Title: Planning the project
1Planning the project
- Project Management
- (lecture)
2Strategic and tactical levels of planning
Hierarchy of plans
- Strategic plans
- Focus on the big picture
- Long term goals (2-5 years)
- What? Why?
- Tactical plans
- Focus on the operations
- Short term goals (1-18 months)
- How?
3Strategic and tactical levels of planning
- Strategy provides a framework for the tactics.
Tactical plans should fit the needs of the
strategy. - To permit effective tactical decision making
strategy should be - Explicit
- Intelligible (easy to understand)
- Capable of accepting change
- Capable of being monitored
- Tactical plans on higher levels act as
strategies for lower levels in the organisation.
4Opportunity cost
- That which is sacrificed by choosing or failing
to adopt a different course of action to that
which is currently planned to be taken -
- the value of the next best alternative foregone
(that is not chosen).
5The project plan
- In its simplest form it is an attempt at the
timetable for ALL the activities which make up
the project. - As a minimum, it sets out
- how
- who does what
- when
- A more sophisticated plan also states
- what quality
- what cost and resources
- Its preparation is an iterative process with
continuous reviewing and updating throughout the
life of the project (it is never static document
but a working tool).
6Detailing the plan
- Amount of details included should vary in time.
- Short term fully detailed
- The short-term horizon is moving forward(the
plan become more-and-more detailed).
7Who is responsible for the project plan?
- The project manager and the project management
team - With the advice and assistance of
- the project sponsor
- the customer
- and other stakeholders
8Elements of project planning
- Project goals (Project SOW)
- Project product specifications, costs, quality,
deadlines, project deliverables etc. - Project management plan
- Work breakdown structure (WBS)
- Project network (connections of tasks)
- Responsibility assignment
- Project schedule (timetable)
- Budget (resources costs)
- Risk assessment and risk management
Iterative process
9Statement of Work (SOW)
- SOW for the whole project a detailed narrative
description of the work required for a project.
Can be written in the form of a legal contract,
if we do the project for an other organisation. - The effective SOW contains
- Introduction and background
- Technical description
- Timeline and milestones
- Client expectations
- There are SOWs for subprojects and even tasks,
too.
10Statement of Work for the tasks within the project
- Describes the activities in the tasks in
sufficient detail. - Content
- estimated durations
- resources required
- costs
- measures of perfomance (performance indicators)
- risks and uncertainties
- reporting procedures
11Project deliverables (milestones)
- a list of things or activities that need to be
delivered to meet the defined goals - when and how each item or activity must be
delivered - an estimated delivery date for each item or
activity
12Work Breakdown Structure
- Similar to the assembly (Gozinto) charts.
- A tool used to define and group a project's
discrete work elements (tasks) in a way that
helps organize and define the total work scope of
the project. - The project is divided into hierarchical groups
of tasks (work packages, and work units). - Tasks, work packages and work units should be
budgetable (money, labor hours, and other
resources). - The technique of creating a WBS is non-uniform.
13Assembly chart (Gozinto chart) example
14Example of a WBS
15Possible levels in a WBS
- Project
- Sub-projects
- Deliverables
- Sub-deliverables
- Work packages
- Work units
16Another WBS example
17Another example of WBS Holiday
holiday
travel documents
booking
household
passport
tickets
choose resort
confirm
cat!
brochures
insurance
18Discussion question
- What is the greatest difference between a Gozinto
and a WBS chart?
19GANTT charts
- Named after Henry Gantt (1861 - 1919) an American
mathematical engineer. - A Gantt chart is a type of bar chart that
illustrates a project schedule. - Gantt charts illustrate the start and finish
dates of the work elements (tasks) of a project. - Elements of a GANTT chart
- Task names
- Start and finish dates of each tasks
(graphically) - Dependency relationships
- Task duration in an additional column
- Lag relationships (start-to-start,
finish-to-start etc.) - Name of the project worker responsible for the
task or - Resource specifications
- other
20GANTT chart example
ID Activities Who is responsible? Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8.
