Title: Engineering Safety: Going Lower - Reducing Risk, Enhancing Projects
1Engineering SafetyGoing Lower - Reducing
Risk, Enhancing Projects
- Howard Thompson February 2013
- AMEC Brownfield Projects Operations Management
- Technical Safety Manager - AMEC Europe Head of Engineering Assurance
Governance
2Outline of Presentation
- Explore some of the trends that influence
Engineering Safety - Explore some of the limitations of Hazard Risk
Management as an approach to Engineering Safety - Outline the principles of an Inherently Safer
approach - Consider the organisational implications in
developing an Inherently Safer approach to
Engineering Safety
3In the Beginning ...
- ... low sensitivity to Consequences or the
Likelihood of them!
4More Recently ...
The Hoover Dam 112 people died during
construction
Attitudes to Hazards and Risks are
constantly evolving
5Trends in Occupational Safety
6Unrevealed Safety Issues
- Despite improving HSE Performance indicators, the
Texas City refinery suffered a major event in May
2005 and a second event two months later - OSHA Recordable Incident Frequency (RIF)
- Texas City refinery From 1.73 (1999) to 0.64
(2004) - API US refining average 0.84 (2004)
- BP Global 0.53 (2004)
- Occupational safety data can give misleading
indications of design or process safety
performance - Process or Design Safety was not widely
measured in 2005, however, indicators of hardware
safety issues are more widely recorded and
assessed now although there are many more
Lagging indicators in use than Leading ones!
7Texas City
8Trends in Refinery Damages
Incident costs - per 1000bbls refinery capacity
corrected to 2000 prices
9Trends
- Increased and increasing public risk aversion
- Reducing regulatory tolerance
- Increased damages where legal action ensues
- Increased focus on occupational safety and
statistics - Increasing focus on technical safety and
statistics - Increased Management of Change (MoC) challenges
- Through the life of modern engineered facilities
and products - Due to evolution in stakeholder organisations
- Changing operational requirements
10An Increasing Complex world Nimrod 2006
- After an Air-to-Air Refuelling (AAR), the plane
caught fire - Experienced crew acted with calmness, bravery
and professionalism, and in accordance with
training, but could not control the fire - Aircraft exploded
- All 14 on board died
11Why Did it Happen?
Fuel vent pipes and couplings
?
No 7 Fuel tank
Airframe anti-icing pipe
?
Cross-Feed Supplementary Cooling Pack Duct
(HOT)
?
Fuel pipes refuel and feed
?------
Uninsulated Bellows
12Why Did it Happen?
- Probable cause was fuel coming into contact with
extremely hot surfaces an overflow due to the
Air to Air Refuelling, ignited by the cross-feed
/ Supplementary Cooling Pack (SCP) duct, - which could be at up to 400ºC,
- and was not properly insulated
- Major design flaws
- Original fitting of cross-feed duct
- Addition of SCP
- AAR modification
13Why Did it Happen?
- Fuel pipe / vent coupling seals sourced from new
supplier - Couplings not to original specification
- Although thought to be by the procurement
function - Fuel pipe / vent couplings known to be
unreliable by maintenance teams - This information never fed back to the design or
safety case teams
14Why Did it Happen?
- A number of previous incidents and warning signs
ignored - Safety case existed but contained significant
errors - Widespread assumption that Nimrod was safe
anyway after 30 years of successful flights - Safety case became a tick-box exercise
- Missed key dangers, should have been the best
opportunity to prevent the accident - Financial pressures and cuts led to there being
distraction from safety as an overriding priority
15 Hazard and Risk Management ...
A crucial ... LIMITED
... contributor
to safety!
16Hazard and Risk Management Paradigm
What could happen?
How often?
How bad?
So what?
What do I do?
17Hazard and Risk Management
Risk Risk Management
Risk Analysis
HazardIdentification
FrequencyAnalysis
Consequence Analysis
Risk Assessment
Evaluation ofHazard Risk
Manage Residual Risk
18Event Sequences
- A corner stone of the Hazard Risk Management
Paradigm is the concept of Event Sequence
- The idea is that all event sequences are
identified in the analysis, or covered within
some more general event sequence
- A key limitation is the issue of
foresee-ability - What is foreseeable?
