Engineering (Mechanical) - PowerPoint PPT Presentation

1 / 42
About This Presentation
Title:

Engineering (Mechanical)

Description:

Engineering (Mechanical) Geoff Barber Contents Station assembly Tracker assembly Installation Patch-panel Installation procedure Infrastructure/Operation Gas system ... – PowerPoint PPT presentation

Number of Views:278
Avg rating:3.0/5.0
Slides: 43
Provided by: TakashiMa
Category:

less

Transcript and Presenter's Notes

Title: Engineering (Mechanical)


1
Engineering (Mechanical)
  • Geoff Barber

2
Contents
  • Station assembly
  • Tracker assembly
  • Installation
  • Patch-panel
  • Installation procedure
  • Infrastructure/Operation
  • Gas system
  • Helium/vacuum window
  • Summary

3
Station assembly
  • We already have built four stations for a
    prototype tracker module
  • We learned a lot from this experience as well as
    from the KEK test beam results
  • We will incorporate quality assurance steps to
    station assembly procedure to eliminate source of
    problems for light-loss and fibre mapping
  • In the following slides, station assembly
    procedure for the production of stations is
    explained step by step

4
Station assembly - sequence
  • Receive doublet-layers from FNAL
  • Visual inspection of the doublet-layers for any
    damage caused in transit
  • Align the doublet-layers on a vacuum chuck
  • Bundle seven fibres with rubber sleeves (QA)
  • Thread the bundle into a station connector (QA)
  • Put the vacuum chuck on an assembly jig
  • Fix a carbon-fibre station to the assembly jig
  • Glue the doublet-layers to carbon-fibre station
  • Attach doublet-layers connectors to the
    carbon-fibre station
  • Cut the fibres
  • Pot the fibres
  • Polish the fibres

5
Station assembly - tools
  • Station holder
  • Bundling Comb
  • Connectorisation bridge
  • Vacuum chuck
  • Alignment jig

6
Station assembly - numbering
  • Unique numbering scheme defined to make sure
    correct fibre mapping
  • Start bundling from the centre fibre, marked
    during doublet-layer manufacturing
  • QA procedure ensures correct bundling with comb

7
Station assembly - bundling
  • Align doublet-layer on vacuum chuck
  • comb to help identify error during bundling is
    being manufactured at Liverpool with aluminium
  • Bundling procedure with comb will be
    established with the existing fibre ribbon

8
Station assembly - connector
  • Bundle is threaded into the correct hole in the
    connector on bridge
  • QA ensures correct threading procedure to be
    defined

QA gauge
View W 20 Way Bundles 1 20 To Bulkhead
Connectors 1, 6, 11, 16 21
1
5
3
4
2
6
8
10
7
9
11
13
12
14
15
16
Station connector Viewed from the polished
face. Internal light-guide connector viewed from
rear or fibre entry side.
18
17
20
19
x
x
9
Station assembly final steps
View of the station onto the polished face of the
connector
  • Put the vacuum chuck on an assembly jig
  • Fix a carbon-fibre station to the assembly jig
  • Glue doublet-layer to carbon-fibre station
  • Connectors on bridge is attached to the correct
    position
  • Cut fibres
  • Pot fibres
  • Polish fibres

10
Station assembly - prototype
11
Station assembly - summary
  • We have built four stations. The fourth station
    design was improved by the experience gained
    during the three stations assembly.
  • We have identified the source of problems to be
    fixed by the KEK test beamconnector hole
    alignment, fibre bundling and fibre
    connectorisation
  • QA procedures will rectify the problems during
    station assembly, see Pauls talk
  • We will build the fifth station with the improved
    assembly procedure which incorporates QA
  • We will be ready to produce the stations soon.
  • TODO
  • Establish QA procedures with comb and bridge,
    see Pauls talk

12
Tracker assembly
  • We have built a tracker prototype with four
    stations
  • Assembly scheme for the prototype will be used
    for the three production version of tracker
    modules with five stations
  • Before starting assembly we need to fix the
    station spacing, see Malcolms talk

13
Tracker assembly - space frame I
  • Space frame between stations connects
  • two stations together
  • Barrel
  • Gluing fillet
  • Structural tube
  • Locating foot
  • Foot design
  • improved from
  • prototype

14
Tracker assembly - space frame II
  • These are the parts used for the prototype
  • Close up view of the space frame
  • feet and structural tubes