1.
2.
3.
4.
5.
6.
7.
8
9
10.
11.
21Benefits of the GANTT chart
- Easy to read and comprehend
- Easy to create
- Identify the project network coupled with its
schedule baseline - Allow for updating and project control
- Useful for resource planning
22Limitations
- Can become quite unwieldy for projects with too
many activities. - Projects are often too complex for a Gantt chart.
- Gantt charts represent only a part of the project
constraints. - The technique of creating a GANTT depends on the
features of the project.
23GANTT chart example
Some Gantt charts also show the dependency
relationships between activities.
24GANTT chart example
25GANTT chart example
Gantt charts can be used to show current schedule
status using percent-complete shadings, or colour
lines and a vertical "TODAY" line.
26Readings
- Lockyer Gordon (2005) Chapter 4
27Seminar exercises
28Opportunity cost
- There are two alternative project. Only one of
them can be selected. - Project A has an expected net cash flow of 100.
- Project B has an expected net cash flow of 80.
- What is the opportunity cost of choosing project
A? - What is the opportunity cost of choosing project
B? -
- There are 3 investment opportunities with given
expected net cash flow - A 300 B 250 C 150.
- Only one investment can be made. Which one
should be selected, and what is its opportunity
cost? - Someone has 1000 HUF. It can be deposited at a
bank (interest is 15). What is the opportunity
cost of not investing?
29WBS problem solving 1
- There is a marketing-research project containing
a focus group interview and a questionnaire
survey with 200 responders. The survey is based
on the analysis of the focus group results. - For the focus we have to gather the participants
(7 days), organize the event (place, time,
equipment etc. 2 days), implement the interview
(1 day), record the interview (2 days), analyse
it (3 days) and write a brief research report for
the client/sponsor (1 day). - For the survey we have to construct the
questionnaire (2 days),test and modify it (1
day), do the sampling (2 day), train the
interviewers (1 day), fieldwork (2 days), record
the data (1 day), analyse the data (2 days) and
write the final study (3 days). - The project manager want to keep a 5 days buffer
time for safety at the end of the project.
30WBS problem solving 2
- Plot a Gozinto and a WBS chart for the next
project - Main task prepare lunch with 2 dishes.
- The 1st course requires 2 main groups of
ingredients (A B) that should be bought
separately (time to buy is 30 mins per
ingredient-group). Cooking is 1 hr. - The 2nd dish requires 3 group of ingredient (A, C
D), procurement time is the same). Cooking
needs 1.5 hrs. - Cleaning after cooking needs 20 mins for 1
person, 10 mins for 2 people.
31Gantt exercise
- Given the marketing research project plot a Gantt
chart with the following information - Task names
- Task durations
- Time schedule
- Use a backward planning (deadline is the 30th
day) and try to reach the shortest total project
time (TPT).
32GANTT exercise 2
- Given the WBS from the lunch-making-project and
the additional information that there are two
identical project workers (X and Z) who can work
simultaneously, plot a simple GANTT chart with
the following content - Task names
- Time schedule (time units are 10 minutes long)
- Task durations
- Denominate the person in charge for every task
- Simultaneous work is possible.
33GANTT exercise 2
- How long is the full project?
- Denote the precedence relationships in the chart!
34GANTT exercise 3
- Show the schedule status on the GANTT chart for
the same project after 80 minutes if - All the A, B and C ingredients are bought, but
the purchase of ingredient D is only 67
complete. - The 1st course is already half-cooked, but the
operations on the 2nd dish could not started
yet.
35GANTT exercise 4
- Plot a new chart with the same data but with real
times within a day. The following information are
added - The market, where the ingredients should be
bought is open only from 8 a.m. to 10 a.m. and
the earliest is the better. - The lunch preparations (including the cleaning)
should be ready exactly at noun (12 a.m.).
36Thanks for the attention!