Title: Engineering (Mechanical)
1Engineering (Mechanical)
2Contents
- Station assembly
- Tracker assembly
- Installation
- Patch-panel
- Installation procedure
- Infrastructure/Operation
- Gas system
- Helium/vacuum window
- Summary
3Station assembly
- We already have built four stations for a
prototype tracker module - We learned a lot from this experience as well as
from the KEK test beam results - We will incorporate quality assurance steps to
station assembly procedure to eliminate source of
problems for light-loss and fibre mapping - In the following slides, station assembly
procedure for the production of stations is
explained step by step
4Station assembly - sequence
- Receive doublet-layers from FNAL
- Visual inspection of the doublet-layers for any
damage caused in transit - Align the doublet-layers on a vacuum chuck
- Bundle seven fibres with rubber sleeves (QA)
- Thread the bundle into a station connector (QA)
- Put the vacuum chuck on an assembly jig
- Fix a carbon-fibre station to the assembly jig
- Glue the doublet-layers to carbon-fibre station
- Attach doublet-layers connectors to the
carbon-fibre station - Cut the fibres
- Pot the fibres
- Polish the fibres
5Station assembly - tools
- Station holder
- Bundling Comb
- Connectorisation bridge
- Vacuum chuck
- Alignment jig
6Station assembly - numbering
- Unique numbering scheme defined to make sure
correct fibre mapping - Start bundling from the centre fibre, marked
during doublet-layer manufacturing - QA procedure ensures correct bundling with comb
7Station assembly - bundling
- Align doublet-layer on vacuum chuck
- comb to help identify error during bundling is
being manufactured at Liverpool with aluminium - Bundling procedure with comb will be
established with the existing fibre ribbon
8Station assembly - connector
- Bundle is threaded into the correct hole in the
connector on bridge - QA ensures correct threading procedure to be
defined
QA gauge
View W 20 Way Bundles 1 20 To Bulkhead
Connectors 1, 6, 11, 16 21
1
5
3
4
2
6
8
10
7
9
11
13
12
14
15
16
Station connector Viewed from the polished
face. Internal light-guide connector viewed from
rear or fibre entry side.
18
17
20
19
x
x
9Station assembly final steps
View of the station onto the polished face of the
connector
- Put the vacuum chuck on an assembly jig
- Fix a carbon-fibre station to the assembly jig
- Glue doublet-layer to carbon-fibre station
- Connectors on bridge is attached to the correct
position - Cut fibres
- Pot fibres
- Polish fibres
-
10Station assembly - prototype
11Station assembly - summary
- We have built four stations. The fourth station
design was improved by the experience gained
during the three stations assembly. - We have identified the source of problems to be
fixed by the KEK test beamconnector hole
alignment, fibre bundling and fibre
connectorisation - QA procedures will rectify the problems during
station assembly, see Pauls talk - We will build the fifth station with the improved
assembly procedure which incorporates QA - We will be ready to produce the stations soon.
