Title: Department of Public Works and Engineering FY11 Budget Presentation


1
Department of Public Works and EngineeringFY11
Budget Presentation
2
PWEMISSION OVERVIEW
  • We plan, design, construct, operate and maintain
    Houston's critical public infrastructure systems
    and administer the Citys building and
    development codes in a coordinated manner to
    provide excellent drinking water and wastewater
    collection and treatment, effective storm water
    drainage, safe buildings and streets and we do
    so responsively, efficiently and in an
    environmentally responsible fashion.

3
PWE BUDGETFY11 OVERVIEW
Budget FY2010 Adopted FY2010 Current FY2010 Estimate FY2011 Proposed
OM 646.2M 639.3M 621.8M 629.9M
Debt Service 421.7M 402.1M 401.7M 458.3M
Equipment 23.3M 18.8M 17.0M 23.1M
Revenue 854.4M 854.4M 824.6M 989.1M
FTEs 4,182.9 4,162.3 3,978.9 4,098.5
4
BUDGET REDUCTION IMPACTFUND 1000
  • RIGHT OF WAY (ROW) and TRAFFIC TRANSPORTATION
    (TT) GENERAL FUND OM DIVISIONAL BUDGETS

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed Variance from Adopted
BUDGET 50.5M 49.2M 48.8M 48.8M (1.7M)
FTEs 514.6 495.5 488.0 486.1 (28.5)
  • PWE has two major General Fund operating
    divisions that were significantly impacted by the
    FY10 and FY11 budget reductions as follows
  • ROW Division (1.1M)
  • Total concrete usage for repairs of base failures
    and buckles in streets decreased from 326,000
    cubic feet in FY10 to 262,000 in FY11.
  • Lane miles of Asphalt Overlay decreased from 185
    in FY10 to 140 in FY11. 185 lane miles was
    budgeted in FY10 but decreased to 165 as part of
    the FY10 budget reductions. Additional 25 miles
    is further reduced in FY11.
  • TT Division (0.6M)
  • Sign installations decreased from 26,000 in FY10
    to 20,000 in FY11.
  • New fabrication of street signs decreased from
    21,000 in FY10 to 18,000 in FY11.

5
TRAFFIC TRANSPORTATION OVERVIEW FUNDS 1000,
1001, 2304 2402
  • RESOURCES OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 21.7M 21.3M 21.2M 22.3M
FTEs 214.9 204.7 198.6 207.6
  • MAJOR PROGRAMS
  • Maintain over 1,000,000 street name and traffic
    control signs
  • Maintain traffic signals at over 2,400
    intersections
  • Maintain over 1,650 school zone beacons
  • Monitor 140 railroad crossings
  • Manage permitting process for lane and sidewalk
    closures
  • Apply 4.2M linear feet of paint and 100,000
    linear feet of thermoplastic striping for
    pavement markings
  • Coordinate Mobility Response Team activities
  • Manage Neighborhood Traffic Management Program
  • Manage Houston TranStar

6
RIGHT OF WAY (ROW) MAINTENANCEOVERVIEW- FUND 1000
  • RESOURCES OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 32.3M 31.5M 30.8M 31.2M
FTEs 313.7 304.8 302.7 301.5
  • MAJOR PROGRAMS
  • - Maintain a total of 15,850 lane miles of
    streets by
  • Applying 16,000 tons of asphalt to potholes and
    street skin patches
  • Overlaying 140 lane miles of streets
  • Applying 262,000 cubic ft of concrete to repair
    failures and buckles
  • - Inspect and repair 1,350 bridges
  • - Replace 8 bridges
  • - Maintain 2,500 dead-end barricades

7
ROW FLEET MAINTENANCEOVERVIEW FUND 1005
  • RESOURCES OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 24.5M 24.5M 24.6M 25.8M
FTEs 96.9 96.9 94.3 96.9
  • MAJOR PROGRAMS
  • Revolving Fund used to service vehicles citywide
  • Maintain 4,700 (4,200 PWE) vehicles/equipment for
    17 departments at 8 repair facilities located
    Citywide
  • Maintain a 95 vehicle availability rate
  • Maintain/operate 17 vehicle fuel sites,
    dispensing 2.6M gallons of unleaded and diesel
    fuel
  • Manage 30 contracts with outside vendors for
    specialty vehicle
    repairs

