Status of the MuCool Cavity Prototype - PowerPoint PPT Presentation

About This Presentation
Title:

Status of the MuCool Cavity Prototype

Description:

Status of the MuCool Cavity Prototype MICE Collaboration Meeting October 21, 2005 Steve Virostek Lawrence Berkeley National Laboratory Progress Since Last Year RF ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 19
Provided by: Deru8
Learn more at: http://mice.iit.edu
Category:

less

Transcript and Presenter's Notes

Title: Status of the MuCool Cavity Prototype


1
Status of the MuCoolCavity Prototype
MICE Collaboration Meeting October 21, 2005
  • Steve Virostek
  • Lawrence Berkeley National Laboratory

2
Progress Since Last Year
  • Leak check of all e-beam welds was performed
  • Cooling tubes were TIG brazed to cavity exterior
  • A final mechanical buff of the interior was
    completed
  • Cavity interior surfaces were electropolished
  • RF couplers were fabricated and conditioned
  • First 201 MHz beryllium window delivered to LBNL
  • Cavity manual tuner and support stand were
    fabricated
  • Final assembly and leak check performed at J-Lab
  • Cavity was shipped to the MTA, assembled and leak
    checked

3
RF Cavity Overview
  • Two 6 mm thick copper shells are e-beam welded
    together at equator to form cavity
  • Cavity half-shells are formed from annealed, flat
    plate using a spinning technique
  • Separate copper nose piece rings are e-beam
    welded to cavity aperture
  • RF and vacuum ports are formed by pulling a die
    through a hole cut across the equator weld
  • Externally brazed tubes provide cooling
  • Two thin, pre-curved beryllium windows are to be
    mounted on cavity aperature
  • Cavity inside surfaces are finished by
    mechanically buffing and electropolishing

4
Shell Spinning Measurement
  • A 6.35 mm OFHC copper sheet is spun against a
    pre-machined form to generate half-shells
  • Shell outer edges are trimmed as specified after
    spinning
  • Half-shell profiles at various cross-sections are
    measured using a portable CMM
  • Half-shell is placed on a copper sheet and
    frequency is determined using low level RF
  • Comparisons are made between RF analysis of
    measured shape and frequency check

5
Cavity Stiffener Ring
  • Hard copper stiffener ring is e-beam welded on
    inside and outside edges to the outside of the
    cavity shell
  • Rings initially provide for safe handling the
    half-shells
  • Rings are turned on a lathe after being welded on
    to provide an accurate reference for subsequent
    operations
  • Rings provide an interface for tuner mechanisms
    and for mounting the finished cavity to the
    support structure
  • Load tests on sample welds indicate the e-beam
    weld strength is much higher than required for
    tuning

6
Nose Hole Equator Joint Machining
  • Nose hole is cut with a numerically controlled
    horizontal mill using the stiffener ring for
    reference
  • Special aluminum fixturing was designed to hold
    the half shells
  • Hole detail includes a 1 mm lip to register the
    nose piece ring
  • Shell lip is cut using a numerically controlled
    horizontal mill with a right angle head adaptor
  • A close fitting aluminum disc supported the lip
    during machining
  • Lip includes a chamfered step that mates with the
    opposing shell to prevent slipping prior to and
    during e-beam welding

7
Shell Cleaning and Buffing
  • Shells are cleaned prior to welding operations by
    rotating them through a chemical bath
  • Some scratches and dents created on the inside
    surfaces of the shells during spinning
  • Cavity surfaces smoothed out mechanically with an
    abrasive buffing wheel

8
Cavity Equator Weld
  • Cavity and fixture system is mounted and
    assembled on a plate and placed on the welder
    sliding table
  • External structural weld is near full penetration
    and is achieved in three offset passes
  • A final cosmetic/vacuum weld is performed on the
    inside of the joint with the cavity mounted on a
    horizontal rotary table
  • Inside equator weld is smoothed using an abrasive
    wheel

9
Nose Fabrication Welding
  • Nose piece ring is OFHC copper with a stainless
    steel support ring brazed to the roughed out
    copper ring
  • SS ring bolt circles allow attaching Be window
    and cover plate
  • After brazing, copper is machined to final shape
  • Cavity is placed in welder chamber horizontally
    on a rotary table with fixturing holding nose
    piece ring
  • Similar to the equator weld, nose piece weld
    consists of 3 offset external welds and an inside
    cosmetic/vacuum pass
  • Inside nose weld are smoothed and weld blow
    through is removed using an abrasive wheel

