Matei Purice - PowerPoint PPT Presentation

About This Presentation
Title:

Matei Purice

Description:

The advantages of having a MTDRC in such contracts: ... 42 days Arbitration Examples of MTDRC in standard forms of contracts FIDIC Standard form of contracts ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 18
Provided by: Tuc54
Category:

less

Transcript and Presenter's Notes

Title: Matei Purice


1
Multi-tier Dispute Resolution
Mechanisms Enforcement Issues
  • Matei Purice
  • Associate
  • Competence Competence Principle.
  • Recurring Issues
  • ICC YAF Conference, Bucharest
  • 27 September 2010

2
Multi-tier Dispute Resolution Mechanisms -
Enforcement Issues
  • What is a multi-tier dispute resolution clause?
  • When should such a clause be inserted in a
    contract?
  • Are all the tiers enforceable?
  • Scenario I Final tier is arbitration
  • Scenario II Final tier is state court litigation
    The Romanian case
  • Special considerations for drafting the multi
    tier dispute resolution clause

3
What is a multi-tier dispute resolution clause
(MTDRC)
  • Contractual clause dealing with the settlement of
    disputes between the contracting parties.
  • Provides for distinct stages and separate
    procedures for solving the dispute.

4
The typical ingredients of a MTDRC
  • Stage 1 good faith negotiations or
    consultations between the parties
    for a certain period of time
  • Stage 2 Mediation, conciliation or other form of
    alternative dispute resolution (ADR)
    including binding but not final
    procedures such as expert determinations /
    dispute boards, etc.
  • Stage 3 Arbitration or state court litigation.

5
Rationale of having a MTDRC in the contract
  • Long term complex projects particularly in the
    construction sector.
  • The complexity of such projects entails the
    possibility of having very different issues under
    dispute bearing very different monetary values.
  • The advantages of having a MTDRC in such
    contracts
  • Tailor-made system of dispute resolution
    encompassing appropriate methods of solving
    disputes for each type of disputes that might
    arise
  • Various mechanisms aiming at solving the disputes
    as quick and cost effectively as possible.

6
Examples of MTDRC in very complex projects
  • The Channel Tunnel project
  • 2 stages
  • A panel of three independent experts who would
    render a written decision within 90 days
  • Arbitration
  • The Hong Kong Airport Core Programme
  • 4 stages
  • Decision of the Engineer
  • Mediation
  • Adjudication through a formal evidentiary
    proceeding with a written decision within 42 days
  • Arbitration

7
Examples of MTDRC in standard forms of contracts
  • FIDIC Standard form of contracts (1999 edition)
  • Adjudication
  • Amicable Settlement
  • Arbitration
  • World Bank Standard Bidding Documents for the
    Procurement of Works
  • Adjudication
  • Amicable Settlement
  • Arbitration

8
The Subject of Inquiry
  • What are the consequences if a party leapfrogs
    the initial tiers going directly to arbitration
    or, as the case may be, state court litigation?
  • Are the first tiers enforceable?

9
Scenario I Arbitration as the final tier the
ICC case
  • Two degrees of control may be envisaged
  • Dismissal of the claim by the ICC Court under
    Article 6.2
  • In the few cases dealing with the issue, the
    Court either found that prima facie an
    arbitration agreement existed or that the issue
    did not relate to the existence or validity of
    the arbitration agreement and therefore referred
    the matter to the arbitral tribunal.
  • Determination of the issue by the ICC Tribunal by
    virtue of the competence-competence principle
  • Non fulfillment of a conciliation step
  • generally depends on the wording of the clause
    (mandatory vs. optional) and on the facts of the
    case (conduct of the parties).
  • Non fulfillment of an intermediary adjudication
    procedure such as expert determination / dispute
    board
  • Inadmissibility (ICC Case No. 6238 and 6535)
  • Prematurity (ICC Case No. 6276 and 6277)
  • Staying of the proceedings and ordering the
    parties to go and fulfill the prior procedures.

10
Scenario I Arbitration as the final tier the
ICC case
  • ICC Case No. 9977 (Final Award of 22 June 1999)
    prior amicable settlement procedure at senior
    management level for 14 days
  • A prior process like the one set forth in the
    Agreement, rather implies a an attitude and
    behavior of the parties inspired in a true and
    honest purpose of reaching an agreement
  • ICC Case No. 4840/1986 Clause 67 of the FIDIC
    Conditions of Contract (second Edition)
    mandatory prior recourse to an engineer
  • Such submission of claims in the first place
    to the Consultant for settlement is required
    under Clause 67 and is a condition precedent to
    filing arbitration with the I.C.C., and that it
    appears, therefore, that the Plaintiffs claims
    for Phase II were prematurely and unduly referred
    to arbitration, and consequently this Tribunal
    does not have jurisdiction thereover.

