Introduction, requirements of the LHC and LHC injectors - PowerPoint PPT Presentation

About This Presentation
Title:

Introduction, requirements of the LHC and LHC injectors

Description:

OPERATION OF THE LHC BEAMS IN THE SPS E. M tral Introduction, requirements of the LHC and LHC injectors challenges The LHC zoo Many (proton) beams required & LHC ... – PowerPoint PPT presentation

Number of Views:205
Avg rating:3.0/5.0
Slides: 77
Provided by: emet3
Category:

less

Transcript and Presenter's Notes

Title: Introduction, requirements of the LHC and LHC injectors


1
OPERATION OF THE LHC BEAMS IN THE SPS
E. Métral
  • Introduction, requirements of the LHC and LHC
    injectors challenges
  • The LHC zoo ? Many (proton) beams required LHC
    commissioning
  • Main SPS supercycle foreseen in 2008 user names
  • Some procedures references for the nominal beam
  • Some words about the ion beams ( early ion beam
    produced in the SPS in 2007)

2
  • Many thanks to many colleagues from OP, ABP, RF,
    BI for their explanations help during the
    2007 run preparation of this course!
  • See also procedures references (from 2007) done
    by Magali http//sps-documentation.web.cern.ch/SP
    S-documentation/
  • Please do not hesitate for any comment!

3
INTRODUCTION (1/13)
  • 2 main challenges involved in the design of the
    LHC
  • Very high magnetic field to reach the collision
    energies in the TeV range
  • Very high luminosity necessary to provide
    significant event rates at this energy

Beam current
Brightness transverse bunch density
It is limited by - Space-charge effects in the
injectors... - Head-on beam-beam interaction
at collision
It is limited by - Collective instabilities -
Cryogenic load (synchrotron radiation and
wall current) - S.C. magnet quench
4
INTRODUCTION (2/13)
  • ? LHC injectors challenges
  • Preservation of the transverse emittance
    (brightness)
  • Generation of the longitudinal structure (25 ns
    bunch spacing)

5
INTRODUCTION (3/13)
SPS operates above transition ( 21 GeV) for
LHC-type beams
Duoplasmatron Source ? 90 keV (kinetic
energy) LINAC2 Linear accelerator ? 50
MeV PSBooster Proton Synchrotron Booster ? 1.4
GeV PS Proton Synchrotron ? 25 GeV SPS Super
Proton Synchrotron ? 450 GeV LHC Large Hadron
Collider ? 7 TeV
LHC (proton) beam in the injector chain
6
INTRODUCTION (4/13) ? TRANSVERSE EMITTANCE
PRESERVATION
  • The initial transverse emittance is given by the
    duoplasmatron source
  • The beam is then adiabatically bunched and
    accelerated in a Radio Frequency Quadrupole
    (RFQ2) under high space charge conditions
  • Fine-tuning of the 50 MeV Drift Tube Linac (DTL)
    and of the transfer line to the PSB

Normalised, at 1?
Depends on extraction aperture, electrode shape
and space charge
?
?
?
7
INTRODUCTION (5/13) ? TRANSVERSE EMITTANCE
PRESERVATION
  • The beams in the Linac2 are quasi square pulses
    with a length which varies depending on the user
    (the beam length varies between 25 µs and 120 µs
    and it is limited at the source)
  • The nominal LHC requirement is a beam of 180 mA
    in 30 ?s at the entrance of the PSBooster
  • The transverse normalised rms beam emittance is
    1.2 ?m
  • ? Challenge of transverse emittance preservation
    in the injectors
  • - PSBooster ejection ? 2.5 ?m
  • - PS ejection ? 3 ?m
  • - SPS ejection ? 3.5 ?m
  • - LHC top energy ? 3.75 ?m

8
INTRODUCTION (6/13) ? LONGITUDINAL BEAM STRUCTURE
  • The generation of the nominal bunch train for LHC
    (25 ns bunch spacing) is done in the PS
  • Double-batch injection from PSBooster due to
    space charge in the PSBooster ? Rings 3-4-2-1-3-4
  • Bunch splittings used instead of debunching /
    rebunching due to longitudinal microwave
    instability

