PROJECT NETWORK DIAGRAM - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

PROJECT NETWORK DIAGRAM

Description:

PROJECT NETWORK DIAGRAM PREPARED BY : NOR AZAH BINTI AZIZ KOLEJ MATRIKULASI TEKNIKAL KEDAH * OBJECTIVES Define Network Diagram Purpose of Network Diagram Method ... – PowerPoint PPT presentation

Number of Views:757
Avg rating:3.0/5.0
Slides: 21
Provided by: KEMENT1
Category:

less

Transcript and Presenter's Notes

Title: PROJECT NETWORK DIAGRAM


1
PROJECT NETWORK DIAGRAM
  • PREPARED BY
  • NOR AZAH BINTI AZIZ
  • KOLEJ MATRIKULASI TEKNIKAL KEDAH

2
OBJECTIVES
  • Define Network Diagram
  • Purpose of Network Diagram
  • Method Activity On the Node (AON)
  • Identify ES, EF, LS, LF using Forward Pass
    Calculation and Backward Pass calculation
  • Identify Critical Path
  • Identify Slack Time

3
INTRODUCTION
  • A PND is a pictorial representation of the
    sequence in which the project work can be done.
  • The activities and its duration are the basic
    building blocks needed to construct a graphic
    picture of the project
  • Its provide
  • - the earliest time at which work can be begin
    on every activity that makes up the project
  • - the earliest expected completion date of the
    project

4
IMPORTANCE OF ND
  • ND can be used for
  • i) Planning gives a clear graphical picture of
  • the relationship between project activities
  • ii) Implementation when updating the project
    file with activity status and estimate to
    completion data, the ND is then automatically
    updated and can be printed or viewed
  • iii) control while updated ND will retain the
    status of all activities, the best graphical
    report and controlling project work will be
    Gantt Chart

5
METHODS
  • THE ACTIVITY ON THE NODE ( AON)
  • Basic unit of analysis in ND is the activity
  • Each activity is represented by a rectangle (
    activity node)
  • Arrows represent the predecessor/successor
    relationship between activities
  • Every activity in the project will have its own
    activity node ( each rectangle)

6
METHODS
  • THE ACTIVITY ON THE NODE ( AON)

7
METHODS
  • THE ACTIVITY ON THE NODE ( AON)
  • Dependencies
  • A dependency is simply a relationship that exists
    between pairs of activities
  • 4 types of activity dependencies

FS A finishes, B start
8
METHODS
  • THE ACTIVITY ON THE NODE ( AON)
  • Dependencies

FF A finishes, B finish
SS A start, B start
9
METHODS
  • THE ACTIVITY ON THE NODE ( AON)
  • Dependencies

SF A starts, B finish
10
  • THE ACTIVITY ON THE NODE ( AON)

11
  • THE ACTIVITY ON THE NODE ( AON)

Creating an initial project network schedule
Forward Pass calculations
12
EST, LST, EFT, LFT
  • CPM uses the following times for an activity
  • EST - Early Start time is the earliest time the
    activity
  • can begin
  • LST - Late Start Time is the latest time the
    activity can begin
  • - still allow the project to be completed on
    time
  • EFT - Early Finish Time is the latest time the
    activity can end
  • LFT - Late Finish Time is the latest time the
    activity can end
  • - still allow the project to be completed on
    time

13
Forward Pass calculations
14
Backward Pass calculations
15
CRITICAL PATH METHOD (CPM)
  • An effective way to analyze complex projects
  • Represent the critical set of activities to
    complete a project
  • Help to focus on essential activities which are
    critical to run the project
  • Allows the project manager to concentrate on
    important activities
  • CP is the longest path on ND and the most
    important part
  • Any delays on the CP will lead to delay of the
    project

16
CRITICAL PATH METHOD (CPM)
17
FLOAT
  • Also known as slack, total float and path float
  • Is computed for each task by subtracting EFT from
    the LFT
  • ( _at_ the early start from the late start)
  • Is the amount of time the task can slip without
  • delaying the project finish date.
  • Free float is the amount of time a task can slip
  • without delaying the early start of any task
  • that immediately follows it.

18
Slack Time calculations
19
EXAMPLE
1. TABLE 1 shows the activities and the
durations required to complete a construction
project, including the precursor activity.
Refering to the TABLE 1 i) draw the
project network diagram. ii)
state the activities on the critical path. iii)
calculate the minimum duration of the
project.
Activity Precursor Duration (week)
A - 7
B A 6
C A 5
D A,B 4
E B,C 3
F D,E 2
20
project network diagram
Write a Comment
User Comments (0)
About PowerShow.com