Sandia National Laboratories, California Interdisciplinary Team (IDT) Review Process of Proposed Site Projects and Activities - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Sandia National Laboratories, California Interdisciplinary Team (IDT) Review Process of Proposed Site Projects and Activities

Description:

Title: Main Title 32pt Last modified by: gwshamb Document presentation format: On-screen Show Other titles: Times Arial Times New Roman Wingdings Helvetica Monotype ... – PowerPoint PPT presentation

Number of Views:118
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Sandia National Laboratories, California Interdisciplinary Team (IDT) Review Process of Proposed Site Projects and Activities


1
Sandia National Laboratories, California
Interdisciplinary Team (IDT) Review Process of
Proposed Site Projects and Activities
  • Gary Shamber, Manager, Environmental Management
  • November, 2006

Sandia is a multi program laboratory operated by
Sandia Corporation, a Lockheed Martin
Company,for the United States Department of
Energy under contract DE-AC04-94AL85000.
2
Set The Stage the problem.
  • In 1992 a new Facilities manager was frustrated
    with the ESH review of facilities projects.
    ESH review was considered somewhat of a
    check-the-box exercise after design was
    essentially complete.
  • Review was conducted in series by routing the
    design package.
  • 3 to 6 week review time was not uncommon.
  • Sat in queue to be reviewed by those who
    ultimately had no interest or input.
  • Not uncommon to get conflicting
    requirements/input.
  • For important projects or those on a tight
    schedule we would walk them through.
  • If a significant ESH issue was identified that
    had not been considered, it sometimes
  • required the engineer to redesign
  • negated purchased material
  • affected an established project schedule

3
(No Transcript)
4
The proposal
  • Lets get all the ESH SMEs together in one place
    at the same time each week.
  • Lets get the facilities project managers to come
    to this group and discuss their projects during
    the planning stage.
  • Lets make the reviews short by not attempting to
    solve issues. Instead.
  • Lets identify the issues that will need to be
    resolved and those individuals who will need to
    be involved to resolve them.

5
IDT Was Born
1992
6
Immediate Results
  • Time dedicated to project reviews reduced by
    gt50.
  • Eliminated conflicts of ESH feedback.
  • Quality of facilities project planning improved.
  • Improved partnership between ESH and Facilities.

7
There were growing pains
  • What needs to be reviewed by IDT?
  • Should IDT be voluntary or mandatory?
  • Whens the right time to present a project /
    activity to IDT?
  • What about project issues other than those
    related to ESH?

8
What needs IDT review?
  • Any new project or activity of significance.
  • Generally anything non-routine.
  • Changes to a routine process.
  • Examples facilities projects, maintenance
    procedures, new lab experiments, new programs,
    site activities (celebrations, open house, Earth
    day, etc.)

9
Voluntary or mandatory?
  • Initially IDT was voluntary. We wanted to offer
    an alternative review process and through time
    demonstrate that it was in the customers best
    interest to use it.
  • Later, IDT was made mandatory for all facilities
    projects.
  • Eventually, IDT review was made a mandatory site
    practice for all projects.

10
Whens the right time to come to IDT?
  • Good time is.Once you thoroughly understand what
    needs to be done and how you would like to do it.
  • Before you complete a design.
  • Before you commit to a schedule.
  • Before you issue a contract.
  • Before you purchase material.
  • Large or long duration projects should perform
    multiple IDTs at key stages.

11
Project issues other than ESH
  • Many projects have issues that bridge between
    ESH, facilities and security (adjacencies,
    safety v security design, changes in space
    allocation and ownership, scheduling).
  • Facilities and security were added as permanent
    members of IDT about 3 years ago.

12
IDT Today
  • The IDT provides a one-stop shop to obtain
    preliminary and interim ESH, Facilities and
    Security review of projects and activities.
  • IDT is also offered as a forum to review proposed
    ESH-related corrective actions or discuss
    organizational ESH compliance, issues or
    difficulties.
  • The IDT consists of subject matter expert
    representatives from all Environmental, Safety
    and Health (ESH) subject areas, Facilities and
    Security.
  • IDT serves as a NEPA trigger.

13
IDT - Desired Outcome
  • Surface and clarify the significant ESH,
    physical security and facility issues (safety
    design, adjacencies, construction safety,
    traffic, capabilities) associated with a proposed
    project.
  • Provide guidance to the customer for further
    project / action development.
  • Identify the SMEs who will need to work with the
    customer in follow-up meetings or interactions to
    resolve the issues, get approvals, completing
    permits, etc.

14
IDT Process
  • Requests are made to the IDT Point-of-Contact any
    time.
  • IDTs are scheduled for Thursday mornings.
    Special or urgent requests are accommodated.
  • Primary IDT SMEs or the designated backups
    attend.
  • 10-30 minute presentation is conducted by
    requester. Covers what/where/whens of the
    project/action, how they are planning to execute
    it, what they perceive as the ESH issues.
  • Presentations are recorded in case any SME needs
    to later review a particular comment or
    discussion detail.
  • At the end of each presentation each SME in turn
    surfaces any issue and indicates whether they
    will need to be further involved.
  • Presenters receive a report by COB Monday
    identifying the issues and who will need to be
    involved to help the customer resolve the issues.

15
IDT process continues to grow.
16
Challenges
  • Some customers come to IDT looking for blanket
    approval.
  • Expensive for simple or benign projects/actions.
  • Thresholds when to engage IDT are subjective.
  • Customers coming to IDT late in project
    development.

17
IDT Residual Benefits
  • Keeps ESH, Security, and Facilities SMEs
    knowledgeable of upcoming site projects/activities
    .
  • Creates a cross functional learning environment
    and teamwork among IDT members.
  • Improves ESH, Security, Facilities visibility
    and customer relations.

18
IDT Customer Feedback(FY2005)
19
Sample Feedback Comments FY06
  • Not sure if I have approval to continue.
  • Great process value.
  • Painless great.
  • Quick, and not over-burdensome.
  • Unclear when to involve IDT.
  • Great system, works well.
  • Meeting discussions were great.
  • Professional straight forward.

20
Case Study 1
  • A facilities project was presented to IDT to
    modify a high pressure test building that had
    been on the site demo list for some time. The
    discussion exposed a much larger program.
  • The line customer was requested to present to
    IDT. Several line customers participated.
  • It was discovered that the proposed test facility
    project was but the initial step of a much larger
    site program to do large quantity hydrogen work
    in not only the test facility but other buildings
    as well.
  • There was also evidence of a space conflict
    between several organizations due to the project.

21
Case Study 1
  • IDT worked with the line customer(s) to
    coordinate many of the program issues
  • The safety design basis of the test facility was
    reviewed to assure it could handle the expected
    explosive potentials.
  • Safety analysis performed on the work to be
    performed in the other facilities.
  • Adjacencies were considered.
  • Building safety systems were coordinated.
  • Investment monies were found to make the longer
    range facility modifications.
  • The space issues were resolved in a systemic and
    satisfactory manner.

22
Case Study 2
  • SNL/CA was planning its 50th Year Anniversary
    celebration.
  • An IDT was performed that resulted in
  • Modification of several demonstration projects
    because of safety concerns to the public.
  • Underground electrical scans/surveys in areas
    where tents were to be installed.
  • Coordinated contingency and emergency response
    planning.
  • Health stations for visitors (expected hot
    weather).
  • Coordination of temporary utilities (water, gas
    powered electric/generators, etc.)

23
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com