Must be the 1st!
LHC Design Report, Ch. 7, p. 45
9
INTRODUCTION (7/13) ? SPS CHALLENGES
MKE kickers issues
  • Impedance reduction programme in the SPS has made
    a major contribution to the ability of the SPS to
    produce the LHC beam
  • Shielding of specific equipment, such as the
    magnetic septa, identified as an impedance source
  • Shielding of some 900 intermagnet pumping ports
    has reduced significantly the resonant impedance
    in the machine and increased the stability of the
    LHC beam
  • The nominal beam has successfully been
    accelerated to 450 GeV/c, despite the discovery
    that the electron cloud effect is a major issue
    for the SPS ? Continued machine development to
    understand and cure the phenomena in the SPS has
    been accompanied by additional studies using the
    SPS as a test-bed for the LHC. Periods of beam
    conditioning are now routinely used to scrub
    the surface of the vacuum chambers, reduce the
    secondary electron yield and minimise the vacuum
    pressure rise

10
INTRODUCTION (8/13) ? SPS BEAM PARAMETERS
Tolerance in bunch intensity? 10
Tolerance in trans. emittance? 20
Tolerance in long. emittance? 20
11
INTRODUCTION (9/13) ? NOMINAL LHC FILLING SCHEME
  • PS cycle length 3.6 s
  • SPS cycle length 21.6 s
  • LHC filling time (for the 2 rings) 8 min 38 s
    ( 12 SPS cycles of 21.6 s per beam ? 24 in
    total, i.e. a filling time of 24 ? 21.6 s 518.4
    s)

12
INTRODUCTION (10/13) ? NOMINAL LHC BEAM IN THE
SPS IN 2004
3.3 ?1013 p at 450 GeV/c (i.e. 4 ? 72 288
bunches with 1.15?1011 p/b)
13
INTRODUCTION (11/13) ? NOMINAL LHC BEAM IN THE
SPS IN 2006
3.6 ?1013 p at 450 GeV/c (i.e. 4 ? 72 288
bunches with 1.24?1011 p/b)
14
INTRODUCTION (12/13) ? NOMINAL (LOW INTENSITY)
BEAM EXTRACTED FROM THE SPS IN 2007
Shown by S. Myers on 26/02/08 (AB meeting)
15
INTRODUCTION (13/13) ? NOMINAL (LOW INTENSITY)
BEAM EXTRACTED FROM THE SPS IN 2007
Shown by S. Myers on 26/02/08 (AB meeting)
16
THE LHC BEAM ZOO (1/4)
M. Benedikt, LHC-OP-ES-0002 rev 1.0 (2004)
Pilot safety beam
  • Interest in the 50 ns variant has been
    resuscitated (since few months) to try and
    satisfy the need for low luminosity in IP2!

17
THE LHC BEAM ZOO (2/4)
Needed before each physics coast
18
THE LHC BEAM ZOO (3/4)
19
THE LHC BEAM ZOO (4/4)
20
MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(1/6)
26 GeV/c or acceleration up to 37 GeV/c
  • SFTLONG1 (13 BP) CNGS1 (5) CNGS2 (5) CNGS3
    (5) LHCFAST1 (7) MD1/2 (5) 40 BP 48 s
  • Later, when LHC is filling properly we will have
    to switch to an LHC filling supercycle

21
MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(2/6)
  • In 2007
  • SPS timing user names changed to beam-type names
  • At the same time we got the possibility via LTIMs
    to activate a given RF MMI stack for a given
    timing user ? Tended to 'decouple' the RF MMI
    stack name from the timing user name
  • The BI settings are organized by beam type and
    can be loaded to any timing user ? This also
    decouples the BI settings from the timing user
    names
  • In 2008 ? The idea is to go back to a given
    timing user associated to a certain SPS magnetic
    cycle more than to a certain beam type
  • LHC1 LHC2 for nominal MAGNETIC LHC cycles
  • LHCFAST1 LHCFAST2 for the short LHC MAGNETIC
    cycles
  • LHCION1 LHCION2 for ion MAGNETIC cycles