- TODO
- Establish QA procedures with comb and bridge,
see Pauls talk
12Tracker assembly
- We have built a tracker prototype with four
stations - Assembly scheme for the prototype will be used
for the three production version of tracker
modules with five stations - Before starting assembly we need to fix the
station spacing, see Malcolms talk
13Tracker assembly - space frame I
- Space frame between stations connects
- two stations together
- Barrel
- Gluing fillet
- Structural tube
- Locating foot
- Foot design
- improved from
- prototype
14Tracker assembly - space frame II
- These are the parts used for the prototype
- Close up view of the space frame
- feet and structural tubes
15Tracker assembly - jigs
- These are jigs used for the prototype assembly
- Jigs to be made after fixing station spacing
- Could be outsourced, the possibility will be
investigated
16Tracker assembly - light-guide
- Channel map for station 1
- Length of the light-guide to be determined after
fixing the station spacing
17Tracker assembly - prototype
- Four stations prototype without light-guides
- Equipped with light-guides
- We will build three more trackers one for spare
18Tracker assembly - summary
- We have built a tracker prototype with four
stations - Assembly tools and scheme for the prototype will
be used for the production version - TODO
- fix the station spacing, see Malcolms talk
19Installation
- We need to install the tracker module inside the
bore of the solenoid module - Damages to the tracker during the installation
procedure should be prevented - In the following slides, patch-panel and
installation procedure is explained step by step
20Installation patch-panel
- Works as a fan-out for light-guides
- Gas-tight with O-ring to contain He
- 25 holes for fibre connectors
- 1 hole for hall probe field monitoring service
21Installation pp and diffuser
- The cover will need to be stiffened and tied back
to the solid region where the patch-panel is
mounted to the solenoid - We have allowed a bore of 331Ø in the cover with
a series of holes and a position for an O-ring - Responsibilities allocated
- Need to finalise detailed design
Detail Drawing almost complete
22Installation pp ext. light-guide
- External light-guide makes one to one connections
between the patch-panel connector and the VLPC
128 way connectors. - O-ring incorporated to ensure a gas seal
- Length of the external light-guide to be fixed
with a full-size mock-up
Patch-panel connector
VLPC connector
23Installation Hall-probe mount
- Hall-probe can be fixed to a collar that will be
attached to the bore of the solenoid - Because we do not want to drill the bore we will
fit the probes to an expanding collar that can be
slid into the bore - The position will be locked by means of a taper
clamp to expand the collar - Need to finalise detailed design
24Installation - sequence
- The following slides shows a first attempt of
installation stages of the tracker into the
solenoid - Serve as a basis for a debate/discussion
- The installation procedure will be evolved by all
interested parties - It should be noted that all of this work will
need to take place in a light-controlled
environment, no ultra-violet light to avoid
damage on scintillating fibres
25Installation - requirements
- To carry out the installation work we will need
at least 2m of clear working area in front of the
solenoid - We hope that this is achievable either by
removing equipment in front of the solenoid or as
is more likely, by moving the solenoid sideways
out of the beam line - The solenoid and its kit would sit on a plinth
and it would move as one - As already stated we will need this area to be
light controlled, this will probably be achieved
by building a tent structure over the area - We think this is better than having a lock
mechanism for the lights in the MICE-hall, since
other parties can work at the same time, less
scheduling headache
26Installation stage 1
- The patch-panel is fitted and sealed to the
solenoid - Hope to test the seals using cover plates at this
stage
27Installation stage 2
- Alignment jig is fitted into the bore of the
solenoid - feet are adjusted to set the cross hairs on the
same axis as the solenoid bore - azimuthal/z retaining bracket is fitted
- whole assembly surveyed
- The alignment jig works as a Go-gauge for the
final installation
28Installation tracker adjustment
- PTFE foot, which rests on thebore of the
solenoid, is eccentric - PTFE foot can be rotated by turningthe green
outer case that has a locating dog - Once adjusted it can be lockedby turning the
blue internal hex key
Views and sections of the adjustable PTFE foot
and its adjusting/locking tool
29Installation tracker positioning
- The tracker module sits on 4 adjustable feet two
at the front, two at the rear - The tracker module is held down by a sprint
loaded foot at the 12 oclock position - These foot aligns the axis of both tracker and
solenoid - The tracker module is aligned in z and azimuth
by pulling a locating block into a Vee, which
is located using dowels to the patch panel
30Installation stage 3
- The alignment jig is mounted onto the CMM in a
jig that simulates the bore of the solenoid - The alignment jig is surveyed
- CMM Computerised Measuring Machine
31Installation stage 4
- The tracker module is mounted on the same jig
- With the survey from the alignment jig, adjust
the 4 support feet till the same axis as the
alignment jig
32Installation stage 5
- The tracker module, complete with the light guide
support structure, is lifted onto the
installation cradle - The light guide support structure is to ensure
that no damaging forces are exerted on the fibres - Covers will be fitted during transit
33Installation stage 6
- The tracker module is slid into its
pre-determined position inside the bore of the
solenoid - The position will already have been determined
using the target module
34Installation stage 7
- With the tracker in position and secured, the
light guides can now be carefully re-routed to
their final position in the patch panel. - The gas-seal is fitted
- If the external light guides are not to be
attached immediately then light tight/protection
covers will remain fitted. - The light-guides are secured.
