Title: Parliamentary submission on the eradication of the Bucket Toilet System 22
1Parliamentary submission on theeradication of
the Bucket Toilet System 22 23 February
2007Cllr. Derrick Ndlovu
2Introduction
- Roughly 4 million households without access to
basic sanitation are still to be served (2010) - Of this amount, roughly 132 000 households in
formalized areas are still using the bucket
system (/- 4 of the total household backlog)
these are to be eradicated by Dec 2007 - The largest concentration of buckets still to be
eradicated are in the Free State, Eastern Cape
North West Provinces - Mpumalanga Province has already eradicated
buckets in their formalized areas at end 2006
3Achievements
- 57 377 buckets were removed in the 06/07
financial year up to January 2007. - 24 136 buckets were removed between April and
June 2006, 18 002 between July and September
2006, while 8 427 were removed between October
and December 2006. In January 2007 alone, a
further 6 812 buckets were removed. - (DWAF Technical MinMec Report February 2007)
4Achievements
- In Mpumalanga Province the bucket system has been
eradicated in all of the formalized households
this provincial programme has seen 18 862
households across five municipalities served (523
households with VIPs in water scarce areas and 18
339 households with waterborne toilets)
5Lessons Learnt
- In Mpumalanga the approach was to appoint
emerging contactors in relation to the
construction of toilet top structures in
designated locations according to the sewer
network layout plan, and professional consultants
undertook the layout and construction of the
sewer bulk line and house connections. - Community participation in the programme was
ensured via the Local Municipalities and their
Ward Structures and municipal technical sections
had designated officials from within the
municipalities, to work in conjunction with the
appointed Project Managers and Contractors under
the WSA, DWAF and DLGH Programme Managers.
6Lessons Learnt
- Progress reports were completed weekly and signed
off at project level by the Contractors, Project
Managers, and Municipal Officials. - Weekly site meetings were held to assess progress
and bottlenecks, and monthly progress meetings
held between all provincial stakeholders.
7Combination of professional emerging service
providers on waterborne bucketeradication
household networks and bulk plant
Lessons Learnt
8Challenges
- Capital MIG fund allocations must be matched by
increased municipal operating budgets (since
waterborne sewage systems make use of water which
is a municipal operating trading account) - Integrated planning within municipal WSDPs
IDPs must be strengthened in line with Provincial
bucket eradication strategies Housing linkages - Bucket eradication project feasibility studies
should be preceding the design implementation
of MIG bucket eradication projects so as to
prevent poor investment to municipalities their
constituents
9Challenges
- The monitoring evaluation of MIG bucket
eradication projects being implemented must be
strengthened by increasing local level municipal
capacity involvement - Municipalities capacity ability to oversee
manage appointed bucket eradication service
providers must be strengthened - Increased municipal capacity to ensure
sustaining, maintaining extending existing
waterborne sewage in light of the bucket
eradication programme must be ensured to prevent
future system failures negative water quality
environmental impacts
10Recommendations
- Include the sustainability aspects of bucket
eradication in the National Sanitation Policy
revision - Ensure that there is increased alignment between
the Department of Housing sanitation sector - Establish a mandatory Sanitation Component of the
MIG so as to ensure eradication of all sanitation
by 2010 beyond the bucket eradication programme - Match capital MIG fund allocations with increased
municipal operating budgets - Develop endorse Provincial bucket eradication
strategies improve Mun planning in WSDPs IDPs
11Recommendations
- Ensure Municipal bucket eradication feasibility
studies are conducted - Increase monitoring of Municipal bucket
eradication project implementation improve data
capture systems - Increase municipal capacity to ensure sustaining,
maintaining extending existing waterborne
sewage to prevent future system failures
negative impacts - Ensure on-going financial, operating
maintenance requirements are met - Improve sector support, monitoring regulation
for all forms of sanitation
12Service after deliverya better life - ?
Bucket system replaced with a leaking
sub-standard waterborne system. The household was
forced to disconnect the water supply due to
municipal charges for water and therefore
resorted to using the old bucket to fetch water
at a standpipe to pour flush the toilet as
needed...
13THANK YOU