Planning the project - PowerPoint PPT Presentation

About This Presentation
Title:

Planning the project

Description:

Planning the project Project Management (lecture) GANTT exercise 3 Show the schedule status on the GANTT chart for the same project after 80 minutes if: All the A, B ... – PowerPoint PPT presentation

Number of Views:182
Avg rating:3.0/5.0
Slides: 37
Provided by: ktk6
Category:

less

Transcript and Presenter's Notes

Title: Planning the project


1
Planning the project
  • Project Management
  • (lecture)

2
Strategic and tactical levels of planning
Hierarchy of plans
  • Strategic plans
  • Focus on the big picture
  • Long term goals (2-5 years)
  • What? Why?
  • Tactical plans
  • Focus on the operations
  • Short term goals (1-18 months)
  • How?

3
Strategic and tactical levels of planning
  • Strategy provides a framework for the tactics.
    Tactical plans should fit the needs of the
    strategy.
  • To permit effective tactical decision making
    strategy should be
  • Explicit
  • Intelligible (easy to understand)
  • Capable of accepting change
  • Capable of being monitored
  • Tactical plans on higher levels act as
    strategies for lower levels in the organisation.

4
Opportunity cost
  • That which is sacrificed by choosing or failing
    to adopt a different course of action to that
    which is currently planned to be taken
  • the value of the next best alternative foregone
    (that is not chosen).

5
The project plan
  • In its simplest form it is an attempt at the
    timetable for ALL the activities which make up
    the project.
  • As a minimum, it sets out
  • how
  • who does what
  • when
  • A more sophisticated plan also states
  • what quality
  • what cost and resources
  • Its preparation is an iterative process with
    continuous reviewing and updating throughout the
    life of the project (it is never static document
    but a working tool).

6
Detailing the plan
  • Amount of details included should vary in time.
  • Short term fully detailed
  • The short-term horizon is moving forward(the
    plan become more-and-more detailed).

7
Who is responsible for the project plan?
  • The project manager and the project management
    team
  • With the advice and assistance of
  • the project sponsor
  • the customer
  • and other stakeholders

8
Elements of project planning
  • Project goals (Project SOW)
  • Project product specifications, costs, quality,
    deadlines, project deliverables etc.
  • Project management plan
  • Work breakdown structure (WBS)
  • Project network (connections of tasks)
  • Responsibility assignment
  • Project schedule (timetable)
  • Budget (resources costs)
  • Risk assessment and risk management

Iterative process
9
Statement of Work (SOW)
  • SOW for the whole project a detailed narrative
    description of the work required for a project.
    Can be written in the form of a legal contract,
    if we do the project for an other organisation.
  • The effective SOW contains
  • Introduction and background
  • Technical description
  • Timeline and milestones
  • Client expectations
  • There are SOWs for subprojects and even tasks,
    too.

10
Statement of Work for the tasks within the project
  • Describes the activities in the tasks in
    sufficient detail.
  • Content
  • estimated durations
  • resources required
  • costs
  • measures of perfomance (performance indicators)
  • risks and uncertainties
  • reporting procedures

11
Project deliverables (milestones)
  • a list of things or activities that need to be
    delivered to meet the defined goals
  • when and how each item or activity must be
    delivered
  • an estimated delivery date for each item or
    activity

12
Work Breakdown Structure
  • Similar to the assembly (Gozinto) charts.
  • A tool used to define and group a project's
    discrete work elements (tasks) in a way that
    helps organize and define the total work scope of
    the project.
  • The project is divided into hierarchical groups
    of tasks (work packages, and work units).
  • Tasks, work packages and work units should be
    budgetable (money, labor hours, and other
    resources).
  • The technique of creating a WBS is non-uniform.

13
Assembly chart (Gozinto chart) example
14
Example of a WBS
15
Possible levels in a WBS
  • Project
  • Sub-projects
  • Deliverables
  • Sub-deliverables
  • Work packages
  • Work units

16
Another WBS example
17
Another example of WBS Holiday
holiday
travel documents
booking
household
passport
tickets
choose resort
confirm
cat!
brochures
insurance
18
Discussion question
  • What is the greatest difference between a Gozinto
    and a WBS chart?

