Proposal for Renovation Project b. 151 - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Proposal for Renovation Project b. 151

Description:

EL-TC 27.4.2005 Proposal for Renovation Project b. 151 1. Overview 2. Photos of old installation 3. Outline of new project 4. Budget 5. Conclusions – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 16
Provided by: Karste46
Category:

less

Transcript and Presenter's Notes

Title: Proposal for Renovation Project b. 151


1
EL-TC 27.4.2005
  • Proposal for Renovation Project b. 151

1. Overview 2. Photos of old installation 3.
Outline of new project 4. Budget 5. Conclusions
K. KAHLE, TS-EL
2
1. Project Overview
b. 151
PS Test (2006)
ME6
3 MeV (2006)
LEIR (2005)
LINAC 4 (2008)
b. 152
b. 150
3
1. Overview
  • Hall 151
  • Test of PS magnets
  • Test of RF equipment

4
2. Old installation
EBD13SHC - obsolete
5
2. Old installation
EBD11SHC - obsolete
6
2. Old installation
EBD30 and EBD31SHC - obsolete
7
2. Old installation
Disconnected OIL CABLE in the cable duct
8
2. Old installation
Old switchboard, disconnected
9
2. Old installation
Spaghetti Bolognese
10
2. Old installation
The purple snake
11
2. Old installation
Socket box - obsolete
12
3. Outline of new project
  • dismantle obsolete switchboards
  • (ERD30SHC, ERD31SHC, EBD11SHC, EBD13SHC,
    EBD14SHC)
  • NEW one single switchboard 1000A (type EBD)
  • existing incoming cables remain (200m x 11 PVC
    240 Cu from b.264)
  • this would free feeders from s/st ME6
  • OPTION
  • one large switchboard ERD one switchboard EBD
    for Gen. Serv.
  • clean all cable ducts, dismantle unused cables
  • replace all outgoing cables from the new
    switchboard
  • remove all oil cables in the zone

13
4. Budget
Work kCHF
Dismantling of old switchboards 10
New single switchboard EBD, incl. installation 30
Support structure for new switchboard or false floor 7
Dismantling of oil cables 20
Dismantling of old and unused cables in the cable ducts 10
Adaptation of 11 incoming feeder cables (extensions, joints, terminations) 5
New cabling (outgoing feeders) 18
New cable ladders, where necessary 3
Documentation 5
Contingency for bad surprises (will certainly be needed!) 10
Total 118
14
5. Conclusion
  • Project is necessary Safety Reasons
  • Project Duration 6 months
  • no manpower available
  • Project is defined now
  • START depending on available manpower budget

15
Questions ?
Thank you.
Write a Comment
User Comments (0)
About PowerShow.com