Title: QUALITY ASSURANCE IN Civil WORKS BY S.N.PANDEY, CIVIL WORKS MANAGER, BIHAR EDUCATION PROJECT COUNCIL, PATNA
1QUALITY ASSURANCE IN
Civil WORKS BY S.N.PANDEY, CIVIL WORKS
MANAGER, BIHAR EDUCATION PROJECT COUNCIL, PATNA
2QUALITY CONSTRUCTION
- Quality construction increases the lifespan,
stability and serviceability of the structure.
It also combines all the resources into
economical output and reduces unnecessary repairs
and maintenance. To cap all it disseminates the
reputation of the agency. - Quality of Civil Work depends on the use of
correct structural design, specifications and
proper material and workmanship. - Rational design is an effective tool for cost
effective and quality construction. As such the
design should be based on the latest relevant
Indian Standards
3SPECIFICATION AND PROPER MATERIALS
- The quality building material, like Cement,
Brick, Aggregate (Course fine) should be
procured at competative rate. The community
should be trained about quality of each building
material and how to procure them. The aim is to
procure best possible quality material at
competative rate.
4 CEMENT CONCRETE
- Followings are constituents of concrete -
- Aggregate
- Sand
- Cement
- Plasticizers for workability.
5 CEMENT
- Followings are the grades of cement being
manufactured- - 33,43 53 MPa.
- ISI / ISO marked cement of ACC, Ultra
tech/Ambuja Birla Gold/Lafarge, Concreto etc to
be procured.
6 CEMENT
- Price increases with increase in grades
- For good construction 33 43 grades are ideal.
- Initial setting time is 30 minutes final
setting time is 600 minutes - With the passage of time cement loses strength
due to hydration as follows- - Period - loss in strength of cement
- Three months 20
- Six 30
- Twelve months 40
- As such fresh cement is to be used
7AGGREGATES
- Coarse aggregate- 20mm down, well graded is
required for all the R.C.C. works in buildings. - Sand- Sand of I.S. Zone II and F.M. not less than
2.25 - Grading of coarse and fine aggregates shall
follow the curve of Road Note 4 which is
attached. On the basis of large nos. of cube
tests carried out combination of the aggregates
is recommended for higher strength and quality
concrete in concluding Para of this note. The
method of test for aggregates for concrete is
given in IS 5779. - The nominal maximum size of coarse aggregate
should be as large as possible within the limits
specified but in no case greater than one-fourth
of the minimum thickness of the member, provided
that the concrete can be placed without
difficulty so as to surround all reinforcement
thoroughly and fill the corners of the form. - For heavily reinforced concrete members as in the
case of ribs of main beams, the nominal maximum
size of the aggregate should usually be
restricted to 5 mm less than the minimum clear
distance between the main bars or 5 mm less than
the minimum cover to the reinforcement whichever
is smaller. -
8 BRICKS
- Bricks as per I.S. 1077 of class 125 preferably.
The water absorption by the brick should be
maximum up to 20.
9WATER CEMENT RATIO BULKAGE IN SAND
- I.S. 456 clauses 9.3 and 9.3.1 deals with
quantity of water of maximum amount to be added
to per 50 Kg. of cement. - Water present in sand should be determined. The
simplest method of determining the bulking of
sand in the field is to fill a graduated jar with
the sand being used in the work upto a mark. Add
sufficient water. Sand will settle down to lower
mark. Difference in the levels of sand gives the
rough idea of bulking which has to be compensated
by increase in the amount of sand. The moisture
content and bulking of medium size sand is given
below. - Moisture content Bulkage
- 0.4 2
- 0.75 4
- 1.45 8
- 3.1 16
- 4 20
-
10WATER CENMENT RATIO BULKAGE IN SAND
- Moisture content Bulkage
- 5 22
- 8 28
- 10 26
- 12 18
- 15 14
- 20
- There is no bulkage in sand if fully saturated or
completely dry. - It is needless to say that very effort be made to
make silt, clay, dust in the aggregates almost
nil. The maximum percentage of fines in aggregate
is limited to 3 of coarse and uncrushed fine
aggregate according to I.S. 383
11 WORK FORCE
- The work force consists of skilled unskilled
workers as under - SKILLED Masons, carpenter, plumber,
electrician, blacksmith, bar benders, etc. if
these are very well trained, this can make lot of
dent in quality construction. - UNSKILLED Labour force, which assist the
skilled workers, should also be trained in order
to achieve quality. (examples)
12 QUALITY CONTROL MEASURES
- Visual inspection.
- Quantitative Quality measures.