19
GANTT charts
  • Named after Henry Gantt (1861 - 1919) an American
    mathematical engineer.
  • A Gantt chart is a type of bar chart that
    illustrates a project schedule.
  • Gantt charts illustrate the start and finish
    dates of the work elements (tasks) of a project.
  • Elements of a GANTT chart
  • Task names
  • Start and finish dates of each tasks
    (graphically)
  • Dependency relationships
  • Task duration in an additional column
  • Lag relationships (start-to-start,
    finish-to-start etc.)
  • Name of the project worker responsible for the
    task or
  • Resource specifications
  • other

20
GANTT chart example
ID Activities Who is responsible? Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8. Time intervals 1. 2. 3. 4. 5. 6. 7. 8.
1.
2.
3.
4.
5.
6.
7.
8
9
10.
11.
21
Benefits of the GANTT chart
  • Easy to read and comprehend
  • Easy to create
  • Identify the project network coupled with its
    schedule baseline
  • Allow for updating and project control
  • Useful for resource planning

22
Limitations
  • Can become quite unwieldy for projects with too
    many activities.
  • Projects are often too complex for a Gantt chart.
  • Gantt charts represent only a part of the project
    constraints.
  • The technique of creating a GANTT depends on the
    features of the project.

23
GANTT chart example
Some Gantt charts also show the dependency
relationships between activities.
24
GANTT chart example
25
GANTT chart example
Gantt charts can be used to show current schedule
status using percent-complete shadings, or colour
lines and a vertical "TODAY" line.
26
Readings
  • Lockyer Gordon (2005) Chapter 4

27
Seminar exercises
28
Opportunity cost
  • There are two alternative project. Only one of
    them can be selected.
  • Project A has an expected net cash flow of 100.
  • Project B has an expected net cash flow of 80.
  • What is the opportunity cost of choosing project
    A?
  • What is the opportunity cost of choosing project
    B?
  • There are 3 investment opportunities with given
    expected net cash flow
  • A 300 B 250 C 150.
  • Only one investment can be made. Which one
    should be selected, and what is its opportunity
    cost?
  • Someone has 1000 HUF. It can be deposited at a
    bank (interest is 15). What is the opportunity
    cost of not investing?

29
WBS problem solving 1
  • There is a marketing-research project containing
    a focus group interview and a questionnaire
    survey with 200 responders. The survey is based
    on the analysis of the focus group results.
  • For the focus we have to gather the participants
    (7 days), organize the event (place, time,
    equipment etc. 2 days), implement the interview
    (1 day), record the interview (2 days), analyse
    it (3 days) and write a brief research report for
    the client/sponsor (1 day).
  • For the survey we have to construct the
    questionnaire (2 days),test and modify it (1
    day), do the sampling (2 day), train the
    interviewers (1 day), fieldwork (2 days), record
    the data (1 day), analyse the data (2 days) and
    write the final study (3 days).
  • The project manager want to keep a 5 days buffer
    time for safety at the end of the project.

30
WBS problem solving 2
  • Plot a Gozinto and a WBS chart for the next
    project
  • Main task prepare lunch with 2 dishes.
  • The 1st course requires 2 main groups of
    ingredients (A B) that should be bought
    separately (time to buy is 30 mins per
    ingredient-group). Cooking is 1 hr.
  • The 2nd dish requires 3 group of ingredient (A, C
    D), procurement time is the same). Cooking
    needs 1.5 hrs.
  • Cleaning after cooking needs 20 mins for 1
    person, 10 mins for 2 people.

31
Gantt exercise
  • Given the marketing research project plot a Gantt
    chart with the following information
  • Task names
  • Task durations
  • Time schedule
  • Use a backward planning (deadline is the 30th
    day) and try to reach the shortest total project
    time (TPT).

32
GANTT exercise 2
  • Given the WBS from the lunch-making-project and
    the additional information that there are two
    identical project workers (X and Z) who can work
    simultaneously, plot a simple GANTT chart with
    the following content
  • Task names
  • Time schedule (time units are 10 minutes long)
  • Task durations
  • Denominate the person in charge for every task
  • Simultaneous work is possible.

33
GANTT exercise 2
  • How long is the full project?
  • Denote the precedence relationships in the chart!

34
GANTT exercise 3
  • Show the schedule status on the GANTT chart for
    the same project after 80 minutes if
  • All the A, B and C ingredients are bought, but
    the purchase of ingredient D is only 67
    complete.
  • The 1st course is already half-cooked, but the
    operations on the 2nd dish could not started
    yet.

35
GANTT exercise 4
  • Plot a new chart with the same data but with real
    times within a day. The following information are
    added
  • The market, where the ingredients should be
    bought is open only from 8 a.m. to 10 a.m. and
    the earliest is the better.
  • The lunch preparations (including the cleaning)
    should be ready exactly at noun (12 a.m.).

36
Thanks for the attention!
Write a Comment
User Comments (0)
About PowerShow.com