- A shield will be fitted to stop any damage on
light guides during diffuser installation - When the diffuser is installed, the light guide
support structure is removed - If we are not ready to fit the diffuser
mechanism then a cover plate will be attached
35Installation stage 8
- The patch-panel cover is installed and sealed to
the patch-panel - We can repeat the gas seal test at this point
- Now, installation finished!!
- Sequence designed, need to elaborate with all
interested parties
36Infrastructure Land grab
- We need space for
- Cryocooler/Cryostat for VLPC read-out
- Two VME creates, local-DAQ computer, cabling
- He gas system for Cryo/Tracker pipes/cylinders
- Tent for installation 4 x 3 x 3 m3 (x, y, z)
to be fixed with mock-up - Because of the amount of equipment required to
fit into the area and possible conflicts this may
cause, it has been decided to build a 3D
virtual model of the region - We need to be sure that all of our fibres can be
accommodated in the fibre length allowed, so this
model will be the first step in this process - We plan to build a full size mock-up of this
region to convince ourselves that what we have
designed is feasible - The patch-panel, fibre run,trellis and VLPC
unit have been modelled and the idea is (we hope)
to ask Stephanie to assemble all of the 3D
modelled items into a master model based on
Tonys floor layout
37Infrastructure layout 1st attempt
38Infrastructure layout 2nd attempt
- This was an attempt to achievea shorter fibre
run - In 2D-model the longest run increased from 1884
mm to 2200 mm - Need to elaborate in 3D-modeland with a full
size mock-up - Activities initiated
39Infrastructure/Operation - Gas
- Maximum volume to be filled per
trackerV(solenoid) pi0.422.735 1.38
m3 (depends on window position)V(p-panel)
pi0.85520.1/2 0.12 m3 (guess)V(total)
1.5 m3 1500L - To fill a tracker, 5 hours with flow rate of
300L/hour - In operation mode, 30L/hour? 7000L (60kg)
cylinder every 9.7 days - Needs- gas cylinder- pressure regulator-
flowmeter- bubbler- supply/exhaust pipes-
shutoff valve?- overpressure valve? - He gas leaks from patch panel WILL NOT cause
oxygen deficit. The MICE hall is ventilated
Exhaust to high release or outside
40Helium/vacuum window - study
- Chris Rogers study on aperture
- measure acceptance of MICE cooling channel in 2D
phase space - The detector and diffuser apertures should be at
least large enough to transport these muons
Apertures m Apertures m Apertures m
Small LH2 RF Large LH2 RF Large LH2 Only
Diffuser z -6.011 0.14 0.18 0.19
Window 1 z-3.8 0.19 0.25 0.28
Window 2 Z3.8 0.24 0.29 0.29
Beam envelope
41Helium/vacuum window - design
- Decoupled from solenoid
- z-position will be adjusted to havesmaller beam
envelope - Make it thinner 0.5mm
- Effects of window will be studied with G4MICE
Top Hat
Top Hat cylindrical length machined to suit
position of the window
Radial distance of window curvature 360mm
Window to have 396mm OD
42Summary
- We will build fifth station to establish
production line for the tracker - As soon as doublet-layer becomes available,
August - Mechanical designs for station/tracker assembly
almost complete - Need to elaborate some details and require a
final set of engineering drawings - There is more work to be carried out on the
installation/layout, helium/vacuum window, gas
system - Works initiated