Title: LHC Commissioning Phases
 1LHC Commissioning Phases
- Detailed Measurements at 450 GeV 
 - presented by Frank Zimmermann 
 - on behalf of the LHCCWG 
 - Particular thanks to 
 - Stefano Redaelli, Massimo Giovannozzi, the EICs, 
 - Roger Bailey, Stephane Fartoukh, Brennan Goddard, 
 -  Rhodri Jones, Verena Kain, Mike Lamont, 
 - Ralph Steinhagen, Jan Uythoven, Jorg Wenninger
 
  2LHC Commissioning Phase 4  Detailed 
Measurements at 450 GeV 
- Phase A.4 Detailed Measurements at 450 GeV 
 - Objectives 
 - Entry conditions 
 - Preconditions and tools 
 - Commissioning procedures with a few examples 
 - Exit conditions 
 - Summary
 
  3LHC Stage A Commissioning phases
Phases for full commissioning Stage A (pilot 
physics run)
Phase Description
A.1 Injection and first turn  injection commissioning threading, commissioning beam instrumentation.
A.2 Circulating pilot establish circulating beam, closed orbit, tunes, RF capture 
A.3 450 GeV initial commissioning  initial commissioning of beam instrumentation, beam dump 
A.4 450 GeV optics beta beating, dispersion, coupling, non-linear field quality, aperture
A.5 Increasing intensity prepare the LHC for unsafe beam
A.6 Two beam operation - colliding beams at 450 GeV 
A.7 Snap-back and ramp single beam 
A.8 Bringing beams into collision adjustment and luminosity measurement
A.9 7 TeV optics beta beating, dispersion, coupling, non-linear field quality, aperture
A.10 Squeeze commissioning the betatron squeeze in all IP's 
A.11 Physics runs physics with partially squeezed beams, no crossing in IP1 and IP5 
- Basic Objectives 
 - establish linear optics 
 - first assessment of orbit  optics stability 
 - chromaticity control preparing for the ramp 
 - collimator setup in view of higher stored beam 
energies  - aperture validation 
 
  4Detailed Measurements at 450 GeV  Overview of 
Steps Involved
Step Activity Priority
A.4.1 Measure  correct closed orbit 1
A.4.2 Measure  correct linear optics (b, D, ...) 1
A.4.3 Measure and correct transverse aperture 1
A.4.4 Measure momentum aperture 1
A.4.5 Commission collimators  protection devices 1
A.4.6 Detailed rf measurements 1 
A.4.7 Measure  correct global non-linear optics 1 to 3
A.4.8 Commission non-linear correctors 1 to 3
A.4.9 Commission IR bumps 2
A.4.10 Perform injection matching 2
A.4.11 Beam loss studies 2
- Priority categories (71th LTC) 
 - absolutely mandatory, 
 - should be done if possible, 
 - would be nice if it could be done 
 
  5Detailed Measurements at 450 GeV  Beam Entry 
Conditions
- Beam Entry conditions 
 - both beams circulating with lifetime gt 1h 
 - separate commissioning for beam 1 and beam 2 
 - some steps require both beams simultaneously 
 -  (1) orbit/optics correction in the common 
regions (2) D1/D2 transfer function checks 
(3) Parallel separation bumps.  - coasting beams (LHC) and InjectDump mode (few s) 
  - only single bunches, intensities up to a few 1e10 
protons  - nominal beam emittance (value agreed for ramping) 
  - reproducible emittance from injector chain 
 - reduced intensity for studies involving full beam 
loss i.e. momentum aperture, injection failure 
scenarios for these use a few 1e9 protons 
(scraping in the SPS?) 
  6Detailed Measurements at 450 GeV  Optics Entry 
Conditions
- Optics Entry conditions 
 - nominal tunes if possible 
 -  (otherwise, need to first correct coupling on 
special commissioning working point)  - stable/reproducible optics and orbit 
 - reproducible injected beams shot by shot 
 - chromaticity under control
 
  7Dd Measurements at 450 GeV  RF  Magnets Entry 
Conditions
- RF  Magnets Entry conditions 
 - RF fully commissioned for pilot intensities 
(see A.3)  - radial steering fully commissioned 
 - transverse damper commissioned possibility to 
switch it ON/OFF  - COD polarity checked and calibrated 
 - full HWC of higher order corrector circuits  
CCC control  -  - lattice correctors coupling (a2), 
chromaticity (b3), Landau octupoles (b4)  -  - spool pieces sextupole (b3), octupole (b4), 
decapole (b5)  -  - MQX correctors orbit, coupling, dodecapoles 
(b6)  - detector magnets OFF 
 - spectrometers at IP2 and IP8 OFF 
 - HWC of steering magnets for IP separation/crossing
 bumps  - both signs of IP bumps available 
 