22
MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(3/6)
For the short magnetic cycles
24 in 2007
32 in 2008
23
MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(4/6)
  • ? Example of a Long MD cycle in 2008
  • Timing user LHC1. LSA settings mapped to that
    user
  • If we take a nominal beam on the cycle, RF MMI
    stack for LHC1 mapped to stack LHC25NS. BI
    settings for LHC-NOMINAL mapped to LHC1
  • If we take a pilot beam on the cycle, RF MMI
    stack for LHC1 mapped to stack LHCPILOT. BI
    settings for LHC-PILOT mapped to LHC1
  • 'Early' LHC filling SC with two fast LHC cycles.
    Cycles are mapped to timing users LHCFAST1
    LHCFAST2. LSA settings mapped to those users
  • If we take a pilot beam on the 2 cycles, RF MMI
    stack for LHCFAST1 LHCFAST2 mapped to stack
    LHCPILOT. BI settings for LHC-PILOT mapped to
    LHCFAST1 LHCFAST2
  • If we take an individual bunch on the 2 cycles,
    RF MMI stack for LHCFAST1 LHCFAST2 mapped to
    stack LHCINDIV. BI settings for LHC-INDIV mapped
    to LHCFAST1 LHCFAST2
  • If we take 12 bunches (1 PSB ring) on the 2
    cycles, RF MMI stack for LHCFAST1 LHCFAST2
    mapped to stack LHC25NS. BI settings for
    LHC-NOMINAL mapped to LHCFAST1 LHCFAST2

24
MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(5/6)
Different acceleration between NOMINAL and FAST
cycles
4320 (or 15120)
7590 (or 18390)
60 (or 10860)
25
MAIN SPS SUPERCYLE FORESEEN IN 2008 USER NAMES
(6/6)
The (proton) LHC user names in the PS PSB
26
ALTERNATIVE FILLING SCHEME!
SOME PROCEDURES REFERENCES FOR THE NOMINAL (4 ?
72 BUNCHES) BEAM
To see how things vary in this case
FILLING PATTERN (1/3)
NOMINAL FILLING SCHEME!
27
4 ? 72 bunches
FILLING PATTERN (2/3)
28
5 ? 48 bunches
FILLING PATTERN (3/3)
58
115
172
229
9
9
9
9
Batch 5
48
48
48
48
48
1.2 s
1.2 s
1.2 s
1.2 s
1.2 s
570
285
855
1140
29
PROCEDURE TO SET UP THE INJECTION (1/4)
  • Check that the PS is not in simulated frequency

6 BPM of TT2 4 BPM in TT10
  • TT10 BP settings

Last 10 BPM of TT10
Couplers with logarithmic amplifiers in TT10 ? No
gain
30
PROCEDURE TO SET UP THE INJECTION (2/4)
  • Injection kickers settings

The first 3 kickers can give until 11 ?s,
whereras the 4th one gives 2.5 ?s
31
PROCEDURE TO SET UP THE INJECTION (3/4)
32
PROCEDURE TO SET UP THE INJECTION (4/4)
33
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(1/13)
ENERGY MATCHING PROCEDURE
- Inject the beam. Adjust BSPS till the first
turn is centered - Switch on RF (if not already
done) - Measure the orbit (about 100 ms after
injection) - Check the position at which the
beam is captured If the beam is not centered,
(that means the energy in the PS is such that
the revolution period in the SPS does not
correspond to the RF frequency in the SPS),
adjust BSPS till the beam is centered after
capture - The first turn is then no longer
centered - BPS should be adjusted (so as to
adjust the beam energy). - An excel spreadsheet
can be used to determine by which amount BPS
should be changed
34
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(2/13)
  • Tunes (measured) ? To avoid slow beam losses from
    resonances (ecloud, space charge tune spreads)
  • SPS Control  ? SPS Beam Control ? New Trim editor
  • Qx ? 26.13
  • Qy ? 26.185
  • When there are more than 1 injection, Qx
    increases with the intensity and Qy decreases
    with the intensity (Laslett tune shift) ? One has
    to compensate for this effect
  • In order to keep the coherent tune constant the
    Qx settings need to be decreased by 0.008 in
    correspondence of every injection and Qy must be
    increased by 0.005
  • ? Jorg added in 2007 a menu in the MultiQ to
    correct the tune shift for each injection GO in
    the 'Tools' menu (main program toolbar) and check
    the box 'Show LHC beam "Injection Q"....'. This
    will make the appropriate menu/DV plot
    appear/disappear

