Managing a Complex Setback Levee Project Habitat Creation Through Restoring Floodplain Processes for - PowerPoint PPT Presentation

1 / 85
About This Presentation
Title:

Managing a Complex Setback Levee Project Habitat Creation Through Restoring Floodplain Processes for

Description:

Managing a Complex Setback Levee Project Habitat Creation Through Restoring Floodplain Processes for – PowerPoint PPT presentation

Number of Views:232
Avg rating:3.0/5.0
Slides: 86
Provided by: hsm3
Category:

less

Transcript and Presenter's Notes

Title: Managing a Complex Setback Levee Project Habitat Creation Through Restoring Floodplain Processes for


1
Managing a Complex Setback Levee
ProjectHabitat Creation Through Restoring
Floodplain Processesfor Multiple Benefits
  • Dan D. Wrye
  • Program Services Manager
  • Public Works and Utilities, Water Programs
  • April 2007

2
Water Programs DivisionPublic Works and Utilities
  • Surface water management utility
  • Levee system
  • Capital projects
  • Municipal NPDES stormwater
  • Basin plans
  • Lands management
  • Nonpoint source pollution, watershed councils
  • Salmon recovery lead entity

3
Soldiers Home Setback Levee
  • Sponsor
  • Pierce County Public Works and Utilities, Water
    Programs Division
  • Pierce County Lead Entity (WRIAs 10/12)
  • Partners
  • Hylebos Partners, Puyallup Tribe, US ACOE

4
Project Description
  • Construct new levee, setback
  • 5,150 feet long
  • 10 feet average height
  • 15 feet wide at top
  • 3 feet thick armor facing
  • 10 feet wide X 3 feet toe depth
  • Remove existing levee
  • Open up 67 acres of riparian floodplain corridor

5
County-line
Tacoma
White/Puy Confluence
Fennel Creek
Soldiers Home
Ford
6
Soldiers Home Setback Levee Project Location
Puyallup River Mile 21.5 22.4 Town of Orting
7
Objectives
  • Flood damage reduction, fish benefit
  • Allow for more natural riverine and floodplain
    functions
  • Floodplain reconnection
  • Reestablish key habitat
  • Off-channel rearing
  • Spawning

8
  • 27 structural, non-structural
  • 18 criteria evaluated
  • Setbacks 2nd highest score
  • Soldiers Home site hotspot

9
(No Transcript)
10
  • Reduce scouring
  • Stable spawning habitat
  • Over-wintering habitat
  • Forage and browse for wildlife
  • Increase channel capacity

11
  • Soldiers Home Setback Levee
  • Puyallup River fall chinook (priority stock)
  • Disconnected floodplain (watershed processes
    impacted)
  • Lower and middle Puyallup River (high priority
    areas)
  • Levee setbacks (priority actions)

12
(No Transcript)
13
Orting
Soldiers Home Setback Levee
14

Alignment of Soldiers Home Levee
15
Costs
  • Property acquisition 1,600,000
  • Design, permitting 565,000
  • Construction 4,108,000
  • Total Cost 6,273,000
  • Not included US ACOE in-kind contribution to
    design and permitting

16
Soldiers Home Levee Funding Challenges
  • Corps of Engineers
  • Design, Construct
  • February 2004
  • No money for construction
  • No money to finish design
  • Spring 2004
  • Water Programs hires Tetra Tech/KCM
  • Design 85 vs. 15
  • 3.7 million funding gap

17
Rescued from the Drawing Board
  • Natural resource damage trustees
  • Potentially responsible parties
  • Credit for cleanup obligations
  • 2 agreements
  • 2.3m in escrow pending Trustees approval and
    permitting
  • Money released at construction, with interest!
  • Worked well!