- Testing of building material like
- Sand
- Bricks
- Concrete Mix
- Cement Water ratio
- Cement mortar
13QUALITY CONTROL OF CEMENT CONCRETE
- 1. Concrete Mix Design
- Concrete must be satisfactory in two stages,
namely in the plastic stage and the hardened
stage. If the condition of the plastic concrete
is not satisfactory it can not be properly
compacted and its structural value is reduced.
Thus, if there are 5 of air voids due to
incomplete compaction, the strength will be
reduced by 30 and 10 of air voids will cause a
loss of strength of about 60. The satisfactory
compaction can be obtained only if the concrete
is satisfactorily and sufficiently workable. The
property of workability, therefore become of
vital importance from structural point of view. - 2. Workability of Concrete
- A Concrete is said to be workable, if it can be
easily mixed, placed, compacted and finishes at
the surface. - A workable concrete should not show any
segregation or bleeding. - Segregation occurs when coarse aggregate try to
separate out from the paste and get accumulated
at one side. This results in large voids, less
strength and less durability. -
14QUALITY CONTROL OF CEMENT CONCRETE
- 3. Tests for workability
- Slump Test I.S. 1199 para 5 deals with this
test. The slump test apparatus is very simple and
cheap and the test can be conducted during the
progress of work in the filed. I.S. 456 para 7.1
prescribes the values of workability. -
15QUALITY CONTROL OF CEMENT CONCRETE
- 4. Durability
- The durability of concrete depends on adequate
cement content and low water cement ratio. Cement
and water is needed to bind together the
aggregates firmly. Thus, the suitable combination
of the aggregates is key to quality concrete. The
proper grading of the aggregates make the
concrete dense. This also governs the quantity of
water required for workability -
16FACTOR GOVERNING QUALITY OF CONCRETE
- Cement Aggregate ratio
- Grading of the aggregates
- Volume/ weight batching
- Mixing
- Compaction
- Curing
- Water / Cement Ratio
- Quality of Sand
- Quality of Water
-
17FACTOR GOVERNING QUALITY OF CONCRETE
- Machine Mixing Sequence
- First pour 25 of the total quantity of water in
the drum. - Dry coarse and fine aggregates are to be
discharged into drum - Full quantity of cement is to be deposited in the
drum - Finally balance quantity of water to be poured.
25 to 30 revolutions are needed for mixing with
drum rotating _at_ 15-20 revolutions per minute -
18(I.S. 456 Clauses 6.1.2, 8.2.4.1 9.1.2)Minimum
Cement Content, Maximum Water-Cement Ratio and
Minimum Grade of Concrete for Different Exposures
with Normal Weight Aggregates of 20 mm Nominal
Maximum Size
Minimum Cement Content Kg/m3 Maximum Free Water- Cement Ratio Minimum Grade of Concrete
300 0.55 M 20
19(I.S. 456 Clauses 9.3 9.3.1) PROPORTIONS FOR
NOMINAL MIX CONCRETE
Grade of Concrete Total Quantity of dry Aggregates by Mass per 50 kg of Cement, to be Taken as the Sum of the Individual Masses of Fine and Coarse Aggregates, Kg, Max Proportion of Fine Aggregates to Coarse Aggregates (by Mass) Quantity of Water per 50 kg of Cement, Max
M20 250 kg i.e. coarse aggregate - 166.66 Kg Fine aggregate- 83.33 kg Generally 12 but subject to an upper limit of 11½ and a lower limit of 12½ 30
20Volume batching per bag of cement i.e. 35 liters
- 50 kg cement 250 aggregate (maximum)
- volume 0.0347 m3 Volume - 0.1389 m3
- i.e. cement aggregate ratio ¼ by volume.
- M20 (1 1.5 3)
- i.e. Cement Aggregate ratio 14.5
- By volume (per bag cement) 11.53 3552.5 105
(all in litres) - Hence batching is to be done by mass of the
aggregate.
21REINFORCEMENT
- The standard trade/ I.S. marks is to be taken
into account. In case standard bars are not
available the weight of piece bar is to be
determined by weighing in the shop which should
be compared with the following table to know
whether the bar is standard one. - Diameter of the rod Weight in Kg/metre
- 6mm 0.222
- 8mm 0.395
- 10mm 0.617
- 12mm 0.888
- 16mm 1.578
22TIMING OF CONCRETING IN SUMMER SEASON
- In freshly laid slabs, sometimes cracks occur
before concrete has set due to plastic shrinkage.
This happens if concrete surface loses water
faster than bleeding action brings it to top.
Quick drying of concrete results in shrinkage and
as concrete is plastic stage can not resist any
tension, short cracks develop in the material.