35
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(3/13)
  • Chromaticities (measured) ? To stabilize the beam
    with respect to the instabilities due to single
    bunch (effects from electron cloud)
  • SPS Control  ? SPS Beam Control ? New Trim editor
  • ?x ? 0.2
  • ?y ? 0.4
  • BEWARE DO NOT TRIM THE RADIAL STEERING BEFORE
    THE LAST INJECTION (even for chromaticity
    measurements). This would change the RF frequency
    we are sending to the PS - and the 40 and 80 MHz
    cavities will not like it!!! The radial position
    can be trimmed after the last injection
  • Octupoles settings ? To achieve a machine as
    linear as possible
  • SPS Control  ? SPS Beam Control ? New Trim editor
  • H - 1 m-4 (Settings are not critical, but they
    shouldn't be too high ? Not larger than about 1
    m-4)
  • V 0

36
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(4/13)
  • Transverse dampers ? The transverse dampers are
    essential in the horizontal direction in order to
    damp the instabilities due to coupled bunches
    (effects from electron clouds and resistive
    wall). In the vertical plane they are mainly used
    to damp resistive wall instability
  • Gain (for the nominal beam)
  • Horizontal 23 dB
  • Vertical 15 dB
  • For 1 bunch or 12 bunches OFF
  • For 72 bunches ? There are 2 pairs of transverse
    dampers per plane. They should be ON during the
    whole cycle

37
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(5/13)
  • Timings ? SPSOP CCM ? Working Set ? RF-SPEC ?
    SPSRF7
  • Switching on timings
  • "tdamper h1 on opera"
  • "tdamper h2 on opera"
  • tdamper v1 on opera
  • tdamper v2 on opera"
  • Settings
  • Timings defined with respect to event
    SIX.F1KFO-CT
  • Coarse delay 995 ms (? i.e. 5 ms before 1st
    injection)
  • Switching off timings
  • "tdamper h1 off opera"
  • "tdamper h2 off opera"
  • tdamper v1 off opera
  • tdamper v2 off opera"
  • These should always be ENABLED
  • Settings
  • Timings defined with respect to event
    SIX.F1KFO-CT
  • Coarse delay 20000 ms

Forewarning 1000 ms before first occurence of
injection
OFF timing should be a few ms after the timing
of the standard dump
38
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(6/13)
  • MOPOS settings

39
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(7/13)
40
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(8/13)
Averaging over 5 orbits
41
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(9/13)
BEAM DUMP SETTINGS
42
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(10/13)
TT2 / TT10 LINE
May be not the latest optics!
43
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(11/13)
Max ?y QD ODD number
Max ?x QF EVEN number
SPS RING
?? ? 90º
SPS transverse tune ? 6 ? (18 / 4) 27!
? Qx ? 26.13 and Qy ? 26.18
44
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(12/13)
TI2
45
PROCEDURE TO SET UP THE MACHINE TRANSVERSALLY
(13/13)
TI8
46
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(1/13)
  • RF loops
  • PHASE LOOP (measures the difference between the
    phase of the RF and the phase from the beam and
    tries to minimize it)
  • SYNCHRO LOOP ? We stay always on the synchro loop
    instead of going at some point on the radial loop
    for acceleration (we cannot do this with the FT
    beams because transition is crossed)
  • BTRAIN is enabled at the beginning the ramp and
    switch off at the end of the ramp (Bup and Bdown
    are 0.1 Gauss)

47
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(2/13)
  • 200 MHz TWC
  • Feedforward (not used on FT beam) 1-turn delay
    feedback together (send correction to the cavity
    through a transmitter) ? To combat the beam
    loading
  • Long. feedback (called also damper) ? Used since
    the injection, and then the gain is adjusted
    (high gain around the injections for injection
    damping), to combat coupled-bunch instabilities
  • Injection into 2 MV bucket (mismatched)
  • 800 MHz TWC
  • Bunch shortening mode