- Is it really possible to foresee all categories
of event
- The case law is demanding engineers and experts
are expected to foresee relatively remote events
- The OG industry regulator is not as demanding
as for example the Nuclear industry regulator in
these matters
19Underlying techniques of Hazard and Risk
Management Process
- REQUIRED The Hierarchical use of controls and
barriers - REQUIRED The Demonstration of ALARP
- ALARP - As Low As Reasonably Practicable
20Safe?
We identified the Hazards and ensured there were
adequate Safeguards, consistent with the ALARP
principle
N.b. ... The cost emphasis of ALARP ... an
encouragement to add safeguards until increased
benefits through risk reduction can not be
justified
21Some North Sea Events
- The SEA GEM 27th December 1965 13 Lost
- Mineral Workings (Offshore Installations) Act
1971
- The ALEXANDER KEILLAND 27th March 1980 123
Lost - Norway Created a clear source of Authority
for Abandonment - The sister rig the Henrik Ibsen also got into
difficulty a few months later
- The PIPER ALPHA July 1988 167 Lost
- Mineral Workings (Offshore Installations) Act
1971
22The SEA GEM The First Rig to Find Hydrocarbons
in the NS
23The Alexander Keilland Semi Sub Drilling
Rig Adjacent to a Production Platform
24Alexander Keilland Structural Arrangement
25Piper Alpha
26Metocean Conditions - Foreseeable ?
The Ocean Ranger Capsized off Newfoundland
February 1982 84 lost
Ocean Ranger with Draupner Wave shown for
comparison 1 The Draupner wave 59 ft / 18 m2
Location of unprotected portlight 28 ft / 8.5
m3 Location of the ballast control room
27How Can We Make It Safer ?
So what can we do differently?
28Inherently Safer Design
- The concept supports the view that the
achievement of safe operations requires that
HAZARDS are addressed during concept development
and all subsequent phases of System, Structure,
or Equipment design AND IMPLEMENTATION - The intent of Inherently Safer Design is to
eliminate a hazard completely or reduce its
magnitude significantly - Thereby eliminating / reducing the need for
safety systems and procedures - Furthermore, this hazard elimination or reduction
should be accomplished by means that are inherent
in the design and process and thus permanent and
inseparable from them
29Principles of Inherent Safety
Inherent Safety Principles
30Examples - Minimise
- Minimise storage of hazardous gases, liquids and
solids - Minimise inventory by phase change (liquid
instead of gas) - Eliminate raw materials, process intermediates or
by-products - Just-in-time deliveries of hazardous materials
- Hazardous materials removed or properly disposed
of when no longer needed - Hazardous tasks (e.g. working at height or above
water, lifting operations) combined to minimise
the number of trips - Need for awkward postures and repetitive motions
- minimised
31Examples - Substitute
- Substitute a less toxic, less flammable or less
reactive substance - Raw materials, process intermediates,
by-products, utilities etc. - Use of water-based product in place of solvent-
or oil-based product - Alternative way of moving product or equipment in
order to eliminate human strain - Allergenic materials, products and equipment
replaced with non-allergenic alternatives
32Examples - Moderate
- Reduce potential releases by lower operating
conditions (P, T) - Process system operating conditions
- New / replacement equipment that operate at lower
Speed, P or T - Dilute hazardous substances to reduce hazard
potential - Storage of hazardous gases, liquids and solids as
far as way as possible in order to eliminate risk
to people, environment and asset - Segregation of hazardous equipment / units to
prevent escalation - Relocate facility to limit transportation of
hazardous substances - New / replacement equipment that produces -
- less noise or vibration
33Examples - Simplify
- Simplify and / or reduce - connections, elbows,
bends, joints, small bore fittings - Separate single complex multipurpose vessel with
several simpler processing steps and vessels - Equipment designed to minimize the possibility of
an operating or maintenance error - Minimise number of process trains
- Reactors designed / modified to eliminate
auxiliary equipment (e.g. blender) - Eliminate or arrange equipment to simplify
material handling - Ergonomically designed workplace
34Examples of Equipment Level ISD in Brownfield
Operations Development 1
- Replace flammable hydraulic fluids with
water-based equivalents - Replace oil-filled switchgear with
vacuum-insulated equivalent - Replace Ex instrumentation with intrinsically
safe equivalents - Use low toxicity oils to replace PCBs in
transformers - Use low smoke, zero halogen, cable insulation
- Use PFP coatings that resist water ingress so
avoid Corrosion Under Insulation
35Examples of Equipment Level ISD in Brownfield
Operations Development 2
- Arrange equipment layout to minimise
restrictions on explosion venting - Arrange Deluge on Gas where advantageous to
minimise explosion overpressures - Arrange beam detection to replace or supplement
point FG detectors - Position acoustic leak detectors to supplement
gas detection for high pressure gas systems - Position hand rails at all locations where there
would be unguarded height, if equipment was
removed for service - Position pipe work, including flanges and
rodding points, so that service leaks will be
caught, and not by operators!
