Lessons Learned on Costing, Prioritization and Operationalisation : PRSPs and MDGs - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Lessons Learned on Costing, Prioritization and Operationalisation : PRSPs and MDGs

Description:

Lessons Learned on Costing, Prioritization and Operationalisation : PRSPs and MDGs Raj Nallari, World Bank Institute, PREM Antoine Heuty, UNDP New York – PowerPoint PPT presentation

Number of Views:166
Avg rating:3.0/5.0
Slides: 24
Provided by: Antoi170
Category:

less

Transcript and Presenter's Notes

Title: Lessons Learned on Costing, Prioritization and Operationalisation : PRSPs and MDGs


1
Lessons Learned on Costing, Prioritization and
Operationalisation PRSPs and MDGs
  • Raj Nallari, World Bank Institute, PREM
  • Antoine Heuty, UNDP New York
  • Vientiane, October 20th, 2004

2
Outline
  • I/ Rationale for costing and Prioritization
  • II/Approaches to Costing
  • III/ The PRSP Experience
  • IV/ Costing the MDGs

3
I/ Rationale for costing and Prioritization
4
Rationale for cost estimates
  • Strategic choice for achieving NGPES-MDG goals
    may be helpful in answering two kinds of
    questions
  • Should an end be pursued ?
  • The feasibility of achieving NGPES-MDG goals,
    given a sufficient application of resources and
    adequate policy and institutional reform , is not
    generally in doubt.
  • However , the discussion implicitly supposes
    that the commitment to achieving the objectives
    is not unconditional.
  • An implicit rationale In the MDGs context,
    convincing developing countries and donors that
    the goals can be achieved without undue sacrifice
    of other objectives.
  • How should an end best be pursued?
  • Budgetary Planning needs, gaps, stickiness
    (irreversibilities, cost of planning).
  • What is the most cost efficient approach to
    achieving the development objectives?

5
Objectives of NGPES Costing
  • To estimate the needed financial resources to
    implement the planned interventions of NGPES.
  • To inform budget preparation and lay out
    tradeoffs for policy-makers.
  • To present alternative scenarios to Laos
    Government in order to identify policy and
    financing options to identify the appropriate
    strategy to reach NGPES-MDG goals

6
Why costing prioritization matters?
  • Lack of prioritization wish list
  • Wish lists are not credible, not likely to be
    implemented, and are likely to disappoint
    domestic stakeholders
  • Wish lists are also less likely to attract
    external financing in the form of budget support
  • Uncosted programs will not receive adequate or
    predictable budgetary allocations, overall or
    appropriate capital/ recurrent mix. And if no
    costing, prioritization is impossible.
  • Prioritization depends on
  • Comprehensive analysis of policy options
  • Good costing
  • Knowledge of aggregate resource envelope
  • Feedback from participatory processes
  • While costing is technical in nature,
    prioritization is a political process which needs
    to be owned and driven by government and
    decision-makers

7
II/Approaches to Costing
8
Which approach for costing NGPES?
  • Costing of NGPES should be done on short and
    medium term but consistent with Laos PDR long
    term development vision
  • This approach needs to balance the focus on
    ambitious development goals and the constraints
    imposed by the macroeconomic framework
  • OBJECTIVE An iterative approach reconciling
    resource requirements assessments based on sector
    or program analysis and resource availability
    based on econometric estimation of growth and
    resource envelope

(3) OPERATIONALIZATION
(1) COSTING - Resource requirement -
Resource availability
9
What does prioritization mean?
  • Prioritization is needed in both the choices of
    policy measures and budget allocations consistent
    with the achievement of NGPES goals.
  • Prioritization implies
  • Analyzing all available policy options in order
    to achieve NGPES goals
  • Limitingand sequencingthe set of policy
    measures to those which can most likely be
    achieved, given human resource and political
    constraints, over the time horizon of the
    strategy.
  • Prioritization leads to
  • Identifying resource gap and assessing of
    potential adaptation of macroeconomic framework
    (foreign assistance, tax reform, borrowing)
  • Recognizing budget constraints, understanding of
    costs and a willingness to reallocate budgets
    from lower priority to higher priority sectors
    and sub-sectors.

10
Prioritization in practice
  • Compare resource needs with resource availability
    to identify resource gap
  • Assess budget constraints based on the aggregate
    resource envelope, including both domestic and
    external funds
  • Information from donors by sector
  • Scope for increasing resource mobilization (ODA,
    taxation, borrowing)
  • Base case should be that considered most likely
  • Alternative scenarios needed in cases of higher
    or lower than expected growth, external flows,
    etc.

11
III/ The PRSP Experience
12
PRSP-Sector Programs-Budget
  • Budget as a key development tool and
  • governance issue
  • Why is budget process important?
  • In formulation phase - determines resource
    envelope
  • - allocates to
    priority policy areas
  • In execution phase - releases funds to the
    service delivery agencies, predictably
  • In reporting phase - accounts for how the
    funds have been used

13
Short-term measures to improve public financial
management
  • In selected Ministries that are ready to move
    ahead
  • adoption of an integrated Financial Management
    System, or
  • improved manual procedures for recording
    spending, and/or
  • Public Expenditure Tracking Surveys
  • Improved budget classification systems
  • Several PRSPs have proposed revising the budget
    classification system in order to allow more
    meaningful targeting and monitoring of public
    expenditure
  • Strengthening Treasury operations to ensure more
    timely release of funds and better reporting of
    expenditure
  • Publication of quarterly or semi-annual budget
    execution reports
  • Placing programming and execution of
    foreign-financed capital expenditure on budget
  • ensuring full recording of externally financed
    project expenditures in the governments accounts
  • Strengthening control institutions such as
    Comptroller General

14
MTEF
STAGE CHARACTERISTICS
Development of Macroeconomic Framework Macroeconomic model that projects revenues and expenditure in medium term
Development of Sectoral Programs Agreement on sector objectives, outputs, and activities Review and development of programs and sub-programs Program cost estimation
Development of Strategic Expenditure Framework Analysis of inter- and intra-sectoral trade-offs Consensus-building on strategic resource allocation
Definition of Sector Resource Allocations Setting medium term sector budget ceilings
Preparation of Sectoral Budgets Medium term sectoral programs based on budget ceilings
Political Approval Presentation of budget estimates to cabinet and parliament for approval
15
A good country case
  • Consensus on priorities built through the
    participatory process, built on ongoing programs.
    Lower priority activities dropped/scaled down
  • ComprehensiveCritical to the success of the PRSP
    is the need to implement only the PRSP
  • PRSP-budget link is central Budget preparation
    scrutiny by MOF to ensure that line agency budget
    submissions are consistent with the PRSP
  • Transition phase for donor activities
  • Existing projects grand fathered
  • All new projects must fit within PRSP priorities
  • Annual review vehicles, envisaged as countrys
    central policy review process
  • PER expenditures impacts
  • PRSP review (annual progress report) complemented
    by a comprehensive review every three years

16
  • Need for patience and perseverance
  • Prioritisation and costing will likely need
    continuing improvement in the context of
    implementation and monitoring of the first PRSP
  • Prioritization and costing will only be possible
    if the PRSP is linked to the budget process
  • MTEF can be valuable
  • The MTEF should not be a parallel exercise, but
    integrated with existing budget processes
  • the institutional arrangements for the MTEF
    PRSP should be consistent in both exercises, and
    recognize the central role of Ministry of Finance
  • Phasing-in of MTEF, by sector and functions,
    needed

17
IV/ Costing the MDGs
18
Global estimates
  • Zedillo Report The cost of achieving the 2015
    goals would probably be on the order of an extra
    50 billion a year.
  • The Banks initial estimates of the cost (to
    donors) of achieving Goal 1 range between US 54
    billion and 62 billion a year. Its estimates
    of the cost of achieving the goal depend on ad
    hoc assumptions concerning, poverty elasticities
    of income, capital-output ratios, national
    savings rates, and absorption constraints.
  • The Bank estimates the total cost of achieving
    the other goals (by adding existing sectoral
    estimates, as does the Zedillo commission) as
    ranging between US 35 and 76 billion per
    year.

19
MDG needs assessment at the country level
  • UNDP country offices have participated in a pilot
    project which has attempted to estimate the cost
    of attaining the MDGs in six countries. The
    reports focused on six MDG targets income
    poverty, primary education, child mortality,
    maternal health, HIV/AIDS and water.
  • The Millennium Project is also preparing a number
    of country case studies to map out the major
    policies and investments required to achieve the
    MDGs in the countries concerned.
  • The World Bank approach gives priority to the
    Poverty Reduction Strategy (PRS) previously
    defined by each country, and asks how, giving
    priority to the objectives and strategy of the
    PRS, the MDGs can best be achieved. PRSPs often
    prominently feature macroeconomic policy
    objectives that are not directly referred to
    among the MDGs.

20
NEPAL MDG COSTING
  • Projection of resource requirement
  • Relevant population forecast (e.g. 6 to 10 year
    old in he education sector)
  • Identification of required inputs and norms based
    on National plan (NGPES in the case of Laos)
  • Calculation of per unit norms of different
    activities
  • Projection of resource availability
  • Revenue Projection based on revenue/GDP ratio
  • Projection of internal borrowing and foreign
    assistance
  • Resource availability at the sub-sectoral level
    is done independently from domestic and external
    sources
  • Different growth scenarios are taken into
    consideration
  • Projection of resource gap
  • Resource gap resource requirement - Resource
    availability
  • Resource gap is presented at two levels
  • Resource gap from internal resource availability
    (revenue borrowing)
  • Total resource gap includes foreign assistance

21
Millennium Project MDG Based Poverty reduction
Strategies (PRS)
  • Pilot countries Cambodia, Ethiopia, Kenya,
    Ghana, Dominican Republic, Yemen, Tajikistan
  • Developing MDG-based Poverty Reduction Strategies
    requires to
  • Set tailored targets for 2015 and beyond (MDGR)
  • Express them in intermediate targets and
    actionable propositions for the short- and
    medium-term (NGPES)
  • Estimate the cost of the intermediate targets so
    they can drive the macro-economic and sectoral
    policy frameworks as well as the national budget.

22
The limits of existing MDG Needs Assessments
Models
  • Costing the MDGs is undermined by five main
    weaknesses
  • The impossibility to define the optimal policy
    framework ex ante (what is a good policy, a good
    institution?)
  • Fixed absorptive capacity constraints
  • The limits of the unit cost approach
  • The interconnectedness between the goals
  • Unpredictable future shocks

23
Making sense of MDG Costing
  • Domestic vs. external funding
  • Financing vs. costing
  • Short- and medium-term vs. long-term costing
  • Ownership vs. donorship
Write a Comment
User Comments (0)
About PowerShow.com