Matched voltage is lt 1 MV
48
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(3/13)
  • Timings
  • At - 425 ms RF ON (TWC200)
  • Phase loop ON (fprog) synchro loop ON
  • 4 injections
  • Before TWC 800 ON in bunch shortening mode after
    the 4th inj. Now it is ON already from the
    beginning due to the MKE kickers
  • Max Bdot 0.35 T/s
  • At 270 GeV/c, longitudinal blow-up done with
    phase modulation on 200 MHz (to have the shortest
    bunch length on the flat-top, otherwise one has
    coupled-bunch instabilities). It is active for
    100-200 ms, with an efficient time of 10-20 ms
  • ?L 0.45 eVs at the end of the flat-bottom and
    it is 0.6-0.7 eVs on the flat-top
  • Synchro with LHC
  • Adiabatic voltage to send the shortest bunch
    lengths

49
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(4/13)
? Example of bunch length with nominal (4?72
bunches) beam but low intensity ( 2.5E13 p)
V200MHz 104 V
Full (4?) bunch length ns/100
V800MHz 103 V
Beam momentum GeV/c
Must enter in the LHC 2.5 ns bucket
50
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(5/13)
  • Injection frequency
  • - Value 200.264550 MHz ? injection B field
    1170.3 Gauss)
  • - Setting SPS Control ? SPS Equipment Control ?
    SPS RF
  • ? SPS RF Control ? RF Synchro ? Injection B field
  • ? select appropriate MMI target (MD1, or LHC25ns,
    ...)
  • ? Write 1170.3 Gauss (corresponds to 200.264550
    MHz)
  • Injection pulses ? Sets the delay on top of the
    prepulse sent by
  • the PS machine, in bucket number
  • - Value 5500
  • - Setting SPS Control ? SPS Equipment Control ?
    SPS RF ? SPS RF Control ? RF Synchro ? Injection
    pulses
  • ? select appropriate MMI target  (MD1, or
    LHC25ns, ...)
  • ? Write 5500

51
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(6/13)
  • Injection bucket selector ? Defines where the
    beam is placed
  • in the SPS (bucket number for 1st bunch in 1st
    batch)
  • - Value 3881 for first batch, 3881 400 ?
    (n-1) for the nth batch
  • - Note this value could change from one day to
    the
  • other in first turn, check that the first batch
    is placed
  • in the right place
  • - Display
  • - SPS Control ? SPS Beam Measurements ? Mountain
    Range
  • - The bunch should be in the centre

52
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(7/13)
  • Measurement
  • SPS Control ? SPS Beam Measurements
  • ? LHC First Bunch Bucket Error
  • This application measures the error with respect
  • to the injection bucket selector. It should be 0.
  • If not correct the injection bucket selector by
    the
  • appropriate amount (indicated by the application
    modulo 4620).

53
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(8/13)
  • Setting
  • SPS Control ? SPS Equipment Control
  • ? SPS RF ? SPS RF Control ? RF Synchro ? Inj.
    bucket selector
  • ? select appropriate MMI target (MD1, or LHC25ns,
    ...)
  • ? Write ...

54
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(9/13)
  • Injection phase ? When there is a change of
    injection bucket,
  • there might be a small injection phase error.
  • The bunches will oscillate in the first few
    turns.
  • The phase loop will try to correct this effect
    quickly.
  • Value 99 (Note This value can change from one
    day to another )
  • Display
  • SPS Control ? SPS Beam Measurements ? Mountain
    Range
  • Some oscillations would be visible in the
    mountain range
  • display
  • Trouble shooting the bunch should be well
    centered at 11 ns.
  • If it is off by 2.5 ns (half a bucket) the
    "injection phase" is
  • wrong by 180 degrees.
  • If it is off by 5 ns (one bucket) it is the
    "injection bucket
  • selector" which is wrong by one unit

55
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(10/13)
  • OASIS
  • ? Connect global ? SPS ? RF LHC Loops
  • If there is an offset, one should increase the
    injection
  • phase accordingly (about 1 degree per 10 mV
    offset)
  • Setting
  • SPS Control ? SPS Equipment Control ? SPS RF
  • ? SPS RF Control ? RF Synchro ? Injection phase
  • ? select appropriate MMI target (MD1, or LHC25ns,
    ...)
  • ? Use only the 1st injection
  • ? Write ...