These cracks maybe 5 to 10 cm. in depth and the
is width could be as much as 3 mm. - Rate of evaporation from the surface of the
concrete depends on temperature of concrete, gain
of heat from suns radiation, relative humidity
of ambient air and velocity of wind playing over
concrete surface. As such in winter days, there
is no problem of timing of concreting. In summer
concreting should be done during early hours of
day when aggregates and mixing water is
comparatively cool and sun rays are slanting.
After concreting, top surface of concrete should
be covered with plastic sheets/gunny bags, straw
or any other available materials. This will
minimise surface shrinkage cracking in the
concrete.
23FORMWORKS
- The shape, and surface finish of concrete depends
upon the Form Work. - Suitable chamber in the form works shall be
provided in horizontal members of the structures,
specially in long span to counteract the effects
of deflection. As a rough guide, it may be 1 to
250 for beams and 1 in 50 for cantilevers. - The inside surfaces of formwork shall be coasted
with soap solutions, raw linseed oil or any other
material, approved by the Engineer in-charge so
as to prevent adhesion of concrete to formwork.
Release agents shall be applied strictly in
accordance with the instructions and shall not be
allowed to come into contact with any
reinforcement. Immediately before concreting, all
formwork shall be thoroughly cleaned. - Propping and centering- Props used for centering
shall be of steel or timber post, ballies or any
other material, approved by the
Engineer-in-charge.
24FORMWORKS
- The shape, and surface finish of concrete depends
upon the Form Work. - It should be strong to support wet concrete and
have smooth surface to prevent loss of slurry
from the concrete. - Thin, deteriorated or non-vertical ballies will
not be permitted at site. - Timber ballies shall always be vertical and never
be in inclined position. - Any scaffolding shall only be on hard ground and
not soft soil.
25STRIPPING TIME OF FORM (Ref
IS-456, Para 11.3.1)
Sl. No. Type of Formwork Minimum period before striking forms
1. Vertical formwork to columns, walls, beams 16-24 h
2. Slabs spanning up to 4.5 m Slabs spanning over 4.5 m 7 days 14 days
3. Beams and Arches spanning up to 6.0 m/ over 6.0 m 14 days/21 days
26CONCLUSION MIX DESIGN
- Following mix design of 124 (Cement Sand
Aggregate) gives strength required for M20 - Cement Aggregate ratio - 16 (i.e. 124)
- Sand - 24
- Nominal size 10mm - 16
- Nominal size 20mm - 60
- This combination gives a minimum of 100 excess
strength over nominal mix of 124. i.e. M15
27 WATER ABSORPTION OF BRICKS
- Field Test The Test specimen shall consist of
five whole dry bricks and shall be selected at
random from the stack. The apparatus shall
consist of a balance sensitive of within 0.2 to
0.3 percent of the weight of the specimen. - The test specimen shall be weighed and shall then
be completely immersed in clean water at room
temperature and allowed to remain in this State
for a period of 24 hours. The specimen shall then
be taken out wiped with a damp cloth and then
weighed immediately.
28 Percentage of water absorption
- Weight of bricks after 24 hours immersion
- ________________________________ x
100 - Weight of dry bricks
29 WATER ABSORPTION OF BRICKS
- Laboratory Test The Test specimen shall
consist of five whole selected at random from the
lot of bricks obtained. The apparatus shall
consist of a balance sensitive to within 0.1
percent of the weight of the specimen. - The test specimen shall be dried to constant
weight in ventilated oven at 1100 to 1150 . The
specimen, shall then be cooled approximately to
room temperature and weighed.
30- The dry specimens shall be completely immersed
without preliminary partial immersion, in clean
water at 15.50 to 300 C for 24 hours. Each
specimen shall then be removed, the surface water
wiped off with a damp cloth 2nd the specimen
weighed. Weighing any one specimen shall be
completed within three minutes after removing the
specimen from the water.
31 DETERMINATION OF COMPRESSIVE STRENGTH
OF BRICKS
- Five bricks shall be immersed in water at 250
to 290 C for 24 hours. They shall then be removed
and allowed to drains at room temperature for
about five minutes and wiped free from surplus
moisture. Their frogs shall be filled with mortar
composed of one part portland cement and one and
a half parts clean coarse sand graded to 3 mm and
down. The bricks shall then be stored under damp
sack for 24 hours. After the expiry of this
period, they shall be immersed in water for seven
days.
32- At the end of seven days, the samples of
bricks shall be taken out, wiped dry and placed
with the flat surfaces horizontal and the mortar
filled face up wards between two-three plywood
sheets each approximately 3 mm thick and
carefully centered between the plates of the
compression to testing machine. The load shall
be applied axially at the uniform rate until
failure occurs. - Arithmetic mean of the Maximum load at failure
- Compressive Strength Area of bricks
33 Thank you