18
Funding
  • SRFB 990,000
  • Pierce County 565,000
  • Port of Tacoma 800,000
  • Pierce County 800,000
  • Hylebos Partners 2,300,000
  • US ACOE In-kind

19
Challenges -- Permits
  • Corps of Engineers
  • NEPA EA 8/04
  • FONSI 3/05
  • Biological Assessments 8/04 and 10/04
  • Amended 4/06 (bull trout critical habitat)
  • JARPA 6/05
  • 404 Issued 7/18/06
  • Bids opened June 16th!
  • Water Programs offered to fund COE permit writer
  • Work window July 15 thru August 31
  • HPA work window July 15 thru September 15

20
Challenges -- Permits
  • Shorelines and Land Use City of Orting
  • Recreation, evacuation, roadway preferences
  • Impact on shoreline jurisdiction
  • Hydraulics Permit WDFW
  • Very supportive
  • Follow-up concerns

21
Challenges -- Construction
  • Advertised May 31, 2006
  • Bids opened June 16, 2006
  • 404 received July 18!
  • Two bids submitted
  • KLB Construction low bidder
  • Extent of clearing challenge
  • Construction July thru October 2006

22
BeforeUpstream End
23
BeforeUpper Middle
24
BeforeLower Middle
25
BeforeDownstream End
26
During Construction Upper
27
During Construction Lower Middle. Note X-mas
Trees.
28
Upper End, Election Day Flood, 11/06
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
(No Transcript)
36
(No Transcript)
37
From the AirLooking Downstream 11/06
38
(No Transcript)
39
(No Transcript)
40
(No Transcript)
41
(No Transcript)
42
(No Transcript)
43
(No Transcript)
44
(No Transcript)
45
(No Transcript)
46
(No Transcript)
47
Note X-mas Trees
48
(No Transcript)
49
(No Transcript)
50
Upper End, November 2006
51
Upper End, April 2007
52
(No Transcript)
53
(No Transcript)
54
(No Transcript)
55
(No Transcript)
56
(No Transcript)
57
(No Transcript)
58
(No Transcript)
59
(No Transcript)
60
(No Transcript)
61
(No Transcript)
62
(No Transcript)
63
(No Transcript)
64
(No Transcript)
65
Project Team
  • Pierce County
  • Randy Brake, David Renstrom, Dan Wrye, Hans
    Hunger, Harold Smelt, Tony Fantello, Tim Ramsaur,
    Debby Hyde
  • Tetra Tech
  • Larry Gibbons, Tony Melone, John Herrmann,
    Deborah Scheibner
  • US ACOE
  • Laura Orr, Lester Soule, Cathy Desgarden, Beth
    Coffey, Michelle Walker, Ron Wilcox, Matt
    Bennett, Phillip Hoffman
  • Key Players
  • Russ Ladley, Puyallup Tribe
  • Travis Nelson, WDFW
  • Clark Davis, James Handmacher, Hylebos Partners
  • Brian Abbott, Leslie Ryan-Connelly, IAC
  • USFWS, NOAA Fisheries, NOAA Restoration Center

66
Lessons Learned
  • Multiple benefits made it happen
  • Multiple partners
  • Persistency
  • Manage expectations
  • Dont expect reviewers get all they need from
    designs
  • Adaptive management
  • Cant sit on laurels

67
County-line
Tacoma
Habitat Creation Through Restoring Floodplain
Processesfor Multiple Benefits
White/Puy Confluence
Fennel Creek
Soldiers Home
Dan D. Wrye, Program Services Manager Water
Programs Division (253) 798-4672
dwrye_at_co.pierce.wa.us
Ford
68
Ford Setback Levee the 1st
69
Orting
Soldiers Home Setback Levee
Ford Setback Levee
70
Ford Setback Levee Construction (1997)
71
Ford Levee Removal Operation (1997)
72
Ford Levee 1998
73
Ford levee 2005
Ford Levee 2005
74
Puyallup River Ford Setback Levee Looking
Downstream from the South - RM 24.8
75
1998 detail
76
2005 detail
77
Ford Setback Levee During Election Day Flood of
Nov 2006
78
County-line
Tacoma
White/Puy Confluence
Fennel Creek
Soldiers Home
Ford
79
(No Transcript)
80
Confluence Puyallup, White
81
Confluence Puyallup, White
82
County Line
83
County Line, Whiteacross from Pacific
84
County-line, White RiverLooking Downstream,
Upper End
85
County-line
Tacoma
Habitat Creation Through Restoring Floodplain
Processesfor Multiple Benefits
White/Puy Confluence
Fennel Creek
Soldiers Home
Dan D. Wrye, Program Services Manager Water
Programs Division (253) 798-4672
dwrye_at_co.pierce.wa.us
Ford
Write a Comment
User Comments (0)
About PowerShow.com