10
Cavity Port Forming Welding
  • Local annealing only (to preserve cavity overall
    strength is) achieved by repeatedly passing a
    diffuse e-beam around port
  • Port pulling tool is used in a horizontal
    orientation, and a weld prep is machined into the
    port lip using an NC mill
  • Cavity is held vertically in welder chamber on a
    fixture that facilitates 90 degree rotations
  • Structural and vacuum weld is made with a single
    inside pass
  • Prototype cavity uses a stainless flange with a
    TIG welded copper insert (flange must hold
    vacuum)
  • MICE cavity will use an all copper flange for RF
    sealing only

11
Vacuum Leak Check
  • After ports are attached, a vacuum leak check of
    all welds (equator, nose pieces 2, stiffener
    rings 2, ports 4, port flange inserts 4) is
    performed
  • Conflat flanges on ports allow easy blank-off and
    leak detector attachment
  • Nose openings are covered by a plate with an
    O-ring
  • An internal support is required to prevent the
    external atmospheric pressure from collapsing
    cavity

12
Cooling Tube Weld
  • Cavity cooling is achieved by TIG brazing a 9.5
    mm diameter copper tube to the exterior in an
    alternating skip pattern
  • Four turns (1 circuit) per cavity side step
    inward near to the stiffener ring OD and then
    step back out to the equator
  • Cooling tube spacing is approximately 10 cm
  • Fittings are brazed to the tube ends and tacked
    to the cavity
  • Nominal flow rate is expected to be 3 gpm per
    circuit

13
Final Interior Buffing
  • Final interior buffing of cavity is performed to
    ensure the surfaces are ready for
    electropolishing
  • Less buffing needed near equator where fields are
    lower
  • An automated process of buffing was developed
    using a rotary buffing wheel and a cavity
    rotation fixture
  • Some local hand work required to clean up some
    areas
  • A series of pads with graduated coarseness was
    used
  • Goal was scratch depth shallow enough for EP
    removal

14
Interior Surface Electropolish
  • After buffing, cavity underwent a chemical
    cleaning process
  • Test bars with various degrees of buffing were
    run through an electropolish process
  • Cavity was rotated with a U-shaped electrode
    fixed in place
  • Initial polish failed due to depletion of the
    solution, and rebuffing was required
  • 2nd EP successfully removed scratches in high
    field regions
  • Final process is a high pressure water rinse of
    cavity surface

15
Cavity RF Couplers
  • Coupling loops were fabricated using standard
    copper co-ax
  • Most coupler parts were joined by torch brazing
    vacuum leaks were found in two of the outer
    conductor joints
  • Coupling loop contains an integrated cooling tube
  • The coupler was designed to mate with an SNS
    style RF window manufactured by Toshiba
  • High power conditioning performed at SNS (ORNL)
  • The MICE coupler will require a bellows
    connection interface with the outer vacuum vessel
    ports

16
201 MHz Beryllium Windows
  • Each cavity will require a pair of 0.38 mm thick
    pre-curved beryllium windows with TiN coating
  • Double-curved shape prevents buckling caused by
    thermal expansion due to RF heating
  • Thermally induced deflections are predictable
  • A die is applied at high temperature to form
    window
  • Copper frames are brazed to beryllium windows in
    a subsequent process

17
Shipment to the MTA at FNAL
  • System assembly included tuner plates, port
    blank-offs, diagnostic spool, window cover
    plates, gate valve and window pumpout tubes
  • Final leak check conducted prior to shipping
  • Cavity was back-filled with nitrogen in its
    assembled state and packaged in a custom made
    crate for shipping to the MTA

18
Final Assembly at the MTA
  • Cavity assembly was mounted on the support and
    couplers were installed in a portable clean room
  • Dummy copper windows (flat) are used initially
  • Couplers were set and frequency was measured
  • Bakeout system hardware was installed
  • System is now leak tight and ready for bake
Write a Comment
User Comments (0)
About PowerShow.com