36Inherently Safer Design Why Bother?
- Helps us to achieve safer operations, both in
terms of day to day safety, and importantly ... - In avoiding low likelihood high consequence
events - Through the elimination and reduction of hazards
and unrevealed system vulnerabilities - Reduced number of Engineered Safeguards
- Reduced Complexity
- Reduced component and vessel sizes
- Reduced energy consumption
- Inherently Safer Designs have reduced CAPEX and
OPEX and are easier to operate and maintain!
37A Case Study ...
An Example of how Design without the application
of ISD results in unrevealed vulnerabilities Mu
mbai High How the cook cut his finger ... and
the platform fell into the sea ...
38Mumbai High North (27 July 2005)
39Mumbai High North Background
- Mumbai High Field was discovered in 1974 and is
located in the Arabian Sea 160 km west of the
Mumbai coast - The field is divided into the north and south
blocks, operated by the state-owned Oil Natural
Gas Corporation (ONGC) - Four platforms linked by bridges
- NA small wellhead platform (1976)
- MHF residential platform (1978)
- MHN processing platform (1981)
- MHW additional processing platform
- Complex imported fluids from 11 other satellite
WHPs and exported oil to shore via pipelines, as
well as processing gas for gas lift operations - The seven-storey high MHN platform had 5 gas
export risers and 10 fluid import risers situated
outside the platform jacket
40Mumbai High North Sequence of Events (1)
- Noble Charlie Yester jack-up was undertaking
drilling operations in the field - The Samudra Suraksha was working in the field
supporting diving operations - A cook onboard the Samudra cut off the tips of
two fingers - Monsoon conditions onshore had grounded
helicopters - The cook was transferred from the Samudra to the
Mumbai High platform complex by crane lift for
medical treatment
41Mumbai High North Sequence of Events (2)
- While approaching the platform the Samudra
experienced problems with its computer-assisted
azimuth thrusters and was brought in stern-first
under manual control - Strong swells pushed the Samudra towards the
platform, causing the helideck at the rear of
vessel to strike and damage one or more gas
export risers the resultant leak ignited - The close proximity of other risers and lack of
fire protection caused further riser failure -
the fire engulfed the Samudra and heat radiation
caused severe damage to the Noble Charlie Yester
jack-up - Emergency shutdown valves were in place at the
end of the risers which were up to 12 km long -
riser failure caused large amounts of gas to be
uncontrollably released
42Mumbai High North (27 July 2005)
43Mumbai High North (27 July 2005)
44Mumbai High North Aftermath
- The seven-storey high processing Platform
collapsed after around two hours, leaving only
the stump of its jacket above sea level - The Sumadra suffered extensive fire damage and
was towed away from scene but later sank on 01
Aug 2005, about 18 km off the Mumbai coast - A total of 384 personnel were on board the
platform and jack-up at the time of the accident
22 reported dead (only) - Significant problems were reported with the
abandonment of all the installations involved,
only 2 of 8 lifeboats and 1 of 10 life rafts were
launched
45How could a better design have avoided this
disaster or reduce its impact?
Would it be possible to eliminate the hazard
altogether?
- Position risers inside jacket structure
- Location of boat landing on lee side of platform
- Larger separation distance between platforms
- Subsea Isolation Valves to reduce hydrocarbon
inventory during release - Relocation and fire proofing of risers to prevent
escalation - Improved availability of evacuation means
46Inherently Safer Design How do we do it?
- Establish an ISD Culture
- Develop processes that support specific
structured ISD events
47Inherently Safer Design How do we do it?
- Establish an ISD culture within the organisation
- Driven from the top
- Involvement of all technical and project
personnel - Roll-out progressively presentations, posters,
pilot events - Establish processes and guidance for their use
- Ensure every project has planned ISD events in
every phase - Including each phase of Implementation
- Measure ISD uptake performance across all
projects - Sustain awareness and interest ensure all new
starts involved and encourage champions
48Success or Failure of ISD Some Factors
- All engineers and project personnel provided with
ISD Awareness training as part of Induction - Ownership - ISD is not owned by HSSE or Technical
/ Process Safety personnel but by All engineering
and project personnel - Operations personnel should be involved in all
ISD workshop / study events - The language of ISD should be sustained in each
project, ISD features should be captured and
presented in appropriate media - Often ISD design features do not receive the
credit and attention they should, or are only
known amongst a few - ISD design features should be acknowledged and
shared with a wider audience
49Putting it all together ...
50Integrating ISD Existing Safety Processes
51AMEC Several Years On A Summary of Findings
Encourage Each Project ...
- To have, and to communicate, a clear systematic
process - Definitions and Terms of Reference shared in
advance with all workshop participants and
stakeholders - Create an ISD Register at the earliest time and
maintain through all phases - Expect to identify some possibilities that will
not be actionable until a future phase, register
needs to keep track of these - Develop and maintain an ISD culture, make ISD
wins visible to the team as a whole
52An ISD Workshop Process
53ISD Goals - Examples of High Level Goals
- LAYOUT EXAMPLES
- Minimise explosion overpressure potential
- Minimise frequency of occurrence of explosion
overpressures - Minimise escalation potential from fire and
explosion events - Minimise vulnerability of Emergency Escape and
Rescue systems to fire and explosion including
Temporary Refuge - PROCESS EXAMPLES
- Maximise simplicity of plant
- Minimise hydrocarbon inventories and pressures
- Minimise leak potential
- Maximise integrity of containment envelope from
internal and external loadings and hazards - High level goals require to be pursued through
the development of low level goals with the
involvement of each and every technical
discipline contributing to the project
54An ISD Register
55An ISD Output
- Bridge length set to optimise separation between
Process and Well Bay areas and the Temporary
Refuge - Minimal inventory fuel gas for GTs
- Both jackets designed for a minimum Reserve
Strength (RSR) of 2.5 - Diverse Fire Pump locations
- Designed so as to minimise HP / LP interfaces
56Strategy for Hazard Management - UK HSE (OTH 96
521)
Identify Hazards
Understand /Assess Hazards
InherentlySafer Design (ISD)
Avoid Hazards
Reduce Severity
Reduce Likelihood
Segregate / Reduce Impact
AdditionalEngineeringControls
Apply Passive Safeguards
Apply Active Safeguards
Apply Procedural Safeguards
Risks ALARP
No
Yes
OK
57In Summary
- Attitudes to safety continue to evolve and pose
engineering project stakeholders ever greater
safety challenges - The traditional Hazard and Risk Management
paradigm is imperfect and further steps are now
required to meet modern challenges - Inherently Safer Design (ISD) consists of
straightforward principals that can be widely
applied -
- ISD when integrated with Hazard and Risk
Management changes the emphasis on how safety is
driven within design and planning processes - This change of emphasis is not only beneficial to
safety but to other project and operational
parameters including cost and maintenance burden
58Thats all for now ... ?
Hindenberg