8
ROW - STORMWATER MAINTENANCEOVERVIEW FUND 2302
  • RESOURCES OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 32.7M 30.9M 30.8M 33.0M
FTEs 374.3 374.3 375.6 378.6
  • MAJOR PROGRAMS
  • Maintain 2,800 miles of roadside ditches
  • Maintain over 3,600 miles of storm sewer lines,
    100,000 inlets and 60,000 manholes
  • De-silt/re-grade 275 miles of roadside ditches
  • Inspect 60,000 unique inlets and/or manholes
  • Inspect 240 miles of storm sewer main lines
  • Mow off-road ditches (3 cycles)
  • Comply with requirements of National Pollutant
    Discharge Elimination System permit (NPDES)
    1,400 storm water investigations, sweep
  • 21,500 miles of gutter, collect 8,500 cubic
    yards of litter and 650,000 lbs of household
    hazardous waste

9
ENGINEERING CONSTRUCTION OVERVIEW FUND 1001
  • RESOURCES- OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 24.3M 24.3M 22.9M 24.7M
FTEs 254.5 254.5 235.6 252.4
  • MAJOR PROGRAMS
  • Manage 343 design/construction projects currently
    in progress
  • 78 water projects (252 million)
  • 77 wastewater projects (104 million)
  • 143 storm sewer projects (203 million)
  • 45 street/bridge projects (97 million)
  • Initiate 481 million in new projects for FY11 CIP

10
PLANNING DEVELOPMENT SERVICES OVERVIEW FUNDS
1000, 1001, 2301 8300
  • RESOURCES OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 61.2M 56.1M 53.0M 55.0M
FTEs 641.6 637.6 613.9 597.7
  • MAJOR PROGRAMS
  • Examine over 35,000 construction plans for
    compliance with building code and ordinances
    issue over 175,000 building permits and conduct
    over 496,000 building code inspections
  • Provide over 1,300 engineering reviews for
    private development in the City manage
    development in the flood plain provide basis for
    FEMA flood insurance rating
  • Plan for Citys future water/wastewater needs
    issue 5,500 wastewater capacity reservations
  • Provide Real Estate support for the annual CIP
  • Perform periodic inspections of multi-family
    properties (over 1,000 complexes)

11
COMBINED UTILITY SYSTEM COST REDUCTIONS
  • FY11 Major Cost Reductions
  • -8.7M Electricity reduction due to lower prices,
    implementing McKinsey recommendations to perform
    more preventative maintenance on pumps, less
    groundwater and more surface water pumping due to
    completion of the Metro Condition Assessment
    project.
  • -2.3M Natural Gas reduction due to lower prices,
    implementation of the McKinsey recommendation to
    utilize more than one centrifuge to a dryer which
    allows more solid waste to be treated for optimal
    results, as well as, utilizing high efficiency
    gas dryers at the Almeda Sims Treatment plant.
  • -2.5M Water Authority Contract Debt reduction
    due to paying down the principal on the Coastal
    Water Authority debt.
  • 4.5M Personnel increased primarily due to HOPE,
    PFP and Health Benefit increases of 5.7M
    however, through attrition and McKinsey
    efficiencies, the Department has been able to
    absorb 1.2M of these costs.

12
PUBLIC UTILITIESOVERVIEW FUND 8300
  • RESOURCES OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 303.2M 303.2M 295.8M 286.9M
FTEs 1,504.7 1,504.7 1,442.8 1,504.0
  • MAJOR PROGRAMS
  • Operate/maintain 3 surface water and 89 ground
    water pump stations, 174 groundwater wells,
    producing 142 billion gallons/year
  • Operate/maintain 39 wastewater treatment plants
    and 420 lift stations, treating 90 billion
    gallons sewage/year
  • Maintain 7,000 miles of water mains and over
    6,700 miles of sanitary sewer collection lines,
    performing 13,000 repairs/year
  • Maintain 54,000 fire hydrants and 182 water
    tanks/towers
  • Provide water and/or sewer service to
    approximately 2.8 million regional residents

13
RESOURCE MANAGEMENTOVERVIEW FUNDS 1000, 1001,
8300 8305
  • RESOURCES- OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 123.5M 124.6M 122.5M 120.2M
FTEs 545.2 545.2 522.1 534.2
  • MAJOR PROGRAMS
  • Manage 16.0 billion in fixed assets
  • Bill and collect over 880 million annually in
    water sewer revenue and read and maintain over
    465,000 meters.
  • Maintain/operate 9 warehouse facilities at 7
    different locations with 8,512 unique commodities
    available provide inventory support to four
    departments.
  • 4,600 construction, engineering and testing
    invoices processed
  • Purchasing and receiving for 6,160 purchase
    orders, 130 active service contracts, 400 active
    project contracts, 154 active supply contracts
    and 330 P-Card users.