15
Tracker assembly - jigs
  • These are jigs used for the prototype assembly
  • Jigs to be made after fixing station spacing
  • Could be outsourced, the possibility will be
    investigated

16
Tracker assembly - light-guide
  • Channel map for station 1
  • Length of the light-guide to be determined after
    fixing the station spacing

17
Tracker assembly - prototype
  • Four stations prototype without light-guides
  • Equipped with light-guides
  • We will build three more trackers one for spare

18
Tracker assembly - summary
  • We have built a tracker prototype with four
    stations
  • Assembly tools and scheme for the prototype will
    be used for the production version
  • TODO
  • fix the station spacing, see Malcolms talk

19
Installation
  • We need to install the tracker module inside the
    bore of the solenoid module
  • Damages to the tracker during the installation
    procedure should be prevented
  • In the following slides, patch-panel and
    installation procedure is explained step by step

20
Installation patch-panel
  • Works as a fan-out for light-guides
  • Gas-tight with O-ring to contain He
  • 25 holes for fibre connectors
  • 1 hole for hall probe field monitoring service

21
Installation pp and diffuser
  • The cover will need to be stiffened and tied back
    to the solid region where the patch-panel is
    mounted to the solenoid
  • We have allowed a bore of 331Ø in the cover with
    a series of holes and a position for an O-ring
  • Responsibilities allocated
  • Need to finalise detailed design

Detail Drawing almost complete
22
Installation pp ext. light-guide
  • External light-guide makes one to one connections
    between the patch-panel connector and the VLPC
    128 way connectors.
  • O-ring incorporated to ensure a gas seal
  • Length of the external light-guide to be fixed
    with a full-size mock-up

Patch-panel connector
VLPC connector
23
Installation Hall-probe mount
  • Hall-probe can be fixed to a collar that will be
    attached to the bore of the solenoid
  • Because we do not want to drill the bore we will
    fit the probes to an expanding collar that can be
    slid into the bore
  • The position will be locked by means of a taper
    clamp to expand the collar
  • Need to finalise detailed design

24
Installation - sequence
  • The following slides shows a first attempt of
    installation stages of the tracker into the
    solenoid
  • Serve as a basis for a debate/discussion
  • The installation procedure will be evolved by all
    interested parties
  • It should be noted that all of this work will
    need to take place in a light-controlled
    environment, no ultra-violet light to avoid
    damage on scintillating fibres

25
Installation - requirements
  • To carry out the installation work we will need
    at least 2m of clear working area in front of the
    solenoid
  • We hope that this is achievable either by
    removing equipment in front of the solenoid or as
    is more likely, by moving the solenoid sideways
    out of the beam line
  • The solenoid and its kit would sit on a plinth
    and it would move as one
  • As already stated we will need this area to be
    light controlled, this will probably be achieved
    by building a tent structure over the area
  • We think this is better than having a lock
    mechanism for the lights in the MICE-hall, since
    other parties can work at the same time, less
    scheduling headache

26
Installation stage 1
  • The patch-panel is fitted and sealed to the
    solenoid
  • Hope to test the seals using cover plates at this
    stage

27
Installation stage 2
  • Alignment jig is fitted into the bore of the
    solenoid
  • feet are adjusted to set the cross hairs on the
    same axis as the solenoid bore
  • azimuthal/z retaining bracket is fitted
  • whole assembly surveyed
  • The alignment jig works as a Go-gauge for the
    final installation

28
Installation tracker adjustment
  • PTFE foot, which rests on thebore of the
    solenoid, is eccentric
  • PTFE foot can be rotated by turningthe green
    outer case that has a locating dog
  • Once adjusted it can be lockedby turning the
    blue internal hex key

Views and sections of the adjustable PTFE foot
and its adjusting/locking tool
29
Installation tracker positioning
  • The tracker module sits on 4 adjustable feet two
    at the front, two at the rear
  • The tracker module is held down by a sprint
    loaded foot at the 12 oclock position
  • These foot aligns the axis of both tracker and
    solenoid
  • The tracker module is aligned in z and azimuth
    by pulling a locating block into a Vee, which
    is located using dowels to the patch panel

30
Installation stage 3
  • The alignment jig is mounted onto the CMM in a
    jig that simulates the bore of the solenoid
  • The alignment jig is surveyed
  • CMM Computerised Measuring Machine

31
Installation stage 4
  • The tracker module is mounted on the same jig
  • With the survey from the alignment jig, adjust
    the 4 support feet till the same axis as the
    alignment jig

