8 NCRs were generated during TMCM preproduction - PowerPoint PPT Presentation

1 / 5
About This Presentation
Title:

8 NCRs were generated during TMCM preproduction

Description:

Finish machining dimensions did not meet dimension specified on drawing. ... original wire bond on die off -center to allow room for re-bond if required. ... – PowerPoint PPT presentation

Number of Views:19
Avg rating:3.0/5.0
Slides: 6
Provided by: RobertP65
Category:

less

Transcript and Presenter's Notes

Title: 8 NCRs were generated during TMCM preproduction


1
NCR Summary
  • 8 NCRs were generated during TMCM preproduction
  • NCR 00029, CLOSED
  • Re-qualification of Omnetics connector is
    required based on process and design revision.
  • NCR 00041, OPEN- Cause and Corrective Action
    submitted
  • Finish machining dimensions did not meet
    dimension specified on drawing.
  • Configuration management process was not adhered
    to, released drawing was not revised and
    re-released to reflect correct dimensions.
  • Tracker meeting held to review drawing release
    configuration management process.
  • Drawing was updated with correct finish machine
    dimensions and released. PWBs were re-inspected
    per released design.

2
NCR Summary
  • NCR 00042, OPEN- Cause and Corrective Action
    submitted
  • One PWB dispositioned scrap for exposed copper
  • One PWB dispositioned scrap for foreign
    material/stain
  • Qty 9 TMCMs RTV for re-label of Serial No.
    Traceability maintained, Re-inspection will be
    performed.
  • NCR 00043, OPEN- Cause and Corrective Action
    submitted
  • Omnetics connector saver is being redesigned
  • 1) Jack screw too long.
  • 2) Gap under jack screw introducing stress and
    bond of plastic body to alum. shell fails.
  • 3) Low shear strength of bond line.
  • Redesign complete, NCR will remain open until
    redesign verified.

3
NCR Summary
  • NCR 00044, OPEN- Cause and Corrective Action
    submitted
  • GSFC rejected dielectric thickness per IPC-6011,
    Class 3
  • Configuration management was not adhered to.
    TMCMs were built to unreleased rev. 6.
  • Tracker Meeting held to review configuration
    management process.
  • Design released, parts meets dielectric
    requirement.
  • NCR 00046, CLOSED
  • Teledyne reported SN 176 to have physical damage
    to Pitch Adaptor traces. Unit passed Final
    Electrical Test.
  • Disposition preproduction unit use-as-is.
    Teledyne reviewed handling procedures to preclude
    recurrence.

4
NCR Summary
  • NCR 00048, CLOSED
  • GSFC rejected panel 152 coupon test for internal
    annular rings shorter that 0.002 inches.
  • Audit performed on all 00077 PWBs in bldg. 33.
  • 152-2 152-4 scrapped.
  • 152-1, 152-3, 152-5 were utilized in non-flight
    preproduction MCMs. These MCMs are marked
    non-flight, introduction into flight stream is
    not possible.
  • NCR 00050, CLOSED
  • GSFC rejected panel 158 coupon test for internal
    annular rings shorter that 0.002 inches.
  • All nonconforming PWBs (qty 4) located and
    quarantined in Bldg. 33 MRB cabinet.

5
Preproduction Waivers
  • Waivers were requested and granted during TMCM
    preproduction for the following
  • Source inspection not performed
  • Source Inspector hired
  • Reject compound wire bond per MIL-STD-883
  • Test in process to translate original wire bond
    on die off -center to allow room for re-bond if
    required.
  • Second application of encapsulation to cover
    exposed wire bonds near ends of TMCM.
  • Standard rework instructions developed
  • Wire bond over disturbed metal
  • Test in process to translate original wire bond
    on die off -center to allow room for re-bond if
    required.