14
OTHERSHR, IT AND DIRECTORS OFFICE FUND 1000,
1001, 2301, 2302, 8300
  • RESOURCES OM Budgets

FY10 Adopted FY10 Current FY10 Estimate FY11 Proposed
BUDGET 23.1M 22.9M 20.2M 30.9M
FTEs 236.6 236.6 193.3 225.6
  • MAJOR PROGRAMS
  • Manage Safety and Environmental programs
  • Provide HR services for approximately 4,000 PWE
    employees
  • Provide Security Management for PWE employees and
    facilities
  • Provide IT support for 80 Applications unique to
    PWE and support 2,600 Users within PWE Department
  • Manage and support the Pay or Play (POP) Program
  • Perform 16 internal audits per year

15
DEBT SERVICEOVERVIEW
  • Water/Wastewater Debt Service - 449.3M, up
    44.3M from the FY10 Adopted Budget (405M)
  • Pension Obligation Bonds Debt Service - 5.2M
  • Special Fleet Equipment Financing
  • Fleet Equipment - 135 thousand
  • Fleet Equipment General Fund - 1.0M
  • Milling Machine Debt Service 227 thousand
  • Special Revenue Financed Equipment
  • ILMS Debt Service - 266 thousand
  • 1002 Washington Avenue Debt - 578 thousand
  • LED Retrofit Traffic Signal Upgrades 1.7M
  • Total Outstanding Debt - 6.0 billion (All Funds)

16
MAJOR REVENUE SOURCESOVERVIEW FY 2011
  • 441.5 million water sales (8300)
  • 411.0 million sewer sales (8300)
  • 9.3 million impact fees (8301)
  • 35.4 million building and sign permits (2301)
  • 1.0 million plan reviews (2301)
  • 9.1 million sale of streets/land (1000/8300)
  • 47.6 million METRO contributions (1000)
  • 13.2 million Interest Income (All Funds)
  • 21.0 million Other (All Funds)
  • 989.1 million Total

17
Efficiencies
  • Traffic
  • Purchase of truck mounted thermoplastic
    applicator to replace paint application with
    thermoplastic material for road striping which
    results in an increase in life expectancy from 6
    months to 3 years.

18
Efficiencies
  • Resource Management
  • Continue to implement McKinsey recommendations to
    increase consumer adaptation to web based
    payments and billings thereby reducing paper
    billings and check processing.
  • Continue to implement McKinsey recommendations to
    accelerate the installation of endpoints (76,900
    for FY11), thereby improving the accuracy of the
    meter reads and revenue billings, as well as,
    minimizing operating costs.
  • Planning Development
  • Implementation of the Integrated Land Management
    System web based program will enhance
    contractors ability to manage projects, permits,
    and inspections online thereby improving the
    efficiency and quality of information exchanges.
  • Co-location of 10 permitting departments from
    several locations citywide to the 1002 Washington
    Avenue Central Permit Facility thereby
    increasing productivity and reducing operating
    costs. Grand opening targeted for July 2011.

19
Efficiencies
  • Public Utilities
  • Continue to optimize chemical dosage through
    improved sensor monitoring and training, as well
    as switching to less costly alternatives.
  • Continue to implement McKinsey recommendation
  • Optimize electricity by performing more
    preventative maintenance on pumps.
  • Reduce natural gas consumption by utilizing high
    efficient dryers at the Almeda Sims Treatment
    Plant, as well as, utilizing more than one
    centrifuge to a dryer which allows more cost
    effective operation.
  • Finalize roll out of reduction of crew size from
    three person to two person that will allow more
    time for preventive maintenance repairs in an
    effort to reduce corrective maintenance costs and
    extend equipment life.

20
Efficiencies
  • Information Technology
  • Continue to implement and support department wide
    wireless WIMAX initiatives for automated water
    meter reading , traffic signal and SCADA
    communications.
  • Continue to replace PWE legacy telephones with
    VOIP telephones, thereby allowing increased
    efficiency of the data circuits by utilizing less
    data lines.
  • Engineering Construction
  • Utilize manpower analysis as a basis for level of
    effort required for CIP Cost Recovery and
    personnel levels.
  • Continue coordination with divisions for overall
    asset inventory for proper planning and
    allocation between Capital and Operation
    Maintenance expenditures.

21
Efficiencies
  • Right of Way
  • Continue to utilize the Data Collection Mobile
    Unit (DCMU) system that automatically detects and
    rates pavement distresses thereby allowing the
    department to better target the utilization of
    limited resources, as well as, improving the
    efficiency and quality of data collection.

22
PWE BUDGETFY11 OVERVIEW
  • Funds included
  • 1000 General Fund
  • 1001 CIP Cost Recovery Fund
  • 1005 Fleet Management Fund
  • 1800 Equipment Acquisition Fund
  • 2301 Building Inspection Fund
  • 2302 Storm Water Utility Fund
  • 2304 Mobility Response Fund
  • 2402 Houston TranStar Fund
  • 8300 Water and Sewer System Operating Fund
  • 8301 Combined Utility System Operating Fund
  • 8305 Combined Utility System General Purpose Fund