32
Installation stage 5
  • The tracker module, complete with the light guide
    support structure, is lifted onto the
    installation cradle
  • The light guide support structure is to ensure
    that no damaging forces are exerted on the fibres
  • Covers will be fitted during transit

33
Installation stage 6
  • The tracker module is slid into its
    pre-determined position inside the bore of the
    solenoid
  • The position will already have been determined
    using the target module

34
Installation stage 7
  • With the tracker in position and secured, the
    light guides can now be carefully re-routed to
    their final position in the patch panel.
  • The gas-seal is fitted
  • If the external light guides are not to be
    attached immediately then light tight/protection
    covers will remain fitted.
  • The light-guides are secured.
  • A shield will be fitted to stop any damage on
    light guides during diffuser installation
  • When the diffuser is installed, the light guide
    support structure is removed
  • If we are not ready to fit the diffuser
    mechanism then a cover plate will be attached

35
Installation stage 8
  • The patch-panel cover is installed and sealed to
    the patch-panel
  • We can repeat the gas seal test at this point
  • Now, installation finished!!
  • Sequence designed, need to elaborate with all
    interested parties

36
Infrastructure Land grab
  • We need space for
  • Cryocooler/Cryostat for VLPC read-out
  • Two VME creates, local-DAQ computer, cabling
  • He gas system for Cryo/Tracker pipes/cylinders
  • Tent for installation 4 x 3 x 3 m3 (x, y, z)
    to be fixed with mock-up
  • Because of the amount of equipment required to
    fit into the area and possible conflicts this may
    cause, it has been decided to build a 3D
    virtual model of the region
  • We need to be sure that all of our fibres can be
    accommodated in the fibre length allowed, so this
    model will be the first step in this process
  • We plan to build a full size mock-up of this
    region to convince ourselves that what we have
    designed is feasible
  • The patch-panel, fibre run,trellis and VLPC
    unit have been modelled and the idea is (we hope)
    to ask Stephanie to assemble all of the 3D
    modelled items into a master model based on
    Tonys floor layout

37
Infrastructure layout 1st attempt
38
Infrastructure layout 2nd attempt
  • This was an attempt to achievea shorter fibre
    run
  • In 2D-model the longest run increased from 1884
    mm to 2200 mm
  • Need to elaborate in 3D-modeland with a full
    size mock-up
  • Activities initiated

39
Infrastructure/Operation - Gas
  • Maximum volume to be filled per
    trackerV(solenoid) pi0.422.735 1.38
    m3 (depends on window position)V(p-panel)
    pi0.85520.1/2 0.12 m3 (guess)V(total)
    1.5 m3 1500L
  • To fill a tracker, 5 hours with flow rate of
    300L/hour
  • In operation mode, 30L/hour? 7000L (60kg)
    cylinder every 9.7 days
  • Needs- gas cylinder- pressure regulator-
    flowmeter- bubbler- supply/exhaust pipes-
    shutoff valve?- overpressure valve?
  • He gas leaks from patch panel WILL NOT cause
    oxygen deficit. The MICE hall is ventilated

Exhaust to high release or outside
40
Helium/vacuum window - study
  • Chris Rogers study on aperture
  • measure acceptance of MICE cooling channel in 2D
    phase space
  • The detector and diffuser apertures should be at
    least large enough to transport these muons

Apertures m Apertures m Apertures m
Small LH2 RF Large LH2 RF Large LH2 Only
Diffuser z -6.011 0.14 0.18 0.19
Window 1 z-3.8 0.19 0.25 0.28
Window 2 Z3.8 0.24 0.29 0.29
Beam envelope
41
Helium/vacuum window - design
  • Decoupled from solenoid
  • z-position will be adjusted to havesmaller beam
    envelope
  • Make it thinner 0.5mm
  • Effects of window will be studied with G4MICE

Top Hat
Top Hat cylindrical length machined to suit
position of the window
Radial distance of window curvature 360mm
Window to have 396mm OD
42
Summary
  • We will build fifth station to establish
    production line for the tracker
  • As soon as doublet-layer becomes available,
    August
  • Mechanical designs for station/tracker assembly
    almost complete
  • Need to elaborate some details and require a
    final set of engineering drawings
  • There is more work to be carried out on the
    installation/layout, helium/vacuum window, gas
    system
  • Works initiated
Write a Comment
User Comments (0)
About PowerShow.com