  8Dd Measurements at 450 GeV  Instrumentation 
Entry Conditions
- Instrumentation Entry conditions 
 - BPM system - polarity  calibration checked 
expected resolution for single bunches of 1 to a 
few 1e10 p closed orbit  10 micron trajectory 
 50-100 micron - sum signal available imposes 
constraints for the operation with two beams!  
- acquisition synchronized with other devices 
(kickers, wires, ...)  - turn-by-turn 
acquisition available - gt1000-turn acquisition 
- simultaneous 1000-turn acquisition for both 
beams  - BCT - DC BCT's cannot be used at pilot or pilot 
intensities - measurements must rely on the 
fast-BCT measurements (10 accuracy with 1e101 
accuracy with 1e11!) - turn-by-turn acquisition 
synchronized to kicker/bpm/wires/blm  - Beam size measurements - Wire scanners priority 
1 - Ionization profile monitors (IPM's) 
priority 3 - Synchrotron radiation monitor 
priority 2 Absolute calibration lt20 for the 
beam size What is the minimum time between 
consecutive measurements? (Implications, e.g. on 
the minimum rise-time of orbit bumps to measure 
beam profiles before and after beam scraping)  - Beam loss monitors - Signal acquisition for all 
the available monitors - Movable monitors ready 
for use - Dedicated fast acquisitions with 
t_acqlt20ms  - Screens Emittance measurements in the TL for 
pulse-to-pulse monitoring  
  9Dd Measurements at 450 GeV  Controls Entry 
Conditions
- Controls Entry conditions 
 - YASP steering program (already available) - 
Correct and steer the closed orbit Correct and 
adjust single (first) turn (e.g., re-tuning of 
injection areas after orbit bumps) 3- and 
4-corrector bumps with variable amplitude optics 
model to calculate Dp/p  - Automatic application for SLIDING BUMPS could be 
part of YASP or use YASP  - Collimator control software 
 - Control, acquisition, display and logging of all 
required BI monitors (BPM, BCT, BLM, wires, 
etc...) and devices (tune kickers, aperture 
kickers, ...) Simultaneous data taking is 
crucial!  - "Aperture database" - Online update for 
"as-measured" aperture model (location of 
aperture bottlenecks, bump settings that optimize 
aperture).  - (On-line) optics model to get (propagate) optics 
- MAD-X online model or multi-turn application 
with MAD-X interface  - Control of AC dipole from Q meter AC dipole 
interlock commissioned 
  10Dd Measurements at 450 GeV  Addtl HW Entry 
Conditions
- Additional Hardware Entry conditions 
 - tune/aperture kickers 
 -  (commissioned already in A.3) 
 - first use of collimator subset 
 - beam scraping at the SPS 
 -  (generate "pencil" beams or small emittances) 
 - additional devices for aperture measurements - 
commissioning of emittance blow up (?) 
 transverse quadrupole noise? RF noise?  - AC dipole 
 
