Conventional Facilities Overview - PowerPoint PPT Presentation

About This Presentation
Title:

Conventional Facilities Overview

Description:

Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule Cost Estimate Organizational Chart Technical Challenges ES&H Issues – PowerPoint PPT presentation

Number of Views:151
Avg rating:3.0/5.0
Slides: 25
Provided by: sae77
Category:

less

Transcript and Presenter's Notes

Title: Conventional Facilities Overview


1
Conventional Facilities Overview
  • SLAC Site Plan
  • Systems Description
  • Construction Schedule
  • Cost Estimate
  • Organizational Chart
  • Technical Challenges
  • ESH Issues
  • Management Challenges
  • Progress to Date

2
SLAC Site Plan
SLAC MAIN GATE
Pep Ring Road
Interstate 280
Research Yard
3
Systems Description
  • Sector 20 Injector Facility
  • Magnetic Measurement Facility
  • Main Control Center Renovation
  • Linac Improvements
  • Beam Transport Hall
  • Undulator Hall
  • Electron Beam Dump
  • Front End Enclosure
  • Near Experimental Hall
  • X-Ray Transport Diagnostics Tunnel
  • Far Experimental Hall
  • Central Lab Office Complex

4
LCLS CF Systems Description
  • Extends SLAC LINAC 1/2 mile (814 meters)
  • Includes a composition of renovations to existing
    SLAC infrastructure and new facilities

5
LCLS CF Systems Description - continued
  • Renovated Facilities
  • Sector 20 Injector Facility - 2,160 sf facility
    incl Laser Rm, Control Rm to house the injector
    laser and assoc equipment
  • Magnetic Measurement Facility - 4,000 sf
    facility used to tune, measure and store the
    undulators magnets
  • Linac Improvements modifications required to
    some utilities to support new bunch compressors

6
LCLS CF Systems Description - continued
  • New Facilities
  • Beam Transport Hall 227m long above grade
    facility to transport the electron beam through
    the existing RSY
  • Undulator Hall 175m long underground tunnel
    housing undulators and ancillary equipment
  • Electron Beam Dump 40m long underground
    facility used to separate the electron and x-ray
    beams
  • Front End Enclosure 30m long underground
    facility to house various diagnostic equipment in
    support of the photon beam

7
LCLS CF Systems Description - continued
  • Near Experimental Hall underground facility
    whose primary function is to house 3 experimental
    hutches, prep and shops
  • X-Ray Transport Diagnostics Tunnel 250m long
    underground tunnel used to transport photon beams
    from NEH to FEH
  • Far Experimental Hall underground
    cavern/tunnels to house 3 experimental hutches,
    prep and shop space
  • Central Lab Office Complex office facility to
    house 300 LCLS researchers, engineers,
    technicians, administrative staff and visiting
    experimentalists

8
LCLS Site Plan
Pep Ring Rd
Spear
Office Complex
SLC
Undulator Hall
NEH
Survey Tower
FEH
Research Yard
Beam Transport Hall
SLC Tunnel
Beam Dump Front End Enclosure
X-Ray Transport
Future Beam Lines
Pep Tunnel
Future Office Space
9
Below Grade Plan
Beam Transport Hall
Near Hall
Undulator Hall
Far Hall
XRTDT
10
Plan at Grade
Beam Transport Hall
Survey Tower Road Upgrade
Research Yard
Central Lab Office Complex
11
(No Transcript)
12
  • IN RESEARCH YARD
  • 227 M LONG
  • 15 x 14-9 (W x H)
  • 63 M HEADHOUSE
  • 72 THICK WALLS
  • 48 THICK CEILING
  • 3 SERVICE AREAS
  • ENDS IN HEADWALL
  • HEADWALL LABYRINTH

13
  • UNDER HILL
  • 175 M LONG
  • 21-11 x 14-6 (W x H)
  • 33 UNDULATORS
  • HEAVY GRANITE SLABS
  • MONOLITHIC FLOOR
  • THERMAL BARRIERS

14
  • UNDER PEP RING RD.
  • 40 M LONG
  • 15 x 12-6 (W x H)
  • CAST-IN-PLACE
  • GROOVED FLOORS
  • E-BEAM DIPS DOWN
  • HEAVY METAL SHEILD

15
  • EAST OF BEAM DUMP
  • 29 M LONG
  • BETWEEN SHEILDS
  • 15 x 12-6 (W x H)
  • CAST-IN-PLACE
  • NUMEROUS EQUIP.

