Title: Managing a Complex Setback Levee Project Habitat Creation Through Restoring Floodplain Processes for
1Managing a Complex Setback Levee
ProjectHabitat Creation Through Restoring
Floodplain Processesfor Multiple Benefits
- Dan D. Wrye
- Program Services Manager
- Public Works and Utilities, Water Programs
- April 2007
2Water Programs DivisionPublic Works and Utilities
- Surface water management utility
- Levee system
- Capital projects
- Municipal NPDES stormwater
- Basin plans
- Lands management
- Nonpoint source pollution, watershed councils
- Salmon recovery lead entity
3Soldiers Home Setback Levee
- Sponsor
- Pierce County Public Works and Utilities, Water
Programs Division - Pierce County Lead Entity (WRIAs 10/12)
- Partners
- Hylebos Partners, Puyallup Tribe, US ACOE
4Project Description
- Construct new levee, setback
- 5,150 feet long
- 10 feet average height
- 15 feet wide at top
- 3 feet thick armor facing
- 10 feet wide X 3 feet toe depth
- Remove existing levee
- Open up 67 acres of riparian floodplain corridor
5County-line
Tacoma
White/Puy Confluence
Fennel Creek
Soldiers Home
Ford
6Soldiers Home Setback Levee Project Location
Puyallup River Mile 21.5 22.4 Town of Orting
7Objectives
- Flood damage reduction, fish benefit
- Allow for more natural riverine and floodplain
functions - Floodplain reconnection
- Reestablish key habitat
- Off-channel rearing
- Spawning
8- 27 structural, non-structural
- 18 criteria evaluated
- Setbacks 2nd highest score
- Soldiers Home site hotspot
9(No Transcript)
10- Reduce scouring
- Stable spawning habitat
- Over-wintering habitat
- Forage and browse for wildlife
- Increase channel capacity
11- Soldiers Home Setback Levee
- Puyallup River fall chinook (priority stock)
- Disconnected floodplain (watershed processes
impacted) - Lower and middle Puyallup River (high priority
areas) - Levee setbacks (priority actions)
12(No Transcript)
13Orting
Soldiers Home Setback Levee
14 Alignment of Soldiers Home Levee
15Costs
- Property acquisition 1,600,000
- Design, permitting 565,000
- Construction 4,108,000
- Total Cost 6,273,000
- Not included US ACOE in-kind contribution to
design and permitting
16Soldiers Home Levee Funding Challenges
- Corps of Engineers
- Design, Construct
- February 2004
- No money for construction
- No money to finish design
- Spring 2004
- Water Programs hires Tetra Tech/KCM
- Design 85 vs. 15
- 3.7 million funding gap
17Rescued from the Drawing Board
- Natural resource damage trustees
- Potentially responsible parties
- Credit for cleanup obligations
- 2 agreements
- 2.3m in escrow pending Trustees approval and
permitting - Money released at construction, with interest!
- Worked well!
18Funding
- SRFB 990,000
- Pierce County 565,000
- Port of Tacoma 800,000
- Pierce County 800,000
- Hylebos Partners 2,300,000
- US ACOE In-kind
19Challenges -- Permits
- Corps of Engineers
- NEPA EA 8/04
- FONSI 3/05
- Biological Assessments 8/04 and 10/04
- Amended 4/06 (bull trout critical habitat)
- JARPA 6/05
- 404 Issued 7/18/06
- Bids opened June 16th!
- Water Programs offered to fund COE permit writer
- Work window July 15 thru August 31
- HPA work window July 15 thru September 15
20Challenges -- Permits
- Shorelines and Land Use City of Orting
- Recreation, evacuation, roadway preferences
- Impact on shoreline jurisdiction
- Hydraulics Permit WDFW
- Very supportive
- Follow-up concerns
21Challenges -- Construction
- Advertised May 31, 2006
- Bids opened June 16, 2006
- 404 received July 18!
- Two bids submitted
- KLB Construction low bidder
- Extent of clearing challenge
- Construction July thru October 2006
22BeforeUpstream End
23BeforeUpper Middle
24BeforeLower Middle
25BeforeDownstream End
26During Construction Upper
27During Construction Lower Middle. Note X-mas
Trees.
28Upper End, Election Day Flood, 11/06
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35(No Transcript)
36(No Transcript)
37From the AirLooking Downstream 11/06
38(No Transcript)
39(No Transcript)
40(No Transcript)
41(No Transcript)
42(No Transcript)
43(No Transcript)
44(No Transcript)
45(No Transcript)
46(No Transcript)
47Note X-mas Trees
48(No Transcript)
49(No Transcript)
50Upper End, November 2006
51Upper End, April 2007
52(No Transcript)
53(No Transcript)
54(No Transcript)
55(No Transcript)
56(No Transcript)
57(No Transcript)
58(No Transcript)
59(No Transcript)
60(No Transcript)
61(No Transcript)
62(No Transcript)
63(No Transcript)
64(No Transcript)
65Project Team
- Pierce County
- Randy Brake, David Renstrom, Dan Wrye, Hans
Hunger, Harold Smelt, Tony Fantello, Tim Ramsaur,
Debby Hyde - Tetra Tech
- Larry Gibbons, Tony Melone, John Herrmann,
Deborah Scheibner - US ACOE
- Laura Orr, Lester Soule, Cathy Desgarden, Beth
Coffey, Michelle Walker, Ron Wilcox, Matt
Bennett, Phillip Hoffman - Key Players
- Russ Ladley, Puyallup Tribe
- Travis Nelson, WDFW
- Clark Davis, James Handmacher, Hylebos Partners
- Brian Abbott, Leslie Ryan-Connelly, IAC
- USFWS, NOAA Fisheries, NOAA Restoration Center
66Lessons Learned
- Multiple benefits made it happen
- Multiple partners
- Persistency
- Manage expectations
- Dont expect reviewers get all they need from
designs - Adaptive management
- Cant sit on laurels
67County-line
Tacoma
Habitat Creation Through Restoring Floodplain
Processesfor Multiple Benefits
White/Puy Confluence
Fennel Creek
Soldiers Home
Dan D. Wrye, Program Services Manager Water
Programs Division (253) 798-4672
dwrye_at_co.pierce.wa.us
Ford
68Ford Setback Levee the 1st
69Orting
Soldiers Home Setback Levee
Ford Setback Levee
70Ford Setback Levee Construction (1997)
71Ford Levee Removal Operation (1997)
72Ford Levee 1998
73Ford levee 2005
Ford Levee 2005
74Puyallup River Ford Setback Levee Looking
Downstream from the South - RM 24.8
751998 detail
762005 detail
77Ford Setback Levee During Election Day Flood of
Nov 2006
78County-line
Tacoma
White/Puy Confluence
Fennel Creek
Soldiers Home
Ford
79(No Transcript)
80Confluence Puyallup, White
81Confluence Puyallup, White
82County Line
83County Line, Whiteacross from Pacific
84County-line, White RiverLooking Downstream,
Upper End
85County-line
Tacoma
Habitat Creation Through Restoring Floodplain
Processesfor Multiple Benefits
White/Puy Confluence
Fennel Creek
Soldiers Home
Dan D. Wrye, Program Services Manager Water
Programs Division (253) 798-4672
dwrye_at_co.pierce.wa.us
Ford