  11Detailed Measurements at 450 GeV  Stage A.4.1  
Closed Orbit
Step Activity Priority
A.4.1 Measure and correct closed orbit 1
A.4.1.1 Measurement and correction of each arc ABP/OP 1
A.4.1.2 Measurement  correction of each IR (needs another iteration with 2 beams) ABP/OP 1
A.4.1.3 Iterate with improved optics knowledge if/as needed ABP/OP 2
reference closed orbit for the following 
phases orbit corrected within tolerance 
(peakr.m.s.) measurement accuracy to be 
defined much of this done in earlier phases 
already first detailed estimates of orbit 
stability and reproducibility 
 12example A.4.1  sensitivity of orbit feedback to 
b beat
R. Tomas, LHCCWG8
R. Steinhagen, LHCCWG6 
 13Dd Measurements at 450 GeV  Stage A.4.2  
Linear Optics
Step Activity Priority
A.4.2 Measure and correct linear optics 1
A.4.2.1 Polarity checks of MQT, MQS, MQSX ABP/OP 1
A.4.2.2 Coupling ABP/OP 1
A.4.2.3 Beta beat ABP/OP 1
A.4.2.4 Dispersion ABP/OP 1
A.4.2.5 Refined optics model, response matrix, BPM calibration (no beam time) ABP/BI/OP 2
A.4.2.6 Generation of new settings for correctors if necessary(?) ABP/OP 2
A.4.2.7 Additional local beta measurements with K-modulation (IR's, wires, collimators, ...) ABP/OP 2
reference optics for following phases beta beat 
measured (and corrected) within tolerance 
 dispersion measured (and corrected) within 
tolerance b and D are corrected together 
 first detailed estimates of optics stability and 
reproducibility coupling, beta-beat  dispersion 
correction may need second iteration with 
2 beams 
 14example A.4.2.1 - coupling correction
R. Tomas, LHCCWG8 
 15example A.4.2.2 - beta beat correction
R. Tomas, LHCCWG8 
 16Dd Measurements at 450 GeV  Stage A.4.3  
Transv. Aperture 
Step Activity Priority
A.4.3 Measure and correct transverse aperture 1
A.4.3.1 Commission sliding bump software ABP/OP 1
A.4.3.2 Measure global aperture measurements with kick  loss method and/or by exciting orthogonal correctors ABP/OP 1
A.4.3.3 Apply local bumps to center orbit in aperture if needed ABP/OP 2-1
A.4.3.4 Iteration of A.4.3.2 and A.4.3.3 until we achieve tolerances if needed ABP/OP 2-1
A.4.3.5 Commission the aperture database, if available ABP/OP 2
A.4.3.6 Dedicated local aperture measurements (IR's, dump,..) ABP/OP 2
A.4.3.7 Commission other measurement tools (emit. blow-up, AC dipole), cross checks ABP/BI/OP 3
first global aperture measurements detailed 
local aperture measurements in critical 
locations optimization of local bottlenecks 
that become critical at 7 TeV priority 2 becomes 
1 if we squeeze after ramp 
 17example A.4.3.6  local aperture measurements
S. Redaelli, LHCCWG11
Established methods based on BCTs are also 
available inject  dump mode possible 
 18Dd Measurements at 450 GeV  A.4.4  Momentum 
Aperture 
Step Activity Priority
A.4.4 Measure momentum aperture 1
A.4.4.1 Radial steering scans (full beam scraping) ABP/OP 1 
 19Dd Measurements at 450 GeV  A.4.5  Collimators 
 PDs
Step Activity Priority
A.4.5 Commission collimators  protection devices 1
A.4.5.1 Beam based alignment of required collimators (TCPs, TCDQ, TDIs, TCTs, some TCSs) Coll. Team 1
A.4.4.2 Measurements of local beta-functions and beam sizes by collimator scans Coll. Team 1
A.4.4.3 Enter beam-based information into database, define reference settings, ... Coll. Team 1
prepare for limited higher stored energies 
 (ramp or higher intensities at 450 GeV) may 
also be done in phase A.5 
 20example A.4.5.1  beam-based collimator 
alignment in SPS
S. Redaelli, Chamonix 2005 
 21Dd Measurements at 450 GeV  A.4.6  RF 
Measurements
Step Activity Priority
A.4.6 Perform detailed RF measurements 1
A.4.6.1 Final commissioning of the radial loop (if not already done) RF 1
A.4.6.2 Longitudinal profile (parasitic) RF 1 
 22Dd Measurements at 450 GeV  A.4.7  Global 
Nonlinear Optics
Step Activity Priority
A.4.7 Measure and correct global nonlinear optics 1
A.4.7.1 Tune versus Dp/p -gt Q', Q'', ... ABP/OP 1
A.4.7.2 Tune vs amplitude ABP/OP 2 
 23Dd Measurements at 450 GeV  A.4.8  Nonlinear 
Correctors
Step Activity Priority
A.4.8 Commission nonlinear correctors 1
A.4.8.1 Commission control of corrector circuits if not done ABP/OP 1
A.4.8.2 Normal sextupole - polarity checks, local measurement and correction ABP/OP 1
A.4.8.3 Skew sextupole - polarity checks, local measurement and correction ABP/OP 3
A.4.8.4 Normal octupole - polarity checks, local measurement and correction ABP/OP 3
A.4.8.5 Normal decapole - polarity checks, local measurement and correction ABP/OP 3
A.4.8.6 Polarity checks of non-linear MQX correctors ABP/OP 3 
 24example A.4.8.2  check of normal sextupole 
circuits
local b3 correction chromatic phase advance
F. Zimmermann, Chamonix 2003 LHCCWG10
simulated Df for 1s kick for dp/p10-3 and 
dp/p0 3 cases (1) no spool piece mispowered, 
 (2) sextupole circuit KCS45 missing (BPMs 194 to 
257), (3) decapole circuit KCD45 missing we can 
detect missing b3 circuits, but not missing b5! 
 25Dd Measurements at 450 GeV  A.4.9  IR Bumps
Step Activity Priority
A.4.9 Commission IR bumps 1-2
A.4.9.1 Commission separation bumps in all IP's ABP/OP 1-2
A.4.9.2 Commission spectrometer compensation in IR8 ABP/OP 2
A.4.9.3 Commission spectrometer compensation in IR2 ABP/OP 3
priority depends on spectrometer status  physics 
plan 
 26Dd Measurements at 450 GeV  A.4.10  Injection 
Matching
Step Activity Priority
A.4.10 Perform injection matching 2-1
A.4.10.1 trajectory, betatron and dispersion matching with injection (and/or multi-turn) screens only necessary in case of inacceptable emittance growth ABP/BT/OP 2-1
acquisition system and software for OTR injection 
matching monitor available only for LHC Phase II 
(75-ns operation) fine tuning is done in later 
phase, e.g. A.5 
 27Dd Measurements at 450 GeV  A.4.11  Beam Loss 
Studies
Step Activity Priority
A.4.11 Beam Loss Studies 2
A.4.11.1 Beam loss map studies Coll. Team/BI 2
A.4.11.2 Estimate collimation cleaning inefficiency Coll. Team/BI 2-3 
 28Detailed Measurements at 450 GeV  Exit Conditions
- Main exit conditions 
 -  Reference orbit and linear optics under control 
(both beams) as precondition for ramp.  -  Nominal injection optics established. 
 -  Collimators and protection devices set up for 
higher stored energies (ramp or intensity 
increase) - much of this could be done also in 
A.5  -  Chromaticity measurements  corrections 
available for ramp.  -  Machine aperture at injection known. 
 -  First assessment of stability  reproducibility. 
 
