Title: Synopsis


1
TIPS 02May02 Carl Biagetti/NISD
SMOV3B PROGRESS
2
SMOV3b PLAN
  • MEASURE/MONITOR NEW SPACECRAFT BEHAVIOR
  • POINTING, THERMAL, POWER
  • RECOMMISSION EXISTING SIs
  • STIS, WFPC2
  • COMMISSION NEW SIs
  • ACS
  • Science/EROs in early April
  • ACS SMOV complete in early June
  • REVIVE AND RECOMMISSION NICMOS
  • VIA NCS COOLDOWN
  • Science/EROs in early May
  • NICMOS SMOV complete in early August

3
---SPACECRAFT EXISTING INSTRUMENTS ---Progress
since 4 April TIPS
  • PCS - Vehicle Disturbance Test (VDT) analysis
    uncovers PCS control-law bug that was causing
    anomalous jitter
  • Jitter was also seen in FGS data
  • Corrected last week
  • STIS - Recommissioned
  • MAMA CCD science has been re-enabled and has
    resumed
  • STIS SMOV complete
  • WFPC2 - Recommissioned
  • UV Monitoring complete
  • GO science enabled and has resumed
  • WFPC2 SMOV complete
  • FGS - Recommissioned
  • Guiding and astrometry
  • Jitter test to be repeated after PCS control law
    update

4
--- NEW INSTRUMENTS --- Progress since 4 April
TIPS
  • ACS
  • Coarse/fine alignment completed 2 April
  • ERO observations performed 1 9 April
  • Media release 30 April
  • SBC activation delayed to early May
  • NICMOS
  • Cooled to target temperature ( 75 degK)
  • NICMOS re-enabled 19 April
  • intentionally safed on 28 March to facilitate
    cooldown
  • Filter Wheel test completes today

5
SMOV PROGRESS AS OF 01 MAY
PLANNED ACTIVITIES
COMPLETED ACTIVITIES
PERCENT COMPLETE
6
MAJOR SMOV MILESTONES UPDATED AS OF 01 May
  • Release 09 March
  • NICMOS Cooldown 18
    Mar 12 Apr (17 day delay)
  • STIS Basic CCD GO Science 22 March
  • WFPC2 Cooldown 22 March
  • WFPC2 GO Science 26 March
  • ACS ALIGN 22 March 2 April 5 days ahead of
    plan
  • ACS CCD EROs 01-09 April 1 week ahead of
    plan
  • ACS Basic GO/GTO Science (CCD) 11 April on
    schedule
  • STIS MAMA GO Science 15 April delayed 2weeks
    for long NICMOS cooldown
  • NICMOS Filter Wheel Test 23 April
    02 May 4 week delay
  • NICMOS Alignment (PAM focus) 03 - 09 May 4
    week delay
  • NICMOS EROs 10 - 16 May 2 week delay
  • NICMOS Basic GO Science Enable 10 May (approx.)
    2 week delay
  • (without fine aperture locations)
  • ACS Coronography Enabled (incl. EROs) 09 June
    3 weeks ahead of plan
  • NICMOS Coronography Enabled 12 August SMOV
    Complete

7
ACS SMOV SCHEDULE
8
NICMOS SMOV SCHEDULE