56
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(11/13)
57
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(12/13)
  • Phase sampling
  • Value 3480
  • Setting
  • TWC 200 MHz Low level 
  • ? Phase Loop ? PL Cycle Select
  • ? select appropriate MMI target  (MD1, or
    LHC25ns, ...)
  • ? Phase sampling
  • ? Parameter set number 2
  • BU Bunch 3480

58
PROCEDURE TO SET UP THE MACHINE LONGITUDINALLY
(13/13)
  • B start ?This is the timing at which RF switches
    to the frequency
  • program (following changes in magnetic field)
  • MTG event "SX.ST-RAMP-CTM" enabled and set to
    10860 ms
  • SPSOP CCM ? Working Set ? RF-SPEC ? SPSRF6
  • "pLHC frequency program b pulses on"
  • Settings
  • Timing defined with respect to event
    SX.S-RAMP-CT
  • (start of the ramp)
  • Delay is 0
  • "pLHC frequency program b pulses off"
  • Settings
  • Timing defined with respect to event
    SX.S-SFLATTOP-CT
  • (end of flat top)
  • Delay is 30

59
MEASURING BEAM PARAMETERS (1/12)
  • Transverse emittance
  • In the PS
  • Fast Wire Scanners (2 H with Dx ? 0 2 V)
  • In the TT2-TT10 transfer line
  • SEM wires SEM grids ? Without PS bunch rotation
    (otherwise meas. perturbed by ecloud!)

60
MEASURING BEAM PARAMETERS (2/12)
61
MEASURING BEAM PARAMETERS (3/12)
  • OTR (Optical Transition Radiation)
  • 4 in TT10 1 in TT2
  • Measurements can be performed without SPS
    injection
  • At least 3 OTRs required for a measurement

62
MEASURING BEAM PARAMETERS (4/12)
  • In the SPS (SPS Control / SPS beam measurement /
    SPS wire scanner)
  • Rotational Wire Scanner (6 m/s) 2 pairs in LSS4
    2 pairs in LSS5
  • Linear Wire Scanner (1 m/s) 2 pairs in LSS5
  • ? DO NOT USE the Linear Wire Scanners as these
    will burn with this high intensity beam (should
    be used for the LHC pilot bunch)

Should be preferred
Should be preferred
LINEAR
63
MEASURING BEAM PARAMETERS (5/12)
64
MEASURING BEAM PARAMETERS (6/12)
65
MEASURING BEAM PARAMETERS (7/12)
  • IPM H (BIPMH51634) and V (BIPMV51734)

MD CYCLE
Gaussian of constant normalized emittance in blue
?x 2.68 mm
? Fanny is currently writing a program to have
the IPM measurement operational in 2008
?x 1.51 mm
66
MEASURING BEAM PARAMETERS (8/12)
  • Longitudinal emittance
  • In the PS
  • Tomoscope (should be preferred) or BSM
  • In the SPS
  • By measuring the bunch length as a function of
    the RF voltage ? An application will be available
    to compute this (Fanny)
  • Intensity
  • In the PS
  • BCT gives the total intensity (of the 72 bunches)
  • BSM gives the relative bunch by bunch intensity
  • Transfer line ? (SPS Control / SPS beam
    measurement / SPS FBCT)
  • 1 FBCT at the beginning of TT2 1 FBCT at the
    end of TT10
  • Absolute intensity, bunch by bunch
  • Possibility to superimpose the measurements
    obtained with 2 different FBCTs

67
MEASURING BEAM PARAMETERS (9/12)
  • In the SPS
  • FBCT (Fast BCT) ? 1 (SPS Control ? SPS beam
    measurement ? SPS FBCT)
  • Absolute intensity, bunch by bunch
  • Possibility to superimpose the measurements
    obtained with two different FBCTs
  • Normal BCTs ? 3
  • 2 for high intensity (DBCTHIGH1 and DBCTHIGH3).
    From 1010 p up to a few 1013 p)
  • 1 for low intensity (DBCTLOW4). From 108 p up to
    a few 1011 p)
  • There is a difference of about 10 between the
    FBCT and the normal BCTs. The normal BCT is used
    for calibrating the FBCT
  • Use one of the 2 high intensity BCTs (DBCTHIGH1
    or DBCTHIGH3)