  29Summary
- Phase A.4  
 - prepare for ramp and for higher intensity 
 - Main focus is on 
 - orbit control 
 - linear optics control 
 - chromaticity control 
 - aperture control 
 - set up of collimators  protection devices (could 
be in phase A.5)  - stability  reproducibility 
 - At the end of this phase 
 -  - we can ramp pilot bunches to 7 TeV (phase A.7) 
 -  - and/or increase the bunch intensity   
bunches (phase A.5)  
  30Comments
- Detailed measurements at 450 GeV will probably be 
interleaved with pilot-bunch ramps to higher 
energy  - Sorting out D1/D2 transfer function errors may 
later on require measurements with triplet 
alignment optics at 450 GeV  -  
 
  31References
- Web documentation 
 - LHC Commissioning procedures, 
 - LHC Commissioning pages 
 - Documentation and Procedures Phase A4 S. 
Redaelli, EICsV. Kain  - Pertinent LHCCWG presentations 
 - Circulating Beam and RF Capture LHCCWG3 G. 
Arduini, A. Butterworth  - Magnetic Field Fill-to-Fill Reproducibility and 
Differences Between the Two Apertures  -  LHCCWG14 L. Bottura 
 - Beam Instrumentation - BPM, BLM, BCT, Transverse 
Diagnostics  -  LHCCWG3 R. Jones 
 - Commissioning Procedures LHCCWG5  6 V. 
Kain  - Snapback and Ramp with Single Beam LHCCWG7 M. 
Lamont  - 450 GeV Optics IR Aperture and IR Bumps 
LHCCWG13 Y. Papaphilippou  - 450 GeV Optics  Mechanical Aperture and Momentum 
Aperture LHCCWG11 S. Redaelli,  - Overview of Feedbacks and Implications for 
Commissioning LHCCWG6 R. Steinhagen  - 450 GeV Optics  Beta Beating, Coupling, 
Dispersion LHCCWG8 R. Tomas  - Response Matrix Measurements and Analysis 
LHCCWG9 J. Wenninger  - Tracking error measurement and correction 
LHCCWG17 J. Wenninger  - Nonlinear Field Quality Checks LHCCWG10 F. 
Zimmermann