Eskom Generation - PowerPoint PPT Presentation

About This Presentation
Title:

Eskom Generation

Description:

Eskom Generation way forward Three drivers of change impacting our business Need for a more integrated approach in growing capacity Eskom s strategic ... – PowerPoint PPT presentation

Number of Views:107
Avg rating:3.0/5.0
Slides: 13
Provided by: Christova7
Category:

less

Transcript and Presenter's Notes

Title: Eskom Generation


1
Eskom Generation way forward
2
Three drivers of change impacting our business
Market Restructuring
Continue preparation for deregulation (also
requires a degree of divisional independence)
  • Need for a more
  • integrated approach
  • in growing
  • capacity

Limited resource availability
Declining surplus capacity
Need to maximise synergies operational
excellence
3
Eskoms strategic positioning
  • Our core business is electricity
  • Generation
  • Transporting
  • Trading (among producers, wholesalers, and bulk
    users)
  • Retail (to end users)
  • Our target market
  • South Africa
  • SADC and the rest of Africa connected to the SA
    grid
  • Rest of Africa

4
Electricity demand and supply key challenges
  • South Africa is approaching the end of its
    surplus generation capacity
  • 1st challenge Avoiding mismatch between demand
    and supply
  • Excess capacity - stranded resources
  • Capacity shortage - constrained economic growth
  • 2nd challenge Correct choice of capacity to be
    constructed from an array of available options
    that differ dramatically in terms of
  • Cost (construction and operating)
  • Lead time to construction
  • Environmental impact
  • Operating characteristics

5
Eskom's Installed Generating CapacityRed Solid
Line until end 2004 Actual peak demand PLUS
10 RESERVE MARGIN, thereafter _at_ 2.5 growth in
peak demand PLUS 10 RESERVE MARGIN.Fifty year
assumed plant life. Demand Side Management
initiatives NOT included
6
5 Year Capital Expansion Plan
  • In October 2004, Cabinet approved the following
  • Eskom to lead this current phase of creating new
    electricity generation capacity
  • Earlier Cabinet decision to exclude Eskom from
    future build programme was reversed
  • Decisions on any future (beyond the current 5
    year programme) build programme will be on a case
    by case basis
  • 5-year infrastructure investment plan in South
    Africa's electricity infrastructure amounting to
    R95 billion (DPE tabling of vote to parliament)

7
Capacity Outlook - 2003 to 2022
  • 6 year-on-year demand increase
  • Major risks of insufficient supply options
  • Ageing infrastructure
  • Shortages if new build not initiated

8
Planning Process Flow
Increasing Certainty
Investment Decision
Concept Screening
Complete business case
PHASE 1 PRE-FEASIBILITY
PHASE 2 FEASIBILITY
BUILD
NEW CONCEPTS
9
Eskoms Return To Service (RTS) project
  • 3 stations with a combined nominal capacity of
    3800MW
  • built in the 1960s, and were mothballed due to
    high excess capacity in the late 1980s and
    1990s
  • An investment expenditure totalling R12 billion
    (nominal rand) on the return to service of the 3
    stations over the next 5 years

10
Budget Vote
  • Alongside this process, using Eskoms
    purchasing power, we would introduce the first
    significant Independent Power Producers (IPP).
    This allowed for the initial indicative 5-year
    investment figures to be provided with some
    degree of certainty.
  • Minister Erwins Budget Vote Speech, 15 April
    2005

11
SA enjoys globally competitive prices
29 gap
12
Eskom remains committed to keep the lights burning
Day Month Year
Write a Comment
User Comments (0)
About PowerShow.com