11
Scenario I Arbitration as the final tier the
ICC case
  • Particular circumstances
  • The ICC ADR Model Clause 4 - Obligation to submit
    dispute to ADR, followed by ICC arbitration as
    required
  • The ICC Dispute Board Model Clause

12
Scenario I Arbitration as the final tier - a
CCIR case
  • The arbitral clause in the contract provided for
    a mandatory conciliation procedure prior to
    commencing arbitration.
  • Respondent objected to Claimants request for
    arbitration arguing that such is premature given
    the non-fulfillment by Claimant of the prior
    negotiation procedures. The arbitral tribunal
    held
  • By contrast to the mandatory conciliation
    procedure envisaged by Article 7201 of the Civil
    Procedure Code applicable in commercial disputes
    under the jurisdiction of the state courts, in
    arbitral matters the failure to fulfill the prior
    conciliation step, provided by the parties, does
    not entail a rejection of the claim as premature
    or, as certain state courts have held, as
    inadmissible but rather imposes, by virtue of the
    mandatory force of the contract, that such
    deficiency is remedied by ordering the claimant
    to first carry on the conciliation procedure.
  • (CCIR Case no. 201/2007 Interlocutory award of
    November 1, 2007)

13
Scenario II State court litigation as the final
tier
  • Romania - MTDRC providing for conciliation
    followed by state court litigation
  • The issue Enforceability of the conciliation
    step
  • Differences between the provisions of Article
    7201 of the Civil Procedure Code (mandatory
    conciliation procedure applicable in commercial
    cases) and conventional agreements for
    conciliation
  • Article 7201 is the minimum requirement under the
    law
  • The parties may provide for a more detailed
    conciliation procedure but have to follow at
    least the requirements of Article 7201
  • The court may decide that the claim is
  • Inadmissible
  • Premature

14
Scenario II State court litigation as the final
tier
  • Romania - MTDRC providing for mediation followed
    by state court litigation
  • The issue Enforceability of the mediation stage
  • Possible approaches
  • May the judge stay the court proceedings?
  • Law No. 192/2006 on mediation
  • Article 6 provides that the judicial and
    arbitral authorities as well as other entities
    having judicial attributions inform the parties
    of the possibility and advantages of recurring to
    mediation and guides them to follow such means in
    order to settle their dispute.
  • Article 62 provides that (in civil matters!) the
    judge will stay the proceedings in order to allow
    the pursuance of the mediation procedure
  • The New Civil Procedure Code (Not yet in force)
    Article 21 The judge will recommend the parties
    the amiable resolution of the case through
    mediation, in accordance with the special laws.

15
Scenario II State court litigation as the final
tier
  • Romania - MTDRC providing for expert
    determination / dispute board followed by state
    court litigation
  • Poor case-law and doctrine on the matter.
  • Possible approaches
  • The court has no express legal grounds to dismiss
    the case either as inadmissible or premature
  • The court has no express grounds to order the
    staying of the proceedings
  • The parties agreement will be considered a
    contractual arrangement with no effects on the
    state courts jurisdiction
  • The court may consider awarding damages for
    breach of contract
  • It may be advisable to include a monetary
    evaluation of the prejudice for breach of the
    MTDRC in the contract

16
Concluding Remarks
  • Special care when drafting the MTDRC
  • Mandatory vs. optional stages may vs.
    shall
  • Clear and objective criteria for moving from one
    stage to the next
  • Possibility to provide for damages in case of
    breach of the MTDRC
  • Choosing the final tier arbitration vs. state
    court litigation.
  • Special care when following the MTDRC
  • Supporting documents attesting that efforts to
    negotiate in good faith have been undertaken by
    Claimant
  • Observe the time limits set up in the MTDRC.

17
Competence Competence Principle. Recurring
IssuesICC YAF Conference, 27 September 2010,
Bucharest, Romania
  • Matei PURICE
  • Associate
  • E-mail matei.purice_at_tuca.ro 
  • Tel (40-21) 204 88 90
  • Web www.tuca.ro
Write a Comment
User Comments (0)
About PowerShow.com