68
? EXAMPLE OF EVOLUTION OF THE BCT FAST BCT
(10/12)
NOMINAL 4 ? 72 bunches
ALTERNATIVE 5 ? 48 bunches
BCT 5?1010 p
V200MHz 104 V
V800MHz 103 V
Beam momentum GeV/c
69
MEASURING BEAM PARAMETERS (11/12)
  • Bunch length
  • In the PS
  • BSM
  • In the SPS
  • Application in BA3 Fanny
  • Momentum spread ? Deduced from measurements of
    bunch length and longitudinal emittance (deduced
    from bunch length and RF voltage)

70
MEASURING BEAM PARAMETERS (12/12)
  • Transverse tunes and chromaticties
  • In the PS
  • Qmeter Bernards application
  • In the SPS
  • Jorg released in 2007 a totally re-factored
    MultiQ application for the SPS based on the BBQ
    system (The old BOSC Qmeter system is no longer
    supported)
  • Jorg also implemented in 2007 an automatic
    measurement of the chromaticity (linear and/or
    nonlinear) in the AutoQ ? It is AutoQprime

71
EXTRACTION (1/2)
  • Once at 450 GeV/c the following actions take
    place during the flat-top, which is approximately
    1 second long
  • Ramping of the extraction elements (magnetic
    septa and closed orbit bumpers) ready for
    extraction
  • Fine re-phasing of the SPS with respect to the
    LHC in order to inject into the LHC at the
    required azimuthal position
  • Compression of the bunch length by an RF voltage
    increase
  • Cleaning of the tails of the beam distribution
    down to 3-3.5s by means of fast scrapers
  • The status and settings of various elements of
    the LHC, the transfer lines, the SPS and the
    extraction channel must be surveyed and checked
    before extraction is permitted

72
EXTRACTION (2/2)
  • MKE extraction kickers
  • LSS4
  • LSS6

73
CHANGES WHEN SWITCHING FROM FT TO
(High-intensity) LHC
  • During (the scrubbing run and) the LONG MDs with
    LHC beam the ZS are RETRACTED / HV to 0 kV / ION
    TRAPS ON (inform the ZS expert). The cooling
    circuit for the septa magnets (circuits 214, 414
    and 614) should be switched OFF (by TI). Block
    the fast vacuum valves OUT in the injection and
    extraction areas (LSS1,LSS2,LSS6)
  • Equipment modifications for the MD
  • Changed accelerator mode for FT no extraction
  • NORTH extraction off
  • MST/MSE girders retracted
  • Servo off
  • Switched off TT20 AUXPS

74
REMAINING ISSUES IN 2008
  • TIDVG outgassing
  • Problem (only) when the beam is repeatedly
    dumped at high energy (450 GeV/c) with the
    nominal LHC beam ? We then have after few minutes
    an interlock on the downstream MKP (to prevent it
    from sparking) ? It is a problem in fact of
    vacuum and not dump!
  • This is issue is currently under study
  • MKDV1 outgassing
  • The nominal LHC beam cannot be extracted to the
    LHC if we dont find a solution!
  • During the 2007 MD we removed the last voltage
    step (which reduces the bunch length at the very
    end before going to the LHC) to allow the beam to
    go to 450 GeV/c otherwise it would not have been
    possible
  • L. Ducimetiere informed us that nothing was done
    on this during the 2007-2008 shutdown

75
(LEAD) IONS (1/2)
76
(LEAD) IONS (2/2)
In the SPS in 2007
2007 MDs ? 90 of the design intensity (4?9E7?82)
with transverse emittances (rms, norm) 25
smaller than design (0.9 ?m instead of 1.2 ?m in
both planes)
? No ions in the SPS in 2008!
Write a Comment
User Comments (0)
About PowerShow.com