Performance Contracting for Construction: Framework for Implementation - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Performance Contracting for Construction: Framework for Implementation

Description:

previous file name: trb2007MarkRobinson-P07-0210.ppt ... Title: VSL Author: Robinson and Zineddin Last modified by: Sid Scott Description – PowerPoint PPT presentation

Number of Views:555
Avg rating:3.0/5.0
Slides: 15
Provided by: Robinsona
Learn more at: https://www.fhwa.dot.gov
Category:

less

Transcript and Presenter's Notes

Title: Performance Contracting for Construction: Framework for Implementation


1
Performance Contracting for Construction
Framework for Implementation
  • Mark Robinson, Ph.D., P.Eng., PMP
  • SAIC
  • 1/22/07

2
Overview
  • Why Performance Contracting for Construction?
  • Framework Purpose
  • Stakeholder Involvement
  • Framework Contents
  • Relation to the Highways for LIFE Program
  • Lessons Learned
  • Pilot Program
  • Next Steps

3
Why Performance Contracting for Construction?
  • Much of Americas transportation infrastructure
    is reaching the end of its design life and needs
    to be re-constructed
  • Traffic levels and the resulting congestion
    levels continue to increase
  • FHWA is developing, identifying, and promoting
    new methods to reconstruct highways and bridges
    safer, faster, and better
  • Using performance contracting will allow State
    and local agencies to define and communicate to
    contractors specifically what they want to
    achieve
  • Contractors will have the flexibility to
    determine how they do the work

4
Some Pros and Cons
  • Pros
  • Introduction of Innovation
  • Defined Outcomes
  • Contractor Flexibility
  • Share of risk and rewards
  • Cons
  • New approach that requires a culture shift
  • May not be applicable to all projects

5
Framework Purpose
  • To provide State and local agencies with
    processes and materials that they can use to
    accelerate the development of a performance
    contract solicitation package for construction
    contracts
  • Meant to be used as a reference guide
  • Should help agencies to avoid common obstacles
    and pitfalls

6
Stakeholder Involvement
  • The project team developed the materials working
    with
  • A select group of stakeholders from State DOTs
    and Industry
  • Provided guidance and review at the 30, 60, and
    90 stages
  • Subject matter experts from FHWA

7
State DOT and Industry Stakeholder Group
  • Scott Jarvis - Caltrans
  • Chuck Suszko - Caltrans
  • Gene Mallette - Caltrans
  • Peggy Chandler - Texas DOT
  • Steve DeWitt - North Carolina DOT
  • Kevin Dayton - Washington State DOT
  • Dexter Newman - the Kentucky Cabinet
  • Sid Scott - Trauner Consulting
  • Brian Deery - AGC
  • Bob Lanham - Williams Brothers Construction-
  • Brian Burgett - Kokosing Construction
  • Rich Juliano - ARTBA

Note Participation did not involve formal
endorsement of the final product
8
FHWA Subject Matter Experts
  • Jim Sorenson
  • Mary Huie
  • Byron Lord
  • Ken Jacoby
  • King Gee
  • Jerry Yakowenko
  • Tracy Scriba
  • Chung Eng
  • Rudy Umbs
  • John Baxter
  • Mark Swanlund
  • Peter Kopac
  • Christopher Schneider
  • David Geiger
  • Tom Deddens
  • Gus Shanine
  • Rob Elliott
  • Evan Wisniewski
  • Jim Hatter
  • John Bukowski
  • Fred Skaer
  • Shari Schaftlein
  • Myint Lwin
  • And others

9
Framework Contents
  • Overall process for performance contract
    development
  • Guidance on selecting appropriate projects
  • Processes, lessons learned, and sample
    solicitation package materials for
  • Performance Goals
  • Measurement Methodology
  • Enhanced Low Bid Award Process
  • Best Value Award Process
  • SEP-14 Process

10
Relation to the Highways for LIFE (HfL) Program
  • HfLs mission is to improve the driving
    experience of the American public
  • HfL is looking for new ways to build highways and
    bridges safer, faster, better, and less costly
  • Performance contracting will be a tool in the HfL
    toolbox
  • HfL projects are not required to use performance
    contracting
  • Additional consideration will be given to
    projects that propose to use performance
    contracting

11
Lessons Learned
  • Each project will be different Processes,
    goals, and materials will need to be tailored to
    the individual application
  • Performance goals should be SMART Specific,
    Measurable, Achievable, Results-Oriented, and
    Timely
  • Performance goals MUST be under the influence of
    the contractor
  • The contractor must have flexibility in how they
    perform the work
  • Ideally, the performance-based environment will
    start at the concept or design stage

12
Pilot Program
  • FHWA is currently seeking 4 to 8 agencies that
    are interested in piloting the Performance
    Contracting Framework.
  • Pilot states will receive tailored technical
    assistance to help them implement this approach
  • Pilot states can propose the use of the framework
    as an innovative approach when applying for
    funding under the Highways for LIFE Program
  • For more information on becoming a pilot agency,
    contact Mary Huie at mary.huie_at_dot.gov or
    202-366-3039

13
Next Steps
  • Perform outreach to recruit agencies to pilot the
    framework
  • Provide technical assistance to 4 to 8 pilot
    projects
  • Capture information on successes and lessons
    learned
  • Prepare case study documents on each pilot
    application
  • Revise and update the Framework for broader
    release

14
For More Information
  • Jim Sorenson, FHWA
  • james.sorenson_at_dot.gov, 202-366-1333
  • Mary Huie, FHWA
  • mary.huie_at_dot.gov, 202-366-3039
  • Mark Robinson, SAIC
  • mark.d.robinson_at_saic.com, 703-676-2384
Write a Comment
User Comments (0)
About PowerShow.com