance
  • Impact to Cost Schedule
  • Corrective Actions
  • VARs
  • Discussed at MPRs
  • Agreed and signed by PM/PL
  • Corrective Actions
  • Reviewed at subsequent MPRs

46
Reporting
47
Shortcomings of Earned Value
  • Quantifying / measuring work progress can be
    difficult.
  • Time required for data input, data gathering and
    calculation
  • It is not the only way to manage a project

48
Summary
  • Use indicators to manage your project and not to
    be a goal in itself. They will drive a
    behaviour.
  • EV data is historical. Use it to predict and
    influence the future
  • Look at Indices and Variances together and
    observe trends
  • Concentrate on the parts of the project that
    trip the variances
  • Not all projects are the same, i.e. do not expect
    the same sort of variances and indices on a
    technically challenging/risky project compared
    with more straight forward projects
  • For EVA to be effective, it requires a credible
    baselined plan.

49
Thank you and any questions?
Write a Comment
User Comments (0)
About PowerShow.com