Description:

TDR / TOF / PHOS have two installation periods Period 1: Before TPC/ITS/Va Period 2: After the installation of TPC/ITS/Va (Vacuum chamber in place) – PowerPoint PPT presentation

Number of Views:23
Avg rating:3.0/5.0
Slides: 5
Provided by: NICE159
Category:

less

Transcript and Presenter's Notes

Title: Reminder on Installation Schedule (ALICE Forum June 2002)


1
Reminder on Installation Schedule (ALICE Forum
June 2002)
  • Install Muon magnet directly into experimental
    hall in temporary position
  • No pre-installation of magnet, absorber, Muon
    filter, Muon chambers in SXL2
  • Assembly of absorber at Point 2
  • Assembly line in SX2 if agreement with Sarov
  • No displacement of TPC and clean-room
  • Keep clean room in SXL2
  • Installation of TPC / ITS / Vacuum chamber
  • This installation has a duration of 6 months and
    is regarded as a block
  • We assume that no other activity can proceed in
    parallel
  • TDR / TOF / PHOS have two installation periods
  • Period 1 Before TPC/ITS/Va
  • Period 2 After the installation of TPC/ITS/Va
    (Vacuum chamber in place)

2
Installation Phases
  • Phase 1 now 01.06.2005
  • Large structures for Muon arm
  • Phase 2 01.06.2005 01.05.2006
  • TRD/TOF/PHOS/HMPID
  • Phase 3 01.05.2006 01.11.2006
  • TPC/ITS/Vacuum
  • Phase 4 01.11.2006 01.04.2007
  • Commissioning
  • PMD and FMD, V0, T0, Si3 on RB24 side
  • Last TOF modules
  • Shielding / machine interface / close L3 magnet
    etc

3
Installation of detectors into space-frame
  • Installation shaft 7 x 15 m2
  • Working position outside the magnet
  • Installation in the space-frame
  • 1st Period outside / inside the L3 magnet
  • 2nd Period after TPC/ITS/Va installation

4
Installation mile stones
  • Close L3 magnet back door
  • Best guess to-day is beginning of 2004
  • Installation of space-frame
  • In the new planning the space-frame is moved from
    SXL2 and installed in the experimental area in
    June 2005
  • I.e. pre-installation testing in SXL2, involving
    the space-frame, must end at this date