16
BEAM TRANSPORT HALL
  • EAST OF FEE
  • 39 M LONG
  • 2 FLOORS
  • 3 HUTCHES
  • 1 LASER BAY (ABOVE)
  • CLOC FACILITY ABOVE
  • PREP CONTROL AREA
  • FREIGHT ELEVATOR
  • CUT FILL TECHNIQUE

17
BEAM TRANSPORT HALL
  • WITHIN NEH
  • TOTAL 3 (CURRENT)
  • ANOTHER 3 (FUTURE)
  • 9.5 M x 10 M
  • SHEILDING NEEDED
  • TWO TANKS/ HUTCH
  • HEAVY SLIDING DOOR
  • EQUIP. ACCESS (HOIST)

18
BEAM TRANSPORT HALL
X-RAY TRANSPORT TUNNEL
  • EAST OF NEH
  • 250 M LONG
  • 18 WIDE CONSTANT
  • BEAM SPLITS IN THREE
  • LABYRINTH TO FEH
  • WALKWAY ALONG BEAM

19
BEAM TRANSPORT HALL
  • END OF X-RAY TUNNEL
  • 29 M LONG
  • 2 CAVERN/TUNNELS
  • 31 x 21 (W x H)
  • CONNECTING TUNNELS
  • OFFICES IN EXTENDED CAVERN
  • ACCESS TUNNEL

20
Below Grade Overview
21
At Grade Overview
  • IN RESEARCH YARD
  • 227 M LONG
  • 15 x 14-9 (W x H)
  • 63 M HEADHOUSE
  • 72 THICK WALLS
  • 48 THICK CEILING
  • 3 SERVICE AREAS
  • ENDS IN HEADWALL
  • HEADWALL LABYRINTH
  • IN RESEARCH YARD
  • 227 M LONG
  • 15 x 14-9 (W x H)
  • 63 M HEADHOUSE 72 THICK WALLS 48 THICK CEILING
  • 3 SERVICE AREAS

Office Complex To Accommodate Approx 300
personnel
22
CF Summary Schedule
Shutdown of FFTB
  • Major construction phase FY 06 at 24-27 months
  • Beneficial Occupancy dates are key to technical
    system interfaces
  • Site-work at NEH is key!

23
Cost Estimate
Total CF Cost (work remaining) 69,410K
24
CF Org Chart FY 04
25
CF Org Chart FY 05
26
CF Org Chart FY 06-08
27
Technical Challenges
  • Tunneling
  • 800m in sandstone w/ some large spans
  • Standing tunnel committee has been formed
  • Undulator Hall
  • Vibration
  • Thermal
  • Independent engineering firm will review HVAC
    system
  • Settlement
  • Near Experimental Hall
  • Vibration
  • Thermal
  • Chris Laughton FERMI Lab
  • Rick Nolting Jacobs Assoc
  • A local eng firm will be used
  • for this function

28
ESH Issues
  • ESH Issues
  • RSY (BTH)
  • The necessity to analyze for PCBs, Diesel and
    Lead will constitute the requirement for drilling
    operations for lab analysis to determine the
    concentration levels in the soil and concrete
  • CLOC
  • The necessity to analyze for PCBs and Diesel
    will constitute the requirement for drilling
    operations to investigate for lab analysis to
    determine the concentration levels in the soil
  • Disposals
  • Top 2 of BTH and CLOC will require disposal
    off-site to a Class II (non-hazardous waste)
    landfill.

29
ES H Issues contd
  • Construction Safety
  • All construction activities to comply with
    Federal and State environmental, safety, health
    and building codes
  • Subcontractor activities
  • In-house activities
  • SLAC will approve construction safety program
    prior to start of construction
  • Special consideration is being addressed
  • Tunnel construction
  • RSY due to the congestion in the area

30
Management Challenges
  • Bay area construction market
  • Materials
  • Labor
  • Large single procurement package
  • Strategy sessions with other labs
  • Schedule concerns
  • Annual lab shut-down periods
  • Schedule for site characterization remediation
  • FFTB decommissioning

31
Progress to Date
  • Title I complete!
  • Major design progress accomplished considering
    late start of Title I (1/04-5/04)
  • Charrette sessions (brain-storming)
  • Multiple design reviews (30-50-100)
  • 2 day VE session (collaborative team)
  • Report available indicating 5M savings
  • Title I deliverables and milestones were met on
    schedule
  • As-built program complete

32
Progress to Date - contd
  • Environmental sampling waste disposal program
    has been initiated
  • Initiated standing tunnel committee
  • Obtained the services for an Independent Cost
    Estimate review (report due 10/15/04)
  • Commenced a site-wide involvement to discuss
    construction impact to SLAC
  • Completed initial geotechnical report, and
    supplemental report is in process (draft report
    due 10/15/04)

33
Summary
  • Where we go from here
  • Interim services by JE between Title I/Title II
  • Engineering studies for additional cost reduction
    and value added opportunities
  • Continue construction procurement strategy
    sessions
  • Title II
  • Scheduled 01/05 thru 7/05
  • Funding limited
  • CM will be on board 5/05
  • Funding limited
  • Title III
  • Scheduled to commence 03/06 09/08
  • Funding limited
Write a Comment
User